Resolved
RESOLVED : That the Economy and Governance Select Committee give their full backing to the proposals, financial detail and bid timetable, to be submitted to Cabinet on 16 June.
Economy and Governance Overview & Scrutiny Select Committee decided this item on Tuesday 7 June 2011. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED : That the Economy and Governance Select Committee give their full backing to the proposals, financial detail and bid timetable, to be submitted to Cabinet on 16 June.
The Grosvenor and Hilbert Park renovation and enhancement programme is one of the key projects identified in the Council’s Strategic Plan.
The redevelopment of the Council’s old Medway depot site at the northern end of Quarry Road in Royal Tunbridge Wells and a subsequent Planning Section106 (S106) agreement has provided £340,000 to refurbish and enhance the adjacent Grosvenor and Hilbert Park.
This funding, whilst significant, would not allow the refurbishment of the whole site thus ensuring that there was a significant impact on not just the immediate locality but the wider area. As such a Heritage Lottery Fund (HLF) Bid is being developed for submission in August 2011 to maximise the funding and the impact of the initial monies from the S106, and seeks to secure a further £1,518,000 for the 5 year project.
This report contains a summary of the progress with the bid, the route to it being finalised, and a summary of the improvements proposed. Cabinet will be requested to endorse this bid and delegate the authority to final changes that may be required (from the consultation exercises) to the Portfolio Holder for Tourism, Leisure and Economic Development.
Corporate Priorities
The submission of a HLF bid will contribute to the corporate priorities as summarised below:
Value The existing funds will be greatly enhanced if the bid is successful therefore maximising the impact of the existing resources secured.
Community The community particularly in the wards specified above will benefit from better facilities and a range of activities and events that will enhance community cohesion. Customers Our customers will have a greatly enhanced service if the bid succeeds. The process has and will continue to involve significant consultation.
People Staff motivation within the service particularly as they are able to provide enhanced services and facilities. The bid included proposals for apprenticeships (via our contractor) and other developmental opportunities
Report status
For Decision
Route to Implementation/Timetable:
This report is being discussed at the Economy & Governance Select Committee on 9 June to enable any comments or recommendations to be considered by Cabinet. The bid to the Heritage Lottery Fund will be submitted by 18 August 2011. Future progress will be dependant on the outcome of this bid and a second round of bidding in 2012, with a view to works commencing in September 2012. The work programme leading to the submission of the bid is shown in Appendix A. Report of the Director of Regeneration and Sustainability
1. Background/Progress to date
1.1The bid process was initiated by TWBC hosting a training session for the HLF where their representatives held a number of sessions. After this Officers from the Council and from the HLF met to discuss the initial feasibility of a bid.
1.2HLF Officers gave very positive feedback from this initial meeting and encouraged a formal bid to be made in due course. They commented that this was a very well prepared proposal for the initial stage.
1.3An audit of the park was undertaken to establish how the park stood in terms of the national standard for parks, namely the Green Flag Award. From this it was clear that the park would not pass at this stage. The gap analysis showed that the injection of funding from s106 on its own would not suffice to bring the site up to this recognised standard.
1.4The specific S106s that have been utilised for our match funding for this bid are:
£39,674 already paid following the completion of the residential blocks on the Medway Depot development.
£250,000 payable on the occupation of the first flat at the Medway Depot development.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Heritage Lottery Fund BidReport | 156 KB | DownloadRead as text |
Follow Economy and Governance Overview & Scrutiny Select Committee at Tunbridge Wells and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 2 May 2012 | Local Authority Mortgage Scheme - Call-in of Cabinet Decision CAB202/11RESOLVED that: The decision be referred to the Cabinet for further consideration for the following reasons: a) Financ... | Decided | Open |
| 3 Apr 2012 | Minutes of Previous MeetingThat the minutes of the Economy and Governance Select Committee meeting, dated 7 February 2012, be confirmed as a cor... | Decided | Open |
| 3 Apr 2012 | Public Realm ReviewThat: 1. The Committee agrees and approves the principles and recommendations set out in the report under the ‘local ... | Agreed | Open |
| 3 Apr 2012 | Update from Supporting Local Businesses Task and Finish GroupThat the update be noted. | Noted | Open |
| 3 Apr 2012 | Date of Next MeetingThat this was the final scheduled meeting of the Economy and Governance Overview and Scrutiny Select Committee. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.