CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Trafford Metropolitan Borough Council
Executive, Monday 16 March 2026 at 6.30pm

Stretford Mall and Residential JV Update

Approved Executive 1 paper

AI summaryTrafford Executive approves updated development strategy for Stretford Phases 2A and 2B, with Homes England and possible GMCA patient equity funding.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedUpdated strategy and programme for Stretford Plots 2A and 2B
Money£1.8 millionExisting IMB-approved budget, £0.9m per shareholder, within budget
What happens nextMarch 2026Phase 2A reserved matters application to be submitted
Who it affectsStretford Town CentreUp to 426 new homes across Phases 2A and 2B

What was decided

The Executive approved the updated development strategy and programme for Stretford Plot 2A and 2B, with the JV to seek affordable housing funding through the Homes England Social and Affordable Housing Programme and submit a viability assessment to the Local Planning Authority. Report P3, P53, 4.1

The JV may make separate reserved matters submissions for open market and affordable housing elements to maximise external funding, and may pursue equity investment from GMCA through the Patient Equity Programme as an alternative to grant or direct JV equity. Report P4, P5, P54, P55

The JV will develop a bespoke funding and development package responding to negotiations with GMCA around Patient Equity and other funding sources, with the detailed strategy to be presented to the Investment Management Board for approval. Report P6, 4.2, 5.2

Why

The Council is committed to delivering the whole Stretford Masterplan in a policy compliant way, and the 2024 approval framework allows ongoing review of the scheme, the economic outlook and funding landscapes to protect the Council's investment. Report 1.6, 3.1, P1

GMCA funding for brownfield schemes like Stretford has shifted from straightforward gap funding to a patient equity model, which is currently a more attractive model than the alternative forward funded approach. Report 3.3, 3.4, P49

Homes England launched a new Investment Strategy in early 2026 aimed at social housing, and Registered Providers prefer discrete affordable blocks for operational efficiency. Report 3.5, 3.6

What happens next

Submit Phase 2A reserved matters application in March 2026 and pursue the Plot 2A Patient Equity funding agreement by April 2026, with mall demolition from April to December 2026. Report P41, 2.5

Finalise the detailed development and funding strategy, including a viability assessment, and present it to the Investment Management Board alongside an Equality Impact Assessment. Report 4.2, 5.2, P13

Review the existing JV agreement with Bruntwood and negotiate a deed of variation or supplemental agreement if needed, with authority delegated to the Corporate Director of Place in consultation with the Executive Member for Economy and Regeneration and the Director of Legal and Governance. Report P61

The money

  • £1.8 million IMB-approved budget to progress Stage 2 for Stretford Phase 2A and 2B, £0.9 million per shareholder Report 5.1

Options considered

  • Rejected: Continue within the existing JV Residential parameters approved in June 2024. Not responding to current market conditions and unlikely to result in delivery of new homes Report P66, P67
  • Chosen: Updated development strategy with Homes England grant funding, separate reserved matters submissions and GMCA patient equity options. Responds to changed funding landscape and protects Council investment while maximising external funding leverage Report P3, P4, P5, P6, 3.1, 3.3

Implications

  • Legal: The JV agreement with Bruntwood may need a deed of variation; a subsidy control assessment is required under the Subsidy Control Act 2022 for any GMCA patient equity or Homes England grant; the Procurement Act 2023 must be reviewed for new funding partners. Report P61, P62, P63
  • Legal: Members deciding this matter should not sit on the Planning Committee for related applications, as the Council is both JV partner and Local Planning Authority, and information barriers must be maintained between regeneration and planning teams. Report P64, P65
  • Risk: Removing the requirement for a forward funder to sign before planning means the Council (through the JV) may carry development risk for longer; the Section 151 Officer should confirm satisfaction with the revised risk profile and the IMB will continue gateway approvals. Report P64, P15
  • Equalities: An Equality Impact Assessment will be undertaken as the development and funding strategy is finalised, to assess impact on access to affordable housing for protected groups, and presented to the Investment Management Board. Report P13
  • Financial: Any additional funding required will be considered by the Investment Management Board alongside the development and funding strategy; delivery of the scheme is expected to generate a return to the Trafford/Bruntwood JV. Report 5.2, P18
  • Climate: A carbon assessment will be commissioned for both design and construction; the scheme will use passive design measures, low energy building services and supplementary renewable technology where required. Report P10, P14
  • Staffing: Existing resources have been identified to support delivery, with external professional support brought in where needed and factored into project costs. Report P14

Who and where

  • Future residents of Stretford Phase 2A (248 market rent units: 120 one-bed, 114 two-bed, 14 three-bed) and Phase 2B (178 affordable units: 89 one-bed, 89 two-bed) Report P40, 1.4
  • The Bruntwood/Trafford Joint Venture and the Council as JV partner Report 1.1, 1.2
  • Greater Manchester Combined Authority as potential Patient Equity investor Report P5, 3.3
  • Homes England as provider of Social and Affordable Housing Programme grant funding Report P3, 3.5
  • Registered Providers and future operators of the affordable housing blocks Report P25, 3.6
  • Stretford Town Centre businesses and visitors during the mall demolition period April to December 2026 Report P41, 2.1, 2.3

Timeline

  • June 2024: Executive agreed principle of new Residential JV arrangement with Bruntwood across three sites, with Stretford Phases 2A and 2B as initial priority Report 1.1, 1.3, 1.4
  • October 2025: Public opening of restored King Street and new Sir Tony Lloyd Square as first phase of Stretford Town Centre regeneration Report 2.1, 2.2
  • End of 2025: Public consultation undertaken by CERT for Residential Phase 1 Report 2.4
  • January 2026: Two floors of the refurbished multi-storey car park opened Report 2.3
  • Early 2026: Homes England launched new Investment Strategy, with initial bids considered in March 2026 Report 3.5
  • March 2026: Phase 2A and public realm reserved matters applications to be submitted; Homes England initial bids considered Report P41, 2.5, 3.5
  • April 2026: Appointment of building contractor for detailed design and confirmation of Plot 2A Patient Equity funding agreement Report P41
  • April to December 2026: Mall demolition Report P41
  • July 2027: Start on site for Phase 2A Report P41
  • November 2029: Indicative scheme completion Report P41

Plain English for the jargon

  • JV: Joint Venture, in this case between Trafford Council and Bruntwood for residential development
  • Patient Equity: A funding model where GMCA takes an equity stake in a scheme and recycles funds into future schemes, rather than providing straightforward gap funding
  • Reserved matters application: A planning application that submits detailed proposals against an existing outline planning permission
  • Forward funder: An investor, such as a Registered Provider or pension fund, that provides funding for a scheme, signing prior to planning being granted under the original 2024 model
  • IMB: Investment Management Board, the Trafford body that oversees the Asset Investment Strategy and provides gateway approval for JV projects
  • RIBA Stage 2: Concept design stage of the Royal Institute of British Architects' work stages; Stage 3 is spatial coordination
  • AIS: Asset Investment Strategy, the source of the Council's share of funding for the JV
  • LPA: Local Planning Authority, the body responsible for determining planning applications
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item8

Resolved

(1) That the updated development strategy and programme for Stretford Plot 2A and 2B, be approved and that the Joint Venture (JV) will seek to secure the funding for affordable housing through the Homes England Social and Affordable Housing Programme and submit a viability assessment to the Local Planning Authority. (2) That the JV may consider separate submissions for Open Market, and Affordable Housing elements of each scheme if this maximises the opportunity to leverage external (private and public) funding. (3) That the JV may consider equity investment by Public Sector partners, specifically Greater Manchester Combined Authority (GMCA) through the Patient Equity Programme and that this may be as an alternative to grant funding or to the JV providing direct equity funding. (4) That the JV will consider a bespoke funding and development package that responds to negotiations with GMCA around Patient Equity and other potential funding sources.
Word for word from the decision Trafford published for this meeting. Source: democratic.trafford.gov.uk

Follow this further

Built from Trafford's papers

What the report saysPro

Report to Executive

Summary

This report provides an update on progress on the creation of a Residential JV with Bruntwood and the Council’s commitment to the delivery of the entire Stretford Masterplan in a policy compliant way, in the context of the latest market position and funding availability.

Recommendation(s)

The Executive is recommended to: a) Approve the updated development strategy and programme for Stretford Plot 2A and 2B. That the JV will seek to secure the funding for affordable housing through the Homes England Social and Affordable Housing Programme and submit a viability assessment to the LPA.

b) The JV may consider separate submissions for Open Market, and Affordable Housing elements of each scheme if this maximises the opportunity to leverage external (private and public) funding.

c) The JV may consider equity investment by Public Sector partners, specifically GMCA through the Patient Equity Programme. This may be as an alternative to grant funding or to the JV providing direct equity funding.

d) The JV will consider a bespoke funding and development package that responds to negotiations with GMCA around Patient Equity and other potential funding sources. Contact person for access to background papers and further information:

Name: Richard Roe Background Papers: None CORPORATE PRIORITIES AND GOVERNANCE CONSIDERATIONS The Best Start for our Children and The decision supports the delivery of quality new Young People family housing.

Healthy and Independent Lives for The decision supports the delivery of quality new Everyone family housing.

A Thriving Economy and Homes The decision supports the delivery of quality new for All family housing.

Address the Climate Crisis A carbon assessment will be commissioned for both Design and Construction of the proposed development.

Culture, Sport and Heritage for N/a Everyone Relationship to GM Policy or The proposed development will provide High Strategy Framework quality housing. Delivery of the Scheme will support the growth ambitions articulated within the emerging Greater Manchester Spatial Framework and the GM Strategy. Financial Considerations As set out in the financial section.

Legal Implications: As set out in the legal section.

Equality/Diversity Implications The proposals in this report include decisions about the mechanism for delivering affordable housing, including the possibility that affordable housing will not be secured through a Section 106 planning obligation but will instead be funded separately through the Homes England Social and Affordable Housing Programme. These decisions engage the Public Sector Equality Duty under Section 149 of the Equality Act 2010, which requires the Council to have due regard to the need to advance equality of opportunity and, in particular, to the needs of persons who share a relevant protected characteristic and who may be disadvantaged by reason of socioeconomic inequality. An Equality Impact Assessment will be undertaken as the development and funding strategy is finalised to assess the impact of the proposals on access to affordable housing for protected groups. The assessment will be presented to the Investment Management Board alongside the detailed development and funding strategy.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Stretford Mall and Residential JV UpdateReport 292 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 12 attended
TR
Councillor Tom RossChair, present
LP
Councillor Liz PatelDeputy Leader, present
SA
Councillor Stephen AdsheadCommittee Member, present
KC
Councillor Karina CarterCommittee Member, present
GD
Councillor George DevlinCommittee Member, present
JH
Councillor Joanne HardingCommittee Member, present
EP
Councillor Eve ParkerCommittee Member, present
JS
Councillor Jane SlaterCommittee Member, present
RT
Councillor Rose ThompsonCommittee Member, present
AW
Councillor Aidan WilliamsCommittee Member, present
JA
John AddisonDemocratic Services Officer, expected
MD
Martin DillonOfficer, expected

On this subject at Trafford

Search all
  1. Stretford Mall and Residential JV UpdateThis decision
  2. Application for planning permission 119112/ful/26 - stretford square, stretford shopping mall, chester road, stretfordDecided
  3. Application for planning permission 112534/var/23 - land at stretford mall and lacy street, chester road, stretfordDeferred
  4. Stamford quarter and stretford mall lease reviewsApproved
  5. Application for planning permission 103844/hyb/21 - land at stretford mall and lacy street, chester road, stretfordDeferred
  6. Application for the grant of a new premises licence under s17 licensing act 2003 at the up top, 4th floor, mscp, stretford mall, kingsway, stretford, m32 9bdApproved

More from Trafford Executive

All decisions
MeetingDecisionOutcome
21 Sep 2026 Greater Manchester End to End Fostering Recruitment Hub1) That the national and Greater Manchester context supporting the developments of the Greater Manchester End-to-End ... Approved Open
21 Sep 2026 Sale Waterside Private Finance Initiative Exit1) That the hand back of the Sale Waterside PFI assets to Council ownership on expiry of the PFI contract on 28 th Oc... Approved Open
20 Jul 2026 Wharfside Strategic MasterplanThat the Executive: (i) Approves the draft Trafford for consultation. (ii) (ii) Delegates authority to the Corporate ... Approved Open
20 Jul 2026 Local Plan Regulation 19 Consultation ApprovalThat the Executive: (i) Approves the Trafford Local Plan (Publication Version) 2026, including allocations, designati... Approved Open
15 Jun 2026 Trafford Good Growth Plan 2026/27(1) That the progress achieved against the actions contained in the Inclusive Economy and Delivery Plan, be noted. (2... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies