CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Tunbridge Wells Borough Council
Cabinet, Thursday 18 April 2013 at 10.30am

Tennis Centre Lighting - Capital Funding Allocation

Approved Executive 3 papers

Cabinet approved this item on Thursday 18 April 2013. Below is the council's own wording, with the papers it was decided on.

ItemCAB204/12

Resolved

RESOLVED 1. That the allocation of capital funds from the capital and revenue initiatives reserve for the replacement and upgrade of obsolete lighting at the Tennis Centre at the Tunbridge Wells Sports Centre be approved, as set out in the exempt appendix; and 2. That authority be delegated to the Property & Development Manager, in consultation with the Portfolio-holders for Property and Major Projects and for Finance and Governance and with the S.151 Officer, to procure and complete these works. REASONS FOR RECOMMENDATIONS: 1. To lengthen the life of this property asset and to protect its capital value. To enable the continuation of this asset for its use and therefore to assist in delivering a Healthy Tunbridge Wells; and 2. To comply with the Council’s Constitution.
Word for word from the decision Tunbridge Wells published for this meeting. Source: democracy.tunbridgewells.gov.uk

Follow this further

Built from Tunbridge Wells's papers

What the report saysPro

Report to Cabinet

Summary

This report seeks authority for capital funding to be allocated to undertake necessary works to replace the obsolete lighting and upgrade the installation to a more energy efficient lighting solution at the Tennis Centre at Tunbridge Wells Sports Centre.

If Cabinet agrees to the allocation of such funds for conversion, it is recommended that authority to approve the procurement and award of a contract be delegated to the Section 151 Officer in consultation with the Portfolio Holders for Property and Major Projects and for Finance and Governance.

LINK TO STRATEGIC COMPASS

Value for money – we strive to identify and deliver efficiencies to manage public finances effectively

Community – A Healthy and Green Tunbridge Wells

Report status

For decision

Route to Implementation/Timetable:

The Report has been considered by Finance and Governance Cabinet Advisory Board on 28 March 2013 and includes the recommendations from that Cabinet Advisory Board.

Subject to Cabinet approval and delegation of authority, Property Services will initiate and complete these works. Portfolio Holders’ Decisions We confirm that we have read the report and approve it for publication

………………………………………………………………………………………………… Signed Councillor David Jukes Dated 4 April 2013 & Councillor James Scholes

BACKGROUND/INTRODUCTION

1. In accordance with the property portfolio management strategy which is set out in the Asset Management Plan, adopted by Full Council, Property Services are required to manage the Property Asset portfolio to maximise its operational and capital return and minimise liability.

2. This report seeks to deliver these objectives by seeking authority for the capital allocation of funds and the authority to undertake replacement works to obsolete lighting at the Tennis Centre in Tunbridge Wells.

3. The existing lighting in the Tennis Centre are the original systems installed when the building was constructed in 1993/94 and consists of a track mounted fluorescent system provided for general usage and floodlights used to provide the correct level of light necessary for competitions. These systems are now obsolete and have frequently failed over the past few years. Temporary repairs have enabled the Centre to continue to be used but it is now no longer possible to repair and there are currently a number of the fluorescent lights that are out of service.

4. It is proposed to take the opportunity to upgrade the installation to achieve a reduction in energy use and maintenance costs. This will be achieved by:-

 the utilisation of new LED lighting technology for general & competition lighting thereby reducing installed lighting load and reduced frequency of lamp/light source replacement

 instantaneous operation of lighting allowing increased energy saving by switching off lighting to unused courts

 dimmable light sources allowing use of daylight sensors to control the lighting thereby making the best use of natural light to achieve the required level of lighting

5. The proposal is expected to achieve a 60% reduction in energy usage which equates to 188,614 kWh pa (or £14,146.00 at 7.5p/kWh) equivalent to a reduction of 27 tonnes of carbon pa.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
130418 Cabinet Report Tennis Centre Lighting App A /12Appendix 102 KB Download
PDF
Capital application form Tennis Centre App B /12Appendix 92 KB Download
PDF
Tennis Centre Lighting: Capital Funding AllocationReport 179 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at Tunbridge Wells

Search all
  1. Tennis Centre Lighting - Capital Funding AllocationThis decision
  2. Supply and Installation of Solar Photo Voltaic system, Tennis Centre Roof, Tunbridge Wells Sports CentreApproved

More from Tunbridge Wells Cabinet

All decisions
MeetingDecisionOutcome
24 Sep 2026 Treasury and Prudential Indicator Management Report Quarter 1RESOLVED – 1. That the Treasury Management and Prudential Indicator position for 2026/27 be noted. 2. That the foreca... Noted Open
24 Sep 2026 Capital Management Report Quarter 1RESOLVED – 1. That the actual gross expenditure and that net of revenue for the year and the sources of finance, as s... Noted Open
24 Sep 2026 Revenue Management Report Quarter 1RESOLVED – 1. That the Quarter 1 net expenditure on services to the end of June 2026 was £5,414,000, £102,000 less th... Noted Open
24 Sep 2026 New Updated Planning Validation Checklist (Post Public Consultation)RESOLVED – 1. That the Draft Tunbridge Wells Local Validation List be adopted and used in the validation and processi... Approved Open
24 Sep 2026 Update on the Full Council Motion regarding the Maintenance of The Pantiles ColonnadeRESOLVED – 1. That the report covering the updates on the Full Council motion (FC103/25) on the Pantiles be noted. 2.... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies