DECISION : 1. That capital expenditure of £60,000 is approved to improve access, water supply and low voltage electrical supply in Calverley Grounds for the ice rink – and that delegated authority (in consultation with the Portfolio holder for Tourism, Leisure and Economic Development) be granted to the Head of Housing & Wellbeing to approve works within that budget limit; 2. That the revenue budget for the ice rink is increased from £210,000 to £260,000 – and that this be set against a commensurate under-spend in the community grants budget in 2012/13; and 3. That consideration is given to savings elsewhere in the events budget, from 2013/14 onwards, to help offset the costs of the ice rink REASON: To help deliver a Christmas ice rink at least cost to local taxpayers
Word for word from the decision Tunbridge Wells published for this meeting.Source: democracy.tunbridgewells.gov.uk
This report updates on progress with providing utilities infrastructure for the Calverley Grounds ice rink
LINK TO STRATEGIC COMPASS
Passionate about our community – healthy, confident and prosperous
Report status
For decision by Cabinet
Route to Implementation/Timetable:
Delivery of ice rink during November-January each year
Portfolio Holder Decisions
I confirm that I have read the report and approve the recommendations
Signed Dated 3 July 2012 BACKGROUND/INTRODUCTION
1 Cabinet in February agreed to the continued provision of a Christmas ice rink in Calverley Grounds over the next 5 years. A revenue budget of £210,000 was agreed.
2 A capital budget of £100,000 was also approved – this was to install a 3 phase electrical supply and reduce revenue spend on generators and fuel.
3 This report advises of the accurate costs of improving the electrical supply and suggests an alternative option.
Electrical infrastructure
4 The Council’s specialist electrical advisers, MVM Mechanical & Electrical Consulting Engineers, advised that a high voltage connection of 800kVA is necessary to power the rink.
5 UK Power Networks are the monopoly supplier of electrical infrastructure in this area. They have quoted £104,000 for the basic equipment. The Council would be responsible, in addition to this sum, for the excavation of trenches and providing a weatherproof and secure switch room.
6 The switch room would be a significant size and would require external treatment which would match existing buildings in the park, particularly the adjacent cafe. It is estimated the additional cost of this building work would be at least £100,000.
7 Electricity costs have also increased in recent times, and the saving from this source of power when compared to generators has diminished.
8 Given a capital cost in excess of £200,000 and reduced revenue savings, the provision of a 3 phase electrical supply – and for an event that only lasts 6 weeks each year - cannot be justified.
Other power options
9 UK Power Networks have been asked whether they could make a contribution to the cost of the new electrical installation given the wider community benefit – they advised that around £12,000 might be available to offset the costs outlined above. Whilst welcome, this does not significantly improve the cost analysis.
10 They have also considered low voltage options for the park lights and small Christmas market, of up to 10 cabins, that is likely to accompany the ice rink this year. Their recommendation is an additional supply of 140kva, which is estimated to cost no more than £20,000. A financial contribution would not be available for such works, but staff from UK Power Networks are likely to be able to assist in some small environmental improvement works in the park.
11 The only other realistic option to power the ice rink is a generator, as used last year. 12 The hire of a generator is likely to add around £10,000 to the contract for the hire of the rink, with diesel fuel costs of around £40,000 for an 18x30 metre rink. This is slightly larger than the 20x20 metre rink provided last year, but the majority of complaints last year related to the small rink size. A larger rink also offers a better opportunity for increased ticket sales.
Water supply and paths
13 The ice rink was filled last year from the domestic supply to the adjacent cafe, with the consequence that the rink took many hours to fill and top up each day. An estimate of £30,000 is recommended to improve the water supply with either (a) a new underground connection to the nearest water main, approximately 150 metres distant at the park entrance or (b) a new bore hole in Calverley Grounds.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Capital Management Report Quarter 1RESOLVED – 1. That the actual gross expenditure and that net of revenue for the year and the sources of finance, as s...
Revenue Management Report Quarter 1RESOLVED – 1. That the Quarter 1 net expenditure on services to the end of June 2026 was £5,414,000, £102,000 less th...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.