Tunbridge Wells Borough Council
Cabinet, Friday 16 May 2014 at 10.30am

Strategic Risk Register

Agreed Executive 4 papers

Cabinet agreed this item on Friday 16 May 2014. Below is the council's own wording, with the papers it was decided on.

ItemCAB177/13

Resolved

That the individual risks shown in the draft register that represent the principal strategic risks for Tunbridge Wells Borough Council be agreed and that the draft Strategic Risk Register be formally approved and adopted. REASON FOR DECISION: The existence of a meaningful will help Tunbridge Wells Borough Council to achieve its strategic objectives and Corporate Plan. That the individual risks shown in the draft register that represent the principal strategic risks for Tunbridge ... view the full minutes text for item CAB177/13
Word for word from the decision Tunbridge Wells published for this meeting. Source: democracy.tunbridgewells.gov.uk

Follow this further

Built from Tunbridge Wells's papers

What the report saysPro

Report to Cabinet

Summary

The report sets out the outcomes of the strategic risk management ‘refresh’ exercise which was conducted on 10 December 2013.

The report was considered and agreed by the Audit & Governance Committee on the 25 March 2014 (AG51/13) and considered by the Finance & Governance Advisory Board on 22 April. This report now seeks approval from Cabinet to formally adopt the draft strategic risk register.

LINK TO STRATEGIC COMPASS

The report covers a number of aspects of the ‘value quadrant’.

Report status

For decision

Route to Implementation/Timetable:

The report has been considered by the Audit & Governance Committee and Finance & Governance Cabinet Advisory Board and now seeks Cabinet approval to formally adopt the strategic risk register.

Portfolio Holder Decision

I confirm that I have read the report and approve it for publication.

Signed: Councillor James Scholes Dated: 1 May 2014 BACKGROUND/INTRODUCTION

1. A strategic risk management workshop was conducted on 10 December 2013; facilitated by Joseph White, Senior Risk Consultant, Zurich Management Services. The exercise was an opportunity for the Management Board, Heads of Service and key Members to refresh (or update) through identification, analysis and prioritisation, those risks that may affect the ability of Tunbridge Wells Borough Council to achieve its strategic objectives and Corporate Plan. Therefore the exercise recognised the need to sustain risk management at the highest level. The attendees for the session were:

 William Benson, Chief Executive  Paul Taylor, Director of Change & Communities  Jonathan MacDonald, Director of Development & Environment  Lee Colyer, Head of Finance & Governance – S151 Officer  Paul Cummins, Monitoring Officer, Legal Services Manager  Gary Stevenson, Head of Environment & Street scene  Kevin Hetherington, Head of Communities and Wellbeing  Adam Chalmers, Democratic and Community Engagement Manager  Val Green, Head of Organisational Development  Cllr James Scholes, Cabinet Portfolio Holder for Finance & Governance  Cllr Len Horwood, Audit & Governance Committee Chair  Cllr David Scott, Audit & Governance Committee Member

2. The risks were identified in the context of their potential for affecting the ability of the organisation to achieve its objectives.

3. The identified broad risk areas were discussed and framed into a risk scenario format, containing risk cause and consequence elements, with a ‘trigger’ (also identified as the risk scenario). This format ensured that the full nature of the risk was considered and it also helped with the prioritisation of the risks.

4. The discussion resulted in 9 risk scenarios being agreed (Appendix B) and these were then assessed for impact and likelihood and plotted onto a matrix (Appendix C). The likelihood of the risks was measured as being ‘very high’, ‘high’, ‘significant’, ‘low’ or ‘very low’ or ‘minimal’. The impact, compared against the key objectives and Corporate Plan was measured as being ‘major’, ‘severe’, ‘medium’, or negligible’.

5. The identified risk scenarios are as follows:

 Cinema site remains undeveloped  Being unable to maximise economic opportunities and resolve infrastructure issues  Resident engagement  Unable to plan financially over the longer term  National policy changes in short term that impact negatively on TWBC, and on direction  Missing something significant (£100k – 250k impact) – ‘dropping the ball’  Being unable to meet expectations within resources  Inspector decision which challenges housing target versus housing supply  Not managing control and change effectively – Staff, Management, and Political

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Strategic Risk RegisterReport 170 KB DownloadRead as text
PDF
Strategic Risk Register appendix A: cross cutting issues /13Appendix 46 KB Download
PDF
Strategic Risk Register appendix B: Strategic Risk Profile /13Appendix 160 KB Download
PDF
Strategic Risk Register appendix C: Strategic Risk Profile March 2014 /13Appendix 100 KB Download

At this meeting

Whole meeting

On this subject at Tunbridge Wells

Search all
  1. Strategic Risk RegisterThis decision
  2. Strategic Risk RegisterNoted
  3. Strategic Risk RegisterNoted
  4. Strategic Risk RegisterNoted
  5. Strategic Risk RegisterDecided
  6. Strategic Risk Register Annual ReportNoted

More from Tunbridge Wells Cabinet

All decisions
MeetingDecisionOutcome
24 Sep 2026 Treasury and Prudential Indicator Management Report Quarter 1RESOLVED – 1. That the Treasury Management and Prudential Indicator position for 2026/27 be noted. 2. That the foreca... Noted Open
24 Sep 2026 Capital Management Report Quarter 1RESOLVED – 1. That the actual gross expenditure and that net of revenue for the year and the sources of finance, as s... Noted Open
24 Sep 2026 Revenue Management Report Quarter 1RESOLVED – 1. That the Quarter 1 net expenditure on services to the end of June 2026 was £5,414,000, £102,000 less th... Noted Open
24 Sep 2026 New Updated Planning Validation Checklist (Post Public Consultation)RESOLVED – 1. That the Draft Tunbridge Wells Local Validation List be adopted and used in the validation and processi... Approved Open
24 Sep 2026 Update on the Full Council Motion regarding the Maintenance of The Pantiles ColonnadeRESOLVED – 1. That the report covering the updates on the Full Council motion (FC103/25) on the Pantiles be noted. 2.... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies