AI summaryTrafford Executive approves updated development strategy for Stretford Phases 2A and 2B, with Homes England and possible GMCA patient equity funding.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedUpdated strategy and programme for Stretford Plots 2A and 2B
Money£1.8 millionExisting IMB-approved budget, £0.9m per shareholder, within budget
What happens nextMarch 2026Phase 2A reserved matters application to be submitted
Who it affectsStretford Town CentreUp to 426 new homes across Phases 2A and 2B
What was decided
The Executive approved the updated development strategy and programme for Stretford Plot 2A and 2B, with the JV to seek affordable housing funding through the Homes England Social and Affordable Housing Programme and submit a viability assessment to the Local Planning Authority. Report P3, P53, 4.1
The JV may make separate reserved matters submissions for open market and affordable housing elements to maximise external funding, and may pursue equity investment from GMCA through the Patient Equity Programme as an alternative to grant or direct JV equity. Report P4, P5, P54, P55
The JV will develop a bespoke funding and development package responding to negotiations with GMCA around Patient Equity and other funding sources, with the detailed strategy to be presented to the Investment Management Board for approval. Report P6, 4.2, 5.2
Why
The Council is committed to delivering the whole Stretford Masterplan in a policy compliant way, and the 2024 approval framework allows ongoing review of the scheme, the economic outlook and funding landscapes to protect the Council's investment. Report 1.6, 3.1, P1
GMCA funding for brownfield schemes like Stretford has shifted from straightforward gap funding to a patient equity model, which is currently a more attractive model than the alternative forward funded approach. Report 3.3, 3.4, P49
Homes England launched a new Investment Strategy in early 2026 aimed at social housing, and Registered Providers prefer discrete affordable blocks for operational efficiency. Report 3.5, 3.6
What happens next
Submit Phase 2A reserved matters application in March 2026 and pursue the Plot 2A Patient Equity funding agreement by April 2026, with mall demolition from April to December 2026. Report P41, 2.5
Finalise the detailed development and funding strategy, including a viability assessment, and present it to the Investment Management Board alongside an Equality Impact Assessment. Report 4.2, 5.2, P13
Review the existing JV agreement with Bruntwood and negotiate a deed of variation or supplemental agreement if needed, with authority delegated to the Corporate Director of Place in consultation with the Executive Member for Economy and Regeneration and the Director of Legal and Governance. Report P61
The money
£1.8 million IMB-approved budget to progress Stage 2 for Stretford Phase 2A and 2B, £0.9 million per shareholder Report 5.1
Options considered
Rejected: Continue within the existing JV Residential parameters approved in June 2024. Not responding to current market conditions and unlikely to result in delivery of new homes Report P66, P67
Chosen: Updated development strategy with Homes England grant funding, separate reserved matters submissions and GMCA patient equity options. Responds to changed funding landscape and protects Council investment while maximising external funding leverage Report P3, P4, P5, P6, 3.1, 3.3
Implications
Legal: The JV agreement with Bruntwood may need a deed of variation; a subsidy control assessment is required under the Subsidy Control Act 2022 for any GMCA patient equity or Homes England grant; the Procurement Act 2023 must be reviewed for new funding partners. Report P61, P62, P63
Legal: Members deciding this matter should not sit on the Planning Committee for related applications, as the Council is both JV partner and Local Planning Authority, and information barriers must be maintained between regeneration and planning teams. Report P64, P65
Risk: Removing the requirement for a forward funder to sign before planning means the Council (through the JV) may carry development risk for longer; the Section 151 Officer should confirm satisfaction with the revised risk profile and the IMB will continue gateway approvals. Report P64, P15
Equalities: An Equality Impact Assessment will be undertaken as the development and funding strategy is finalised, to assess impact on access to affordable housing for protected groups, and presented to the Investment Management Board. Report P13
Financial: Any additional funding required will be considered by the Investment Management Board alongside the development and funding strategy; delivery of the scheme is expected to generate a return to the Trafford/Bruntwood JV. Report 5.2, P18
Climate: A carbon assessment will be commissioned for both design and construction; the scheme will use passive design measures, low energy building services and supplementary renewable technology where required. Report P10, P14
Staffing: Existing resources have been identified to support delivery, with external professional support brought in where needed and factored into project costs. Report P14
The Bruntwood/Trafford Joint Venture and the Council as JV partner Report 1.1, 1.2
Greater Manchester Combined Authority as potential Patient Equity investor Report P5, 3.3
Homes England as provider of Social and Affordable Housing Programme grant funding Report P3, 3.5
Registered Providers and future operators of the affordable housing blocks Report P25, 3.6
Stretford Town Centre businesses and visitors during the mall demolition period April to December 2026 Report P41, 2.1, 2.3
Timeline
June 2024: Executive agreed principle of new Residential JV arrangement with Bruntwood across three sites, with Stretford Phases 2A and 2B as initial priority Report 1.1, 1.3, 1.4
October 2025: Public opening of restored King Street and new Sir Tony Lloyd Square as first phase of Stretford Town Centre regeneration Report 2.1, 2.2
End of 2025: Public consultation undertaken by CERT for Residential Phase 1 Report 2.4
January 2026: Two floors of the refurbished multi-storey car park opened Report 2.3
Early 2026: Homes England launched new Investment Strategy, with initial bids considered in March 2026 Report 3.5
March 2026: Phase 2A and public realm reserved matters applications to be submitted; Homes England initial bids considered Report P41, 2.5, 3.5
April 2026: Appointment of building contractor for detailed design and confirmation of Plot 2A Patient Equity funding agreement Report P41
April to December 2026: Mall demolition Report P41
July 2027: Start on site for Phase 2A Report P41
November 2029: Indicative scheme completion Report P41
Plain English for the jargon
JV: Joint Venture, in this case between Trafford Council and Bruntwood for residential development
Patient Equity: A funding model where GMCA takes an equity stake in a scheme and recycles funds into future schemes, rather than providing straightforward gap funding
Reserved matters application: A planning application that submits detailed proposals against an existing outline planning permission
Forward funder: An investor, such as a Registered Provider or pension fund, that provides funding for a scheme, signing prior to planning being granted under the original 2024 model
IMB: Investment Management Board, the Trafford body that oversees the Asset Investment Strategy and provides gateway approval for JV projects
RIBA Stage 2: Concept design stage of the Royal Institute of British Architects' work stages; Stage 3 is spatial coordination
AIS: Asset Investment Strategy, the source of the Council's share of funding for the JV
LPA: Local Planning Authority, the body responsible for determining planning applications
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item8
Resolved
(1) That the updated development strategy and programme for Stretford Plot 2A and 2B, be approved and that the Joint Venture (JV) will seek to secure the funding for affordable housing through the Homes England Social and Affordable Housing Programme and submit a viability assessment to the Local Planning Authority. (2) That the JV may consider separate submissions for Open Market, and Affordable Housing elements of each scheme if this maximises the opportunity to leverage external (private and public) funding. (3) That the JV may consider equity investment by Public Sector partners, specifically Greater Manchester Combined Authority (GMCA) through the Patient Equity Programme and that this may be as an alternative to grant funding or to the JV providing direct equity funding. (4) That the JV will consider a bespoke funding and development package that responds to negotiations with GMCA around Patient Equity and other potential funding sources.
Word for word from the decision Trafford published for this meeting.Source: democratic.trafford.gov.uk
This report provides an update on progress on the creation of a Residential JV with Bruntwood and the Council’s commitment to the delivery of the entire Stretford Masterplan in a policy compliant way, in the context of the latest market position and funding availability.
Recommendation(s)
The Executive is recommended to: a) Approve the updated development strategy and programme for Stretford Plot 2A and 2B. That the JV will seek to secure the funding for affordable housing through the Homes England Social and Affordable Housing Programme and submit a viability assessment to the LPA.
b) The JV may consider separate submissions for Open Market, and Affordable Housing elements of each scheme if this maximises the opportunity to leverage external (private and public) funding.
c) The JV may consider equity investment by Public Sector partners, specifically GMCA through the Patient Equity Programme. This may be as an alternative to grant funding or to the JV providing direct equity funding.
d) The JV will consider a bespoke funding and development package that responds to negotiations with GMCA around Patient Equity and other potential funding sources. Contact person for access to background papers and further information:
Name: Richard Roe Background Papers: None CORPORATE PRIORITIES AND GOVERNANCE CONSIDERATIONS The Best Start for our Children and The decision supports the delivery of quality new Young People family housing.
Healthy and Independent Lives for The decision supports the delivery of quality new Everyone family housing.
A Thriving Economy and Homes The decision supports the delivery of quality new for All family housing.
Address the Climate Crisis A carbon assessment will be commissioned for both Design and Construction of the proposed development.
Culture, Sport and Heritage for N/a Everyone Relationship to GM Policy or The proposed development will provide High Strategy Framework quality housing. Delivery of the Scheme will support the growth ambitions articulated within the emerging Greater Manchester Spatial Framework and the GM Strategy. Financial Considerations As set out in the financial section.
Legal Implications: As set out in the legal section.
Equality/Diversity Implications The proposals in this report include decisions about the mechanism for delivering affordable housing, including the possibility that affordable housing will not be secured through a Section 106 planning obligation but will instead be funded separately through the Homes England Social and Affordable Housing Programme. These decisions engage the Public Sector Equality Duty under Section 149 of the Equality Act 2010, which requires the Council to have due regard to the need to advance equality of opportunity and, in particular, to the needs of persons who share a relevant protected characteristic and who may be disadvantaged by reason of socioeconomic inequality. An Equality Impact Assessment will be undertaken as the development and funding strategy is finalised to assess the impact of the proposals on access to affordable housing for protected groups. The assessment will be presented to the Investment Management Board alongside the detailed development and funding strategy.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Trafford Good Growth Plan 2026/27(1) That the progress achieved against the actions contained in the Inclusive Economy and Delivery Plan, be noted. (2...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.