Strategic Land Review Programme Update

Noted Executive 1 paper

AI summaryTrafford Executive approves 2026/27 Strategic Land Disposal Programme and delegates wide authority to the Corporate Director of Place, after a 2025/26 sales total of £3,509,623 (plus further sales subject to contract).

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNoted2026/27 programme and broad delegated powers to Corporate Director of Place
Money£3,509,623 plus STC2025/26 confirmed capital receipts from land sales
What happens nextDisposal and development work in 2026/27 onwardsSites listed in Category 1 and Category 2 to progress
Who it affectsCouncil-owned land across the Borough

What was decided

The Executive noted the 2025/26 Land Sales Programme outcome and approved the 2026/27 Disposal Programme with its earmarked sites. Report P5, P6

The Executive delegated wide authority to the Corporate Director of Place, covering bid negotiation, planning applications, surveys, demolitions, acquisitions, marketing, alternative disposal methods, community engagement and transfers between Categories 1 and 2, including sites valued over £499,999. Report P8, P9

The Executive also delegated authority to the Director of Legal and Governance to finalise and enter into the legal agreements needed to deliver the Disposal Programme for 2025/2026. Report P9

Why

Selling or developing surplus assets cuts Council running costs and backlog maintenance, raises capital receipts for the Capital Programme, and supports regeneration and housing growth, including family housing aligned with corporate priorities. Report 8.1, P13, P14, P15, 8.2

Self-development or partnership delivery is expected to give the Council a greater retained receipt and more control over affordable housing, energy efficiency, carbon reduction and design quality. Report 8.2

What happens next

Continue progressing the Category 1 disposal list of 24 sites, mainly with receipt dates in 2026/27, with further sites to 2027/28 and 2028/29. Report 3.3, 3.5, P41, P42, P43, P44

Take forward the Category 2 development sites (including Partington Town Centre, former Sale Magistrates, Stokoe Avenue Altrincham, former Tamworth Court, Chapel Road, K Site Stretford, Lacy Street land assembly and Oakfield Road/Moss Lane Altrincham) for self-development or joint venture delivery. Report 3.7, P47, P48, P49, P50, P51

Monitor receipt levels through the capital monitoring process and consider any new surplus sites or acquisition opportunities during the year, with acquisitions over £500k requiring Executive approval. Report 4.1, 5.1

The money

  • £1,200,000 Capital receipt from sale of Merry House Report P27
  • £1,800,000 Capital receipt from sale of Kara House Report P27
  • £509,623 Capital receipt from sale of Tamworth, Old Trafford Report P27
  • 3,509,623 (plus STC) Total 2025/26 land sales receipts Report P27
  • 2,124,217 Acquisition price for Kara and Merry House Report P29
  • 150,182 Legal fees and other costs on Kara and Merry acquisition Report P29
  • 2,274,399 Gross acquisition cost of Kara and Merry Report P29
  • 441,339 CAPEX on Kara and Merry funded by TMBC Report P30
  • 3,000,000 Disposal proceeds for Kara and Merry Report P31
  • 75,361 Legal fees and other costs incurred on Kara and Merry disposal Report P31
  • 2,924,639 Net disposal proceeds for Kara and Merry Report P31
  • 208,901 Profit on disposal of Kara and Merry Report P32
  • £499,999 Threshold above which delegated site additions/substitutions require consultation as set out in delegation (g) and (m) Report P9
  • £500k Threshold above which acquisition opportunities require Executive approval Report 4.1

Options considered

  • Chosen: Approve the 2026/27 Disposal Programme with the proposed delegations. Supports Capital Programme funding, reduces holding costs, enables regeneration and housing delivery Report P6, 8.1, 5.1
  • Rejected: Retain surplus property. Would harm Capital Programme resourcing, revenue savings and delivery of Council objectives Report 6.1

Implications

  • Financial: Capital receipts from Category 1 disposals and returns from Category 2 development are earmarked to support the Capital Programme, with levels reported through capital monitoring and tied to the Capital Strategy Report 2026 to 2029. Report P17, 5.1
  • Legal: Each disposal and development will be reviewed for legal implications individually, and the Director of Legal and Governance is authorised to finalise the required agreements. Report P18, P9
  • Equalities: The report records no equality or diversity implications arising from it. Report P19
  • Climate: Capital receipts generated are expected to support capital schemes that contribute to the Council's carbon neutrality objectives. Report P19
  • Risk: Risks relate to holding vacant property and to development risk on self-development and joint venture sites; a risk register and risk management process will be maintained for each development. Report P20
  • Staffing: Existing resources have been identified to support delivery of the land sales programme. Report P20

Who and where

  • Council-owned land and property portfolio across the Borough Report 1.1, 1.2
  • Residents of Kara House and Merry House, who have been moved to other locations during a managed transition Report 2.2
  • Local stakeholders in areas affected by major disposals, subject to consultation Report 7.1
  • Developers and purchasers approached to bid on listed sites Report P8, P9
  • Partners such as affordable housing providers identified through service area consultation Report 7.1

Timeline

  • 12th January 2026: Cut-off date used in the report for 2025/26 sales progress Report 2.1
  • 2025/2026: Receipts expected from Altrincham Town Hall and former Tamworth Court (Category 1 item 6 and Category 2 item 4) and Chapel Road (Category 2 item 5) Report P43, P49, P50
  • 2026/2027: Expected receipt year for most Category 1 sites listed (including Former RBS Bank Partington, Stamford Quarter and Stretford Mall, former Altrincham Library, Jubilee Centre Bowdon, Wharf Road Garages, Land at Balmoral Rd, Central Way, Brown Street Car Park, Land at Irlam Road Flixton, Land at Lime Road Stretford, former Trafford High School, former Davyhulme Youth Centre, Land at Firsway Sale) and for Category 2 sites 1 to 3, 6 and 8 Report P41, P42, P43, P44, P47, P48, P51
  • 2027/2028: Expected receipt year for Land at Seymour Grove Old Trafford, former Moss View Primary School Partington, and the Lacy Street land assembly Report P44, P50
  • 2028/2029: Expected receipt year for Land in Davenport Green (PfE allocation) Report P44
  • During 2026/27 programme: Period for progressing the programme, with receipts possibly phased or deferred into later years Report 3.3, 3.4

Plain English for the jargon

  • Category 1 disposals: Sites already committed for disposal or disposed of on a statutory basis, or where the Council has assessed no development potential or benefit in direct development.
  • Category 2 development sites: Property assets where partnership, joint venture or self-development is considered to give significant advantage, often requiring enabling works.
  • STC: Subject to contract, used in the report where a sale has been agreed but not yet completed.
  • CAPEX: Capital expenditure, used in the Kara and Merry House financial analysis.
  • Residual proceeds: Net money left to the Council from a disposal after deducting acquisition, capital and disposal costs, as shown in the Kara and Merry House analysis.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item10

Resolved

1) That the outcome of the 2025/26 Land Sales Programme, be noted. 2) That the Disposal Programme for 2026/27 as set out in the report, be approved, and the sites that have been earmarked for disposal / development, be noted. 3) That the Corporate Director of Place, be delegated authority to: a. Negotiate and accept bids in consultation with the Director of Finance and Systems and the Director of Legal and Governance for all sites listed on the Disposal Programme. b. Engage external resources where this will assist in implementing the programme, including a professional team where reasonably required to support a development project. c. Commission, submit and / or authorise as appropriate: i. Any applications for planning permission on any properties included in the programme where this will assist in marketing and/or add value, or in any case where the Council is proposing to redevelop the site whether directly or in partnership with another party. ii. Any surveys/investigations where such surveys will reduce the risks associated with redevelopment, add value to the capital receipt /revenue return and/or assist with the preparation, submission and resolution of any planning permission application, or any other usual pre-development survey or investigation. iii. Any feasibility study or design for the site and or premises in association with either obtaining a planning consent or as part of options appraisal. iv. Any demolitions or physical alterations that will either reduce the risks associated with holding the premises or accelerate the sale/redevelopment and/or add value to the capital receipt/revenue return. d. Offset eligible disposal costs against capital receipts in accordance with capital regulations. e. Advertise the intention to dispose of a site in the event that it comprises open space as defined by the Town and Country Planning Act 1990, in accordance with the relevant statutory procedure, and if any objections are received, to refer to the relevant portfolio holder for consideration in consultation with the Executive Member for Environment and Regulatory Services. f. Acquire adjacent land or property where the acquisition will either add value to the overall development or de-risk the disposal/development of the Council asset. g. Delegate authority to the Corporate Director of Place, in consultation with the Executive Member for Housing and Regeneration and the Director of Finance and Systems, to add or substitute sites into the programme during the year including sites with a value of over £499,999. h. Transfer sites from Category 1 to Category 2 and vice versa. i . Commission security services. j. Authorise alternative methods of disposal where appropriate. k. Authorise community engagement and consultation where the Corporate Director of Place deems it necessary or advantageous. l. In relation to any site currently in development or any site which commences development during this programme, agree any licence or approve the grant of any easement or lease or any other disposal, including where that disposal taken in isolation would constitute a disposal at undervalue, which is designed or intended to implement or facilitate the development. m. Authorise marketing, pricing ...
Word for word from the decision Trafford published for this meeting. Source: democratic.trafford.gov.uk

Follow this further

Built from Trafford's papers

What the report saysPro

Report to Executive

Summary

To report to Members the progress update of the 2025/26 Land Sales Programme.

To approve the Land Sales Programme for 2026/27 including assets, asset transfers that are ongoing and to be brought forward for disposal in future financial years.

Recommendation(s)

The Executive are recommended to:

1.Note the outcome of the 2025/26 Land Sales Programme.

2. Approve the Disposal Programme for 2026/27 as set out in the report and note the sites that have been earmarked for disposal/development.

3.Delegate authority to the Corporate Director of Place to:

a. Negotiate and accept bids in consultation with the Director of Finance and Systems and the Director of Legal and Governance for all sites listed on the Disposal Programme. b. Engage external resources where this will assist in implementing the programme, including a professional team where reasonably required to support a development project. c. Commission, submit and/or authorise as appropriate: i) any applications for planning permission on any properties included in the programme where this will assist in marketing and/or add value, or in any case where the Council is proposing to redevelop the site whether directly or in partnership with another party. ii) any surveys/investigations where such surveys will reduce the risks associated with redevelopment, add value to the capital receipt /revenue return and/or assist with the preparation, submission and resolution of any planning permission application, or any other usual pre-development survey or investigation. iii) any feasibility study or design for the site and or premises in association with either obtaining a planning consent or as part of options appraisal. iv) any demolitions or physical alterations that will either reduce the risks associated with holding the premises or accelerate the sale/redevelopment and/or add value to the capital receipt/revenue return.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Strategic Land Review Programme UpdateReport 233 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 12 attended
TR
Councillor Tom RossChair, present
LP
Councillor Liz PatelDeputy Leader, present
SA
Councillor Stephen AdsheadCommittee Member, present
KC
Councillor Karina CarterCommittee Member, present
GD
Councillor George DevlinCommittee Member, present
JH
Councillor Joanne HardingCommittee Member, present
EP
Councillor Eve ParkerCommittee Member, present
JS
Councillor Jane SlaterCommittee Member, present
RT
Councillor Rose ThompsonCommittee Member, present
AW
Councillor Aidan WilliamsCommittee Member, present
JA
John AddisonDemocratic Services Officer, expected
MD
Martin DillonOfficer, expected

On this subject at Trafford

Search all
  1. Strategic Land Review Programme UpdateThis decision
  2. Strategic Land Review Programme UpdateNoted
  3. Strategic land review land programme update - part 1Noted
  4. Strategic land review programme 2022 - 2023 - part iNoted
  5. Strategic land review programme 2021-2024 - part iNoted
  6. Strategic Land Review Programme 2020/23Approved

More from Trafford Executive

All decisions
MeetingDecisionOutcome
21 Sep 2026 Greater Manchester End to End Fostering Recruitment Hub1) That the national and Greater Manchester context supporting the developments of the Greater Manchester End-to-End ... Approved Open
21 Sep 2026 Sale Waterside Private Finance Initiative Exit1) That the hand back of the Sale Waterside PFI assets to Council ownership on expiry of the PFI contract on 28 th Oc... Approved Open
20 Jul 2026 Wharfside Strategic MasterplanThat the Executive: (i) Approves the draft Trafford for consultation. (ii) (ii) Delegates authority to the Corporate ... Approved Open
20 Jul 2026 Local Plan Regulation 19 Consultation ApprovalThat the Executive: (i) Approves the Trafford Local Plan (Publication Version) 2026, including allocations, designati... Approved Open
15 Jun 2026 Trafford Good Growth Plan 2026/27(1) That the progress achieved against the actions contained in the Inclusive Economy and Delivery Plan, be noted. (2... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies