RESOLVED – i. That Swale Borough Council, Tunbridge Wells Borough Council and Maidstone Borough Council enter into a ten year ICT partnership commencing on the 1 April 2013 based on the collaboration agreement set out at Exempt Appendix J to this report with full review (to include ... view the full minutes text for item CAB193/11
Word for word from the decision Tunbridge Wells published for this meeting.Source: democracy.tunbridgewells.gov.uk
ICT is a key building block in the establishment of further shared services and a factor in ensuring the success of those shared services already in place. Each authority produces their own ICT related policies but a partnership offers an opportunity to develop a single voice and contribute effectively to the County agenda. Exploring options for pursuing a partnership arrangement was therefore identified by the MKIP Management Board as strategically sound. Substantial work has been undertaken to date on assessing the best model for partnership working. This included exploring an outsourcing model which would have enabled initial savings of 35-40% but would not have offered the opportunity of ongoing savings. It was therefore discounted at this time, though it was noted that this could be considered at a later date.
The project has demonstrated, however, that there are opportunities to transform the way the service is provided within all the authorities through the shared service model. Through providing resilience and also average savings1 in the region of £3.71M (£371,000 per annum) across the three districts over the next ten years.
The report (Appendix A) sets out in detail the aims and outcomes expected from a shared ICT service.
LINK TO STRATEGIC COMPASS
ICT is no longer a back office function; it is now at the forefront of delivering the Council’s Strategic Compass. The average citizen is becoming increasingly ICT aware and expectations are growing exponentially. The proposed Shared ICT service will support the following corporate priorities.
Community – By supporting a wide range of information and communication technologies.
1 This includes staff and non staff savings Customers – Are effectively communicated with, understood, their needs are met and they are offered a choice of service access channels.
People – The Council’s is committed to maintaining a well resourced and motivated workforce. ICT systems have a very important role to play in ensuring that staff are properly equipped to fulfil their roles and responsibilities as public servants.
Value – Striving to identify and deliver efficiencies; and delivering value through innovation.
Portfolio Holder Project - To ensure value from the Council’s ICT investments.
Report status
For decision.
Route to Implementation/Timetable:
If approved by Cabinet Decision on 16 April 2012, the project will follow the implementation of the transition plan attached as Appendix Hb. BACKGROUND/INTRODUCTION
1. Prior to this paper detailed work has already been undertaken on exploring an MKIP ICT partnership which involved looking at a range of operational and financial information, seeking the views of key stakeholders and exploring different models of operation.
2. Following a final paper in October 2011 Management Board was satisfied in principle with a recommendation of a shared service model and requested that an Interim Head of ICT be appointed to develop the business case further and develop a strategy for a shared service.
3. Work has been undertaken since then to develop a strategy, staff structure, operational plan as well as establishing expected savings.
4. In developing these proposals over the past six months discussions have taken place with leading members, officers and staff, as well as reviewing a range of documents and plans.
WHAT IS THE ISSUE THAT REQUIRES A DECISION AND WHAT DOES THIS MEAN FOR THE PEOPLE OF TUNBRIDGE WELLS?
5. Cabinet is asked to consider the proposals for a shared ICT service provision covering the Mid Kent Improvement Partnership area and to agree the next phase of work.
WHO HAVE WE CONSULTED AND HOW? (OR WHO WILL WE CONSULT FOLLOWING THE DECISION?)
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Capital Management Report Quarter 1RESOLVED – 1. That the actual gross expenditure and that net of revenue for the year and the sources of finance, as s...
Revenue Management Report Quarter 1RESOLVED – 1. That the Quarter 1 net expenditure on services to the end of June 2026 was £5,414,000, £102,000 less th...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.