DECISION MADE: 1. That an Exception to CPR 21 be approved to grant permission to extend the existing contract for 6 months to allow sufficient time for the full OJEU tender process to be completed; and 2. That authority be granted to seek tenders for the cleaning of the Council’s building portfolio in accordance with Council procurement procedures and EU regulations for a contract period of 5 years with the provision for two 12 month extensions. REASONS FOR DECISION: To ensure the Council can achieve the most economic cleaning solution for the Council’s building portfolio. Contact Officer: Andy Cole – Head Of Customer Access, Transformation And Delivery Tel: 01892 526121 Ext 3254 or e-mail: [email protected]
Word for word from the decision Tunbridge Wells published for this meeting.Source: democracy.tunbridgewells.gov.uk
The Council currently runs a number of separate cleaning contracts and in order to comply with EU regulations and to achieve the most economic cleaning solution it is proposed to procure one contract, with options for separate packaged lots. This will ensure the maximum number of contractors of various sizes have the opportunity to tender and provide the Council with the most economic cleaning solution.
The current cleaning contract for the main Civic Buildings expired on 31March 2011 without provision to extend. It is proposed that an exception to the Council’s procurement procedures is approved and the existing contract extended to allow sufficient time for the full tender process to be undertaken.
Corporate Priorities
The report supports corporate priorities by providing value for money. Cleaning forms a vital part of the Councils provision of work place.
Report Status
The report is for decision
Route to Implementation/Timetable:
If agreed the existing contract will be extended until end September 2011 and procurement of all Cleaning through the full OJEU notice procedure will be tendered for start October 2011.
110421/CAB004 10B - 2
Background/Introduction
1. The existing Civic Buildings cleaning contract was procured in 2007 and expired on the 31 March 2011. The contract contained no provision for options to extend beyond this date.
2. To procure a contract of this value a full EU tendering procedure is required. In order to have sufficient time to take a more proactive approach to obtain best value from a new cleaning contract procurement process, and to maintain current cleaning standards, a short term, interim contract is required.
3. Under the Council’s procurement procedures, short term contracts in excess of £50,000 require tenders to be sought from 4 contractors. After consideration of letting a short term cleaning contract, it was concluded that with the current contractor having ownership of cleaning equipment and the implications of TUPE legislation, only the existing contractor would be in a position to provide a competitive price.
4. The extension of the existing contract will allow time for a restructure and rationalisation of all the current cleaning contracts operated by the Council. It will provide an opportunity to examine the potential for aggregating existing cleaning contracts, negotiate flexibility within the contract timescale and deliver best value for the council.
5. It is proposed that the Council works in partnership with its Mid Kent Improvement partners to manage and implement the procurement process.
Cross cutting issues
Legal 6. There is provision in the Constitution to waive the procurement rules in certain circumstances of which this would qualify under Exception to CPR 21.2
Finance and other resources, including ICT 7. Proposals offer best value for the council
Staffing 8. No additional staffing will be required to manage the new contract although some movement of staff resource may be required. The procurement process is being managed with the assistance of Maidstone Borough Council’s Procurement department.
Value for money 9. The proposal will market test and offer value for money
Risk Management 10. Cleaning of the buildings is paramount to offer safe environments for staff and members to conduct the council’s business.
110421/CAB004 10B - 3
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Capital Management Report Quarter 1RESOLVED – 1. That the actual gross expenditure and that net of revenue for the year and the sources of finance, as s...
Revenue Management Report Quarter 1RESOLVED – 1. That the Quarter 1 net expenditure on services to the end of June 2026 was £5,414,000, £102,000 less th...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.