Resolved
RESOLVED to note the report.
Joint Transportation Board noted this item on Monday 28 April 2014. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED to note the report.
Highway Improvement Scheme Progress Report
A report by the County Council’s Traffic schemes and members Highway Fund Manager to the Tunbridge Wells Joint Transportation Board on 28 April 2014
The following schemes are those which have been approved for funding by both the relevant Member and John Burr, Director of Highways, and is up to date as of 2 April 2014.
The details below are for Highway Schemes only and does not detail contributions Members have made to other groups such as Parish Councils.
More detail on their schemes can accessed by each Member via the online database or by contacting their Member Highway Fund Officer.
John Davies
Scheme Cost Status Salt bins at Redland Avenue and Grange Road 700 Installation Complete Mount Ephraim Zebra Crossing 20550 Consultation complete. Pre-Construction stage
Sean Holden
Scheme Cost Status Implement changes to the junction layout at 21250 Design is on going Waterloo Road j/w Angley Road A229 to give traffic priority on the main A road. Works include extension to the centre island, new signing and lining, relocation of lit street furniture and double yellow line parking restrictions
Christopher Hoare
Scheme Cost Status Installation of parking restrictions in the vicinity 1000 Design and consultation of St Philips Court, Sandhurst on going 2 Day Gang Hire – Pembury Parish 1599 Works identification on- going St Barnabus School, Quarry Road, Tunbridge 6000 Design on-going Wells – 20mph proposal Highway Trees – Greggs Wood Road 1010 To be handed over for delivery Gang Work and path clearance – Pembury 4669 Works identification on- Parish going Sandrock Road, Tunbridge Wells – Installation 1500 Design on-going of School Warning Signs Kerb Realignment – Greggs Wood Road 4662 Pre-construction stage junction with Liptraps Lane Salt Bin – The Coppice, Pembury 350 To be handed over for delivery Alex King
Scheme Cost Status Improvements to Lamberhurst Village entry 2862 Works Complete points Speed Reduction on Brenchley Road, Matfield 3730 Consultation now closed, Pre-Construction stage Interactive Sign – The Slade, Lamberhurst 5000 Consultation to commence with the Parish Council Highway Mirror – A262 Cranbrook Road/B2084 1045 Handed Over for Delivery
Peter Oakford
Scheme Cost Status Removal of 3 tree stumps and installation of 4 2399 Awaiting Installation replacement trees – Chestnut Avenue, Southborough Replacement of 2 trees – Yew Tree Road, 650 Awaiting Installation Southborough Change in priority at the junction of 1497 Works Complete Constitutional Hill and Church Road, Southborough Monitoring of Constitutional Hill/Church Road 1000 Surveys to be carried out Scheme in Southborough in June 2014 Installation of bending warnings and additional 1425 Works Complete carriageway markings (edge of carriageway and centre line) – Chestnut Avenue, Southborough Installation of parking restrictions outside the 2500 The Traffic Regulation Bike Shop and Hairdressers on A26 London Order process is currently Road, Southborough underway. To be advertised shortly Kibbles Lane, Southborough – Pothole Repair 4000 Handed Over for Delivery Wilman Road, Tunbridge Wells – Installation of 350 To be Handed Over for Salt Bin Delivery Installation of parking restrictions on Pennington 2500 The Traffic Regulation Road at the junctions of Doon Acre, Fernhurst Order process is currently Crescent and in the vicinity of the Church underway. To be advertised shortly
James Scholes
Scheme Cost Status Claremont Primary School, Claremont Road, 4500 Design On-going Tunbridge Wells – 20mph proposal St James CofE School, Sandrock Road, 4500 Design On-going Tunbridge Wells – 20mph proposal Cornford Lane, Tunbridge Wells – Traffic 8750 Consultation Complete – Options see separate report ______________________________________________________________
Donna Rixson – 03000 41 81 81
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Highway Improvement Scheme and Progress and Member Highway Fund UpdateReport | 131 KB | DownloadRead as text |
Follow Joint Transportation Board at Tunbridge Wells and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 13 Jul 2026 | Minutes of the meeting dated 20 April 2026RESOLVED : That the minutes of the Joint Transportation Board meeting dated 20 April 2026 be accepted as an accurate ... | Decided | Open |
| 13 Jul 2026 | Parking Consultation York Road and Dudley Road, Tunbridge WellsRESOLVED – That the Joint Transport Board notes the results of a public consultation proposing changes to waiting res... | Decided | Open |
| 13 Jul 2026 | Active Travel UpdateRESOLVED – The report was noted. | Noted | Open |
| 20 Apr 2026 | Minutes of the meeting dated 2 February 2026RESOLVED – That the minutes of the meeting dated 2 February 2026 be approved as a correct record. | Approved | Open |
| 20 Apr 2026 | Parish Highways Improvement Projects GrantsRESOLVED – The report was noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.