Resolved
That the actions taken to manage the strategic risks relating to the cinema site be noted ... view the full minutes text for item AG20/14
Audit and Governance Committee noted this item on Tuesday 23 September 2014. Below is the council's own wording, with the papers it was decided on.
Resolved
That the actions taken to manage the strategic risks relating to the cinema site be noted ... view the full minutes text for item AG20/14
This report sets out the current Strategic Risks and identifies the specific risk CSR1’ Cinema site remains undeveloped’ for consideration at this meeting.
LINK TO STRATEGIC COMPASS
The report offers support across the Corporate priorities by ensuring that we are well managed, proactive and deliver value for money services. Risk management also forms part of the Corporate Governance framework.
Report status
For information
Route to Implementation/Timetable:
Specific action plans have been developed to identify and manage the authority’s strategic risks that are subject to review and monitoring by Management Board, Cabinet and Audit & Governance Committee throughout the year. BACKGROUND/INTRODUCTION
1. The Council is committed to the effective management of risk and has a Risk Management Strategy setting out its approach.
2. To fulfil our corporate governance responsibilities we must manage risks effectively. This report sets out the current position on strategic risks, reflecting changes agreed by Management Board previously circulated to members of this Committee.
3. It was agreed at Management Board and subsequently approved by this Committee in March 2014 (AG51/13) that risk owners would periodically attend Committee meetings to provide an update on management of their allocated risk(s)’.
4. The Committee should determine which risk(s) they wish to review in future and incorporate that within its work programme.
5. For this meeting the Committee requested a review of Corporate Strategic Risk - 1 Cinema site remains undeveloped. (Appendix B). The Deputy Chief Executive, Jonathon MacDonald owns the risk and will be present at the meeting to discuss the action plan in operation to manage the risk.
6. This risk was identified during a risk workshop undertaken in December 2013 by senior managers and members and included on the Council’s strategic risk register. This risk has been kept up to date since the initial identification.
7. As part of the review in December, the Council refocused risks to align with corporate priorities and created a revised Strategic Risk Register. This Committee considered the revised Register on 25 March 2014 (AG51/13) and Cabinet subsequently approved it on 16 May 2014 (CAB177/13). An additional risk CSR10 Development Programme has been created since the last Committee meeting in July and copies of the revised/amended action plans have been circulated.
8. Appendix 1 below summarises the Strategic Risks as at 31 August and highlights the risk for discussion at this meeting. (CSR1 Cinema site remains undeveloped) No Risk Scenario Likelihood Impact Risk Owner
1 Cinema site remains undeveloped (5) (3) Jonathan High Severe Macdonald 2 Being unable to maximise economic opportunities (5) (3) David Candlin and resolve infrastructure issues High Severe 3 Resident Engagement (4) (3) William Significant Severe Benson 4 Unable to plan financially over the longer term (6) (3) Lee Colyer Very High Severe 5 National policy changes in short term that impact (6) (2) William negatively on TWBC, and on direction Very High Medium Benson 6 Missing something significant (4) (2) Lee Colyer Significant Medium 7 Being unable to meet expectations within (5) (2) William resources High Medium Benson 8 Inspection decision which challenges housing (4) (4) Jane Lynch targets Vs supply Significant Major 9 Not managing control and change effectively – (4) (3) William Staff , Management & Political Significant Severe Benson 10 Development Programme (5) (3) David Candlin High Severe 9. The full Risk register includes:
• Risk Scenario • Likelihood/Impact – risk score • Risk Owners • Vulnerability/Contributing factors • Impact/Consequences • Controls and Mitigation
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
/14Appendix A | 88 KB | Download |
PDF |
/14Appendix B | 180 KB | Download |
PDF |
/14Appendix C | 99 KB | Download |
PDF |
Strategic Risk Review: Cinema SiteReport | 134 KB | DownloadRead as text |
Follow Audit and Governance Committee at Tunbridge Wells and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 2 Jul 2026 | Minutes of the meeting of the Audit and Governance Committee dated 10 March 2026RESOLVED – That the minutes of the meeting dated 10 March 2026 be approved as a correct record. | Approved | Open |
| 2 Jul 2026 | Future Work Programme as at 2 July 2026RESOLVED – That the Future Work Programme as at 2 July 2026, be noted. | Noted | Open |
| 2 Jul 2026 | External Audit Progress and Sector Update ReportRESOLVED - That the committee consider and agree the Audit Progress and Sector Update Report. | Agreed | Open |
| 2 Jul 2026 | Internal Audit Report & Annual Audit Opinion 2025/26RESOLVED – 1. That the Audit & Governance Committee notes the Head of Audit Partnership opinion. 2. That the Audit & ... | Decided | Open |
| 10 Mar 2026 | Minutes of the meeting of the Audit and Governance Committee dated 25 November 2025RESOLVED – That the minutes of the meeting dated 25 November 2026 be approved as a correct record. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.