CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Tunbridge Wells Borough Council
Cabinet, Thursday 12 September 2013 at 10.30am

Quarter 1 - Revenue Management to 30 June 2013

Decided Executive 6 papers

Cabinet decided this item on Thursday 12 September 2013. Below is the council's own wording, with the papers it was decided on.

ItemCAB57/13

Resolved

That the forecast outturn position for the year and the variances to the revised budget and forecast outturn as at quarter 1 be acknowledged. REASON FOR DECISION: To recognise the revenue expenditure and impact on reserves for the year ending 31 st March 2014.
Word for word from the decision Tunbridge Wells published for this meeting. Source: democracy.tunbridgewells.gov.uk

Follow this further

Built from Tunbridge Wells's papers

What the report saysPro

Report to Cabinet

Summary

This report shows the actual expenditure on services compared to the revised budget for the period ended 30 June 2013, and the forecast outturn position, highlighting significant variances from the revised annual budget.

The forecast outturn shows a net overspend of £296,000 to be funded from the General Fund essentially resulting from lower than budgeted car park income. The Council will need to take action to either raise revenue or reduce costs to bridge this shortfall.

LINK TO STRATEGIC COMPASS

This report supports the Value and Community quadrants of the strategic compass in particular that we manage public finances effectively.

Report status

For decision

Route to Implementation/Timetable:

Cabinet can make these decisions

Portfolio Holder Decision I confirm that I have read the report and approve it for publication.

Signed: Councillor James Scholes Dated: 29 August 2013 BACKGROUND/INTRODUCTION

(1) This report shows the revenue actual outturn for the period ended 30 June 2013, and highlights the significant changes from the approved revised budget.

(2) The forecast outturn Net Expenditure on Services shows an increase from the revised budget of £296,000 which will need to be recovered by the end of the year to meet the objective of a balanced budget.

WHAT IS THE ISSUE THAT REQUIRES A DECISION AND WHAT DOES THIS MEAN FOR THE PEOPLE OF TUNBRIDGE WELLS?

Summary Outturn – See Appendix B (3) Appendix B shows the overall income and net expenditure on services outturn position as at 30 June 2013. Total income and expenditure on services can be seen in greater detail within Appendix C, which provides further detail per service area. The approved budget was set by Council on 20 February 2013 and does not change. The revised budget is used to record virements amongst service areas and from reserves, whilst the forecast outturn is used to record the reporting of savings, overspends and allocations from reserves.

(4) It can be seen that the forecast outturn for expenditure on services has increased by £296,000 compared to the revised budget. This is due to a £300,000 expected shortfall to budget in car parking revenue, partially offset by a £4,000 reduction in the cost of Members allowances.

(5) Net interest is still forecast meet budget at £341,000. The budget for investments is £661,000 set at 1.45% based upon average funds of £45.7m. The market is somewhat unstable at the moment and the year end result will depend upon investment opportunities available as present investments mature. There is still £15m of the Public Works Loan Board loan to repay and interest is being paid at 2.38%, the total cost of which is £336,000 for 2013/14. The remaining £16,000 is other smaller amounts of interest paid to the Council.

(6) Appendices B and F show that £82,000 has been recorded and transferred to the Vacancy Factor from Directorate budgets. This is below the £90,000 budgeted for the quarter by £8,000 and leaves £278,000 to be achieved in the remaining three quarters of the year. Whilst the actual is very close to budget for the quarter this is always monitored carefully.

Earmarked Reserves – See Appendix D (7) Earmarked reserves are amounts set aside by the Council from its General Fund balance to meet identified future liabilities. Unlike last year, none of the Earmarked reserves have been set aside to pay for revenue costs. This complies with the Council’s new definition of a balanced budget.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Q1 13-14 /13Appendix A 106 KB Download
PDF
Overall Revenue and Net Expenditure on Services Q1 2013-14 /13Appendix B 29 KB Download
PDF
(a and b) Net Expenditure Q1 201314 /13Appendix C 64 KB Download
PDF
Earmarked Reserves Q1 2013-14 /13Appendix D 19 KB Download
PDF
Major Expenditure Accounts Q1 13-14 /13Appendix E 24 KB Download
PDF
Quarter 1: Revenue Management to 30 June 2013Report 179 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at Tunbridge Wells

Search all
  1. Quarter 1 - Revenue Management to 30 June 2013This decision
  2. Revenue Management Report Quarter 1Noted
  3. Revenue Management Report Quarter 1Decided
  4. Revenue Management Report Quarter 4Decided
  5. Revenue Management Report Quarter 4Decided
  6. Revenue Management Report Quarter 3Noted

More from Tunbridge Wells Cabinet

All decisions
MeetingDecisionOutcome
24 Sep 2026 Treasury and Prudential Indicator Management Report Quarter 1RESOLVED – 1. That the Treasury Management and Prudential Indicator position for 2026/27 be noted. 2. That the foreca... Noted Open
24 Sep 2026 Capital Management Report Quarter 1RESOLVED – 1. That the actual gross expenditure and that net of revenue for the year and the sources of finance, as s... Noted Open
24 Sep 2026 Revenue Management Report Quarter 1RESOLVED – 1. That the Quarter 1 net expenditure on services to the end of June 2026 was £5,414,000, £102,000 less th... Noted Open
24 Sep 2026 New Updated Planning Validation Checklist (Post Public Consultation)RESOLVED – 1. That the Draft Tunbridge Wells Local Validation List be adopted and used in the validation and processi... Approved Open
24 Sep 2026 Update on the Full Council Motion regarding the Maintenance of The Pantiles ColonnadeRESOLVED – 1. That the report covering the updates on the Full Council motion (FC103/25) on the Pantiles be noted. 2.... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies