Museum and Art Gallery Lift Installation Project

Decided Executive 2 papers

Cabinet decided this item on Thursday 14 June 2012. Below is the council's own wording, with the papers it was decided on.

ItemCAB16/12

Resolved

RESOLVED – 1. That the £110,000 capital allocation be released; and 2. That an additional capital funding of £16,000 be allocated to ensure delivery of this project.
Word for word from the decision Tunbridge Wells published for this meeting. Source: democracy.tunbridgewells.gov.uk

Follow this further

Built from Tunbridge Wells's papers

What the report saysPro

Report to Cabinet

Summary

The project is to install lift access to museum and art gallery and to upgrade WC facilities to make them fully accessible. Additional works were identified as necessary following consultation with Planning and Building Control.

The report seeks release of the £110k capital allocation for the project and the allocation of £16k of capital to fund the additional works.

LINK TO STRATEGIC COMPASS

This fits firmly within the community quadrant of the strategic compass and is identified within the Confident Borough segment as project 34: Deliver a new lift and public lavatory into the museum. It also links in with the Customers quadrant - that needs are met through provision of accessible facilities.

Report status

For decision

Route to Implementation/Timetable:

If approval is given, the project will commence in July with completion in November 2012. BACKGROUND/INTRODUCTION:

1. The Museum and Library building is owned by KCC with a user agreement in place for TWBC to occupy specific areas. KCC are responsible for all internal and external improvements, alterations, repairs and maintenance of the whole building and can recover a proportion from TWBC. For improvements and alterations the percentage recoverable from TWBC is 50% and they are contractually and legally obliged to pay such sums under the terms of the agreement with KCC.

2. Capital funding of £110k has been allocated to fund provision of a lift and public toilets to the museum which has been identified as a key project within the strategic compass. Led by KCC, plans have been developed and a tender for contractors completed. Applications have been submitted for planning and listed building consent.

3. During consultation with TWBC planning and Building Control officers, a number of additional elements have been added to the original plans to ensure that the works comply with fire safety and evacuation procedures. These include upgrading of existing doors to fire doors, provision of fire screens and upgrading of the electrical system to ensure power supply in an emergency – all of which are particularly difficult to achieve in a Grade 2 listed building.

4. Value engineering principles have been applied to the lowest tender submission, but the TWBC contribution cannot be negotiated below a figure of £142k - leaving a shortfall of £32k from the capital allocation.

5. It is proposed that 50% of the additional funding requirement is met by using donations made to the museum over the last 10 years. Donations are invited from the public to contribute toward the development of the museum service. £16k is available from the public’s donations to the museum to help meet this additional cost.

6. Currently, visitors and staff with a disability or mobility impairments are effectively restricted to the ground floor of the building with no access to the museum, art gallery or reference library. The building also lacks accessible toilets for both the public and staff. Male and female toilets (staff only) are currently located on the ground and first floor. These toilets are not suitable for disabled users, and need to be adapted accordingly.

7. The proposed works will ensure the building complies with disability rights legislation and provides a suitable environment to all our museum and art gallery visitors.

WHAT IS THE ISSUE THAT REQUIRES A DECISION AND WHAT DOES THIS MEAN FOR THE PEOPLE OF TUNBRIDGE WELLS?

8. To agree the release of the £110k capital allocation for this project.

9. To agree the allocation of an additional £16k, to be vired from the Capital and Revenue Initiatives Reserve.

10. Completion of the project will address longstanding issues around accessibility to the town’s museum. WHO HAVE WE CONSULTED AND HOW?

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Item 12: Museum and Art Gallery Lift Installation Project Appendix A /12Appendix 68 KB Download
PDF
Museum and Art Gallery Lift Installation ProjectReport 119 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at Tunbridge Wells

Search all
  1. Museum and Art Gallery Lift Installation ProjectThis decision
  2. Application for Consideration - 20/02298/LBC Tunbridge Wells Library Adult Education Centre Museum And Art Gallery Mount Pleasant Road RTWApproved
  3. Application for Consideration - 19/00577/FULL - Tunbridge Wells Library, Adult Education Centre, Museum & Art Gallery, Mount Pleasant Road, Royal Tunbridge Wells, KentApproved
  4. Application for Consideration - 19/00614/LBC - Tunbridge Wells Library, Adult Education Centre Museum And Art Gallery, Mount Pleasant Road, Royal Tunbridge Wells, KentApproved
  5. Application for Consideration - 17/03640 - Tunbridge Wells Library, Adult Education Centre, Museum & Art Gallery, Mount Pleasant Road, Royal Tunbridge WellsApproved
  6. Application for Consideration - 17/03642 - Tunbridge Wells Library, Adult Education Centre, Museum & Art Gallery, Mount Pleasant Road, Royal Tunbridge WellsApproved

More from Tunbridge Wells Cabinet

All decisions
MeetingDecisionOutcome
24 Sep 2026 Treasury and Prudential Indicator Management Report Quarter 1RESOLVED – 1. That the Treasury Management and Prudential Indicator position for 2026/27 be noted. 2. That the foreca... Noted Open
24 Sep 2026 Capital Management Report Quarter 1RESOLVED – 1. That the actual gross expenditure and that net of revenue for the year and the sources of finance, as s... Noted Open
24 Sep 2026 Revenue Management Report Quarter 1RESOLVED – 1. That the Quarter 1 net expenditure on services to the end of June 2026 was £5,414,000, £102,000 less th... Noted Open
24 Sep 2026 New Updated Planning Validation Checklist (Post Public Consultation)RESOLVED – 1. That the Draft Tunbridge Wells Local Validation List be adopted and used in the validation and processi... Approved Open
24 Sep 2026 Update on the Full Council Motion regarding the Maintenance of The Pantiles ColonnadeRESOLVED – 1. That the report covering the updates on the Full Council motion (FC103/25) on the Pantiles be noted. 2.... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies