That the projected gross and net expenditure for the year, as shown in Appendix C and Appendix D to the report be noted; 2. That the proposed variations set out in notes 7 to 9 in the report be approved; and 3. That the 4 year capital budget as set out in Appendix N to the report (see note 15) be approved. REASONS FOR DECISIONS: 1. The deferrals in note 7 reflect changes to this years capital programme but do not impact on the overall requirement from earmarked reserves; 2. The variations outlined in note 8 show a net reduction in the use of earmarked reserves; 3. New schemes are recommended in note 9, which are in line with the Council’s priorities and are affordable in terms of reserves; and 4. The sale of surplus pieces of land has made funds available to finance the capital programme.
Word for word from the decision Tunbridge Wells published for this meeting.Source: democracy.tunbridgewells.gov.uk
This report summarises the actual and forecast outturn expenditure on capital schemes as at 31 December 2014. Total capital expenditure for the current financial year is forecast to be £16,734,000, a reduction of £2,239,000 from the previously approved budgets. This consists of £2,026,000 in spending deferred into 2015/16, and of net underspends of £245,000, offset by £32,000 in new schemes (£351,000 over the years to 2017/18).
LINK TO STRATEGIC COMPASS
This report supports the Value and Community quadrants of the strategic compass in particular that we manage public finances effectively.
Report status
For decision by Cabinet.
Route to Implementation/Timetable:
Cabinet can make these decisions.
Portfolio Holder Declaration
I confirm that I have read the report and approve it for publication.
Signed: Councillor Michael Rusbridge Dated: 18 February 2015 BACKGROUND/INTRODUCTION
(1) At their meeting on 26 June 2014, Cabinet approved schemes to be met from the Capital Programme for the years from 2014/15 to 2017/18.
(2) The figures approved by Cabinet were on the basis of the net cost after specific funding to be met by the Council, either from reserves or from the sale of existing assets. The gross approved spending for was £20,227,000 during that period, of which £17,230,000 was to be spent during 2014/15. Further approvals since then have brought the total approved programme to £26,196,000, of which £18,973,000 was due to be spent in 2014/15. Details of the movement in total approved budgets are shown in Appendix B.
(3) Appendices C and D set out in gross and net terms the actuals and amounts approved against the forecast outturn to 31 March 2015, while Appendix L sets out the position for the complete capital programme through to 2017/18.
(4) Approval is sought for £2,026,000 gross expenditure to be deferred to future years (see note 7), and for a reduction to the plan of £245,000 due to underspends (see note 8).
(5) Approval is also sought for increases in the overall capital programme of £351,000, of which £32,000 will fall in 2014/15. In net terms (the amounts to be met from earmarked reserves or from the disposal of assets) these increases amount to £204,000 in the overall capital programme, £12,000 of which falls into 2014/15.
(6) Budgets are approved by Full Council in February each year. Since 2012/13 approvals for capital expenditure have been approved in principle, as shown in Appendix M, but schemes need to be formally approved by Cabinet before they can be included in the approved capital programme. Some of these approvals in principle have now been given formal approval, leaving £5.5m in schemes still to be approved.
WHAT IS THE ISSUE THAT REQUIRES A DECISION AND WHAT DOES THIS MEAN FOR THE PEOPLE OF TUNBRIDGE WELLS?
Schemes deferred into future years
(7) There are seven projects where implementation has been delayed, and Cabinet approval is requested to defer gross expenditure totalling £2,026,000 into future years (see Appendix C):
£100,000 of the £105,000 approved for enhancements to the Financial Management System. £22,000 of the cremators replacement project. £1,722,000 of the £1,766,000 investment in the sports centres The £118,000 approved for memorial schemes £22,000 of the crematorium feasibility study £37,000 of the £42,000 improvement to the Monson Road Properties The £5,000 remaining for North Farm Art Works Over and underspends on approved projects.
(8) There are six projects where Cabinet approval is requested for variations totalling a reduction of £245,000 in gross terms, as shown in Appendix C.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Capital Management Report Quarter 1RESOLVED – 1. That the actual gross expenditure and that net of revenue for the year and the sources of finance, as s...
Revenue Management Report Quarter 1RESOLVED – 1. That the Quarter 1 net expenditure on services to the end of June 2026 was £5,414,000, £102,000 less th...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.