That the Buildings at Risk Strategy and Implementation Plan be adopted; and 2. That the proposed changes to the Heritage Partnership Grants Scheme to provide greater flexibility in use for heritage assets be agreed. REASON FOR DECISIONS: To ensure that the Borough Council provides clear guidance for the interpretation of the NPPF and Core Strategy Policies to ensure consistency of approach throughout the Borough That the Buildings at Risk Strategy and Implementation Plan be adopted; and 2. That the proposed changes to the Heritage Partnership Grants Scheme to provide greater flexibility in use for heritage assets be agreed. REASON FOR DECISIONS: To ensure that the Borough Council provides clear guidance for the interpretation of the NPPF and Core Strategy Policies to ensure consistency of approach throughout the Borough
Word for word from the decision Tunbridge Wells published for this meeting.Source: democracy.tunbridgewells.gov.uk
The purpose of this report is to present a proposed Strategy and implementation plan that reflects best practice for dealing with local authority heritage assets at risk. Set out in this strategy and implementation plan are proposals for identifying and monitoring heritage at risk in the Borough. (The Strategy and implementation plan form Appendix B of this report). The proposed Building at Risk (BAR) strategy is required to meet English Heritage best practice and to amplify the guidance on heritage at risk which is contained within the National Planning Policy Framework at Para 126. The strategy will allow a process of identification and monitoring of buildings at risk that will allow for early and pro-active intervention by the Authority to prevent buildings becoming a major problem requiring high levels of investment to bring back to an economical or viable use.
As a result of the proposed Buildings at Risk Strategy and its implementation plan minor amendments to the current Heritage Partnership Grants Scheme are also sought. These amendments are twofold and are intended to have additional benefits beyond the BAR strategy. The changes are explained in the Heritage Partnership Grant Report that forms Appendix C of this report, however in brief the changes requested are:-
To widen the type of projects eligible for heritage partnership grant to support the facilitation of local communities engaging their own buildings at risk surveys with professional assistance and supported by grant funding. This will directly benefit the BAR strategy That use of the grant fund be expanded to support the use of statutory powers under the Planning (Listed Buildings and Conservation Areas) Act 1990. In cases of particularly problematic buildings where end use viability is uncertain, to commission external expect advice to identify uses that may or may not be viable and on methods or works that would be required to increase levels of viability to allow building restoration. This would allow the Authority to utilise existing resources in a much more proactive manner, much earlier in a buildings deterioration cycle resulting a more economic use of resource and funding. The above changes would all maximise the effectiveness of the BAR strategy. A copy of the existing Grants Strategy agreed in 2007 and the proposed amendments recommended is attached for comparison at Appendix C.
In addition to the above three criteria and to indirectly assist the BAR strategy it is requested that the amendments to the Heritage Partnership Grant additionally include the following:-
the type of projects eligible for Heritage Partnership Grant be widened to support the facilitation of local communities engaging with other conservation type work where local community involvement is a requirement, for example conservation area appraisals and management plans, Local Heritage Asset list production (in line with the Local Heritage Asset Supplementary Planning Document Adopted by Cabinet in June 2012) again utilising professional assistance where required.
The benefits to the BAR strategy of the above addition would be the freeing up of in-house resource to allow greater proactive input into achieving the goals of the BAR Strategy and in proactively bringing redundant, under used and vulnerable buildings at risk into viable acceptable uses. A subsidiary benefit for general conservation would be a pro-active and positive opportunity for greater community engagement that goes beyond current best practice and which allows the opportunity for greater appreciation of local heritage within the local community.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Capital Management Report Quarter 1RESOLVED – 1. That the actual gross expenditure and that net of revenue for the year and the sources of finance, as s...
Revenue Management Report Quarter 1RESOLVED – 1. That the Quarter 1 net expenditure on services to the end of June 2026 was £5,414,000, £102,000 less th...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.