That the acceptance of the tender submitted by Company A be approved and that authority be delegated to the Head of Economic Development, in consultation with the Interim Director of Finance (Section 151 Officer), to enter a 3 year contract with an optional extension of 2 years. REASON FOR DECISION: To enable the report to be taken to Cabinet and thereby complying with public procurement legislation and to deliver savings in the Council’s revenue expenditure. That the acceptance of the tender submitted by Company A be approved and that authority be delegated to the Head of Economic Development, in consultation with the Interim Director of Finance (Section 151 Officer), to enter a 3 year contract with an optional extension of 2 years. REASON FOR DECISION: To enable the report to be taken to Cabinet and thereby complying with public procurement legislation and to deliver savings in the Council’s revenue expenditure.
Word for word from the decision Tunbridge Wells published for this meeting.Source: democracy.tunbridgewells.gov.uk
Author of report: Keith Delves, Facilities Management Surveyor
Classification: Part Exempt (Appendix B Exempt)
Ward: All
SUMMARY This report presents the process, background and recommendations regarding the provision of Cleaning Services on the Council’s property portfolio. The careful re-specification of services and competitive tender process has resulted in an annual saving of £83k saving pa (or 33%) over the current spend on cleaning services subject to Cabinet approval and acceptance of the tender offer.
LINK TO STRATEGIC COMPASS The Corporate Property Cleaning contract links predominantly in the providing value quadrant of the Strategic Compass, providing good coverage across all the segments, but principally in identifying and delivering efficiencies.
Report status
For Cabinet approval.
Route to Implementation/Timetable:
Subject to Cabinet approval, the contract will be awarded with a commencement date 12th May.
Portfolio Holder Decision I confirm that I have read the report and approve it for publication.
Signed: Councillor James Scholes Dated: 28 March 2014 BACKGROUND/INTRODUCTION
1. Resulting from an internal audit report presented to members of the Audit and Governance Committee on 25th June 2013, it was identified that various contracts had not been competitively tendered for a number of years. Included in this was the main cleaning contract that serviced the Town Hall, Assembly Hall and Museum.
2. There was also a desire to make efficiency savings and, after a review of the current provision, it was clear that in some buildings cleaning was over specified so a number of options were considered to reduce the cost of this service.
3. The EU procurement rules require that all similar supplies of services have to be considered when evaluating what level of tendering process is used, so when considering the Town Hall cleaning requirement, we also had to include all other cleaning services provided to the council. This included the Gateway, NFL Depot, Crematorium and Public WCs
4. As the combined requirement for cleaning services is over the EU threshold (£257k in 2012-13) a full EU compliant tendering process had to be undertaken. The whole of the council’s cleaning requirement was offered but sub divided into 3 lots to allow Small Medium Enterprises to have an opportunity to tender. The lots comprised: Lot 1 Office Buildings Lot 2 Public Access Buildings Lot 3 Public WCs
5. All the current contractors providing these services have been notified that their current contracts will be terminated were invited to take part in the pre qualification exercise for the new contract. TUPE is likely to apply to a number of the employees of the current contractors and the transfer process will be managed by the successful contractor.
6. The EU Notice was published on the 29th July 2013 and the opportunity was advertised in the local press and on the South East Business Portal linked from the council’s website. The Delta e-Sourcing electronic procurement system has been utilised to manage the process. 91 interested companies downloaded the pre qualification questionnaire (PQQ) documentation, 40 of which have responded with a PQQ submission.
7. The PQQs were evaluated and the 5 highest scoring submissions were invited to tender. All those invited applied for all three lots however none of the current contractors successfully came through this stage.
8. The specification was completely redrafted and changed from an input or frequency specification to an output specification. An output based cleaning specification is where the required outcome is specified rather than a process to achieve an outcome and this avoids unnecessary cleaning tasks being carried out.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Capital Management Report Quarter 1RESOLVED – 1. That the actual gross expenditure and that net of revenue for the year and the sources of finance, as s...
Revenue Management Report Quarter 1RESOLVED – 1. That the Quarter 1 net expenditure on services to the end of June 2026 was £5,414,000, £102,000 less th...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.