DECISION: That Cabinet authorises an exception to the Contract Procedure Rule under 10.1.1 (c) to enable the Head of Environment and Street Scene to use the Crematoria Solutions Contract 248 framework agreement administered by the Yorkshire Purchasing Organisation to obtain tenders for the crematorium upgrade project. REASON: This recommendation has been reached in order to comply with the Council’s Contract Procedure Rules and obtain best value and best use of resources.
Word for word from the decision Tunbridge Wells published for this meeting.Source: democracy.tunbridgewells.gov.uk
In conducting market research prior to the actual market testing for the replacement of the cremators and pollution abatement equipment, officers have become aware of a national framework agreement that has recently been created. This framework complies with the appropriate procurement legislation will comply with our Contract Procedure Rules (CPR), provided that Cabinet authorise the use of Contract Procedure Rule Exception 10.1.1 (c)
The framework is managed by Yorkshire Purchasing Organisation (YPO), a not-for-profit organisation set up by a group of local authorities to improve procurement efficiency and achieve greater value for money. It has been utilised successfully by this authority previously and has successfully procured similar services for three other local authorities to date.
By entering into this framework it is expected to deliver the benefits of larger scale procurement efficiencies and reduce the time and resources required to procure the services required.
Cabinet are therefore requested to authorise officers to use the YPO Crematoria Solutions contract 248 framework agreement.
LINK TO STRATEGIC COMPASS
By utilising this framework agreement greater efficiency in the use of resources and better value for money will be obtained. This directly contributes to the Passionate about providing value for money quadrant and more specifically to managing public finances effectively and delivering value through innovation.
Report status For decision. Route to Implementation/Timetable:
Subject to Cabinet approval, officers will enter the framework agreement and send to YPO our specifications. YPO will, on our behalf, conduct a mini market testing exercise involving the contractors appointed within the framework. We will manage the evaluation process and ultimately decide, with appropriate authorisation by Cabinet, the appointment of the successful contractor and then project manage the work on site with the appointed contractor. BACKGROUND/INTRODUCTION
1.1Cabinet at their meeting of 15 September 2011 approved the budget for the replacement of the cremators, pollution abatement equipment and associated building work after a soft market testing exercise had been completed to identify, amongst other things, an indicative cost for the project.
1.2Cabinet also instructed officers to market test the project fully and come back to recommend the appointment of a contractor to undertake the work.
1.3The full OJEU procurement process and associated work, whilst commenced, will still take up to a further year to reach the stage where a recommendation to Cabinet to appoint a contractor will be ready.
1.4The use of a framework agreement, where the OJEU process has already been completed and a mini market test within the framework can be conducted, will mean that we will be able to reach the stage where we can recommend to Cabinet the appointment of a contractor in the next 6 to 9 months
1.5As part of the framework agreement YPO will receive 1% of the contract price direct from the successful contractor. It is possible that the contractors may include this cost in their tenders but it is believed that the scale of the framework is significantly larger than the business opportunity we alone can offer to the market so it is expected that cost efficiencies will be obtained.
1.6Prior to entry into the framework agreement, a service level agreement will be entered into to confirm the roles and responsibilities discussed with YPO.
1.7YPO have confirmed that the Council will have no liabilities to them or any contractor by entering into the framework agreement and that, if ultimately we do not appoint a contractor within the framework, we will owe nothing to either YPO or any of the contractors in the framework.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Capital Management Report Quarter 1RESOLVED – 1. That the actual gross expenditure and that net of revenue for the year and the sources of finance, as s...
Revenue Management Report Quarter 1RESOLVED – 1. That the Quarter 1 net expenditure on services to the end of June 2026 was £5,414,000, £102,000 less th...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.