Certification of Grant Claims 2013/14

Noted Finance 3 papers

Audit and Governance Committee noted this item on Tuesday 24 March 2015. Below is the council's own wording, with the papers it was decided on.

ItemAG43/14

Resolved

That the findings of Grant Thornton’s report be noted.
Word for word from the decision Tunbridge Wells published for this meeting. Source: democracy.tunbridgewells.gov.uk

Follow this further

Built from Tunbridge Wells's papers

What the report saysPro

Report to Audit and Governance Committee

Summary

This report summarises the outcomes of Grant Thornton’s work to certify the grant and subsidy claims that the Council submitted during 2013/14.

LINK TO STRATEGIC COMPASS

This report supports the ‘value’ quadrant on the Strategic Compass.

Report status

For information. BACKGROUND/INTRODUCTION

1. The Audit Commission prescribes the arrangements for the audit of key grant and subsidy claims. This is to provide assurance to the grant paying body that the claims for grant and subsidies are made properly and that the financial returns are reliable. Grant Thornton are the Council’s external auditors and are acting as agents of the Audit Commission.

SUMMARY OF WORK UNDERTAKEN

2. Grant Thornton undertook work to certify the Housing Benefits subsidy claim submitted by the Council, with a value of £34.9 million.

3. The level and form of testing varies between claims to reflect the value and specific requirements of the grant paying body.

RESULTS OF THE 2013/14 CERIFICATON WORK

4. Grant Thornton concluded that they are satisfied that the Council has appropriate arrangements in place to compile; complete, accurate and timely claims/returns for audit certification. However they did identify some errors which resulted in minor agreed amendments to the claim which are detailed in Appendix B.

WHO HAVE WE CONSULTED AND HOW? (OR WHO WILL WE CONSULT FOLLOWING THE DECISION?)

5. Grant Thornton has consulted with the Head of Revenues and Benefits Partnership.

HOW WILL THE DECISION BE COMMUNICATED?

6. This report will be published on to the Council’s website.

WHAT ALTERNATIVE ACTION COULD WE TAKE? (where appropriate)

7. The report is provided for information only.

CONCLUSIONS

8. That Grant Thornton has certified that the Council has prepared and submitted grant and subsidy claims to a good standard.

Recommendation

9. That the Audit and Governance Committee notes the findings of Grant Thornton’s report in Appendix B.

Reason for recommendation

10. The Audit and Governance Committee’s functions and delegations, as outlined in its constitution and terms of reference states that it should:

 agree the external Audit Plan for the year;  approve the cost of the audit;  consider specific reports as agreed with the external audit work and to ensure it gives value for money; and  comment on the scope and depth of external audit work and to ensure it gives value for money.

Contact Officer: Stephen McGinnes, Head of Revenues and Benefits Shared Service

Lee Colyer Finance Director

Background Papers None

APPENDICES TO REPORT Appendix A: Cross Cutting Issues Appendix B: Certification work report 2013/14

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
/14Appendix A 66 KB Download
PDF
/14Appendix B 76 KB Download
PDF
Certification of Grant Claims 2013/14Report 80 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at Tunbridge Wells

Search all
  1. Certification of Grant Claims 2013/14This decision
  2. Certification of Grant Claims 2012/13Noted
  3. Certification of Grant Claims 2011/12Noted

More from Tunbridge Wells Audit and Governance Committee

All decisions
MeetingDecisionOutcome
2 Jul 2026 Minutes of the meeting of the Audit and Governance Committee dated 10 March 2026RESOLVED – That the minutes of the meeting dated 10 March 2026 be approved as a correct record. Approved Open
2 Jul 2026 Future Work Programme as at 2 July 2026RESOLVED – That the Future Work Programme as at 2 July 2026, be noted. Noted Open
2 Jul 2026 External Audit Progress and Sector Update ReportRESOLVED - That the committee consider and agree the Audit Progress and Sector Update Report. Agreed Open
2 Jul 2026 Internal Audit Report & Annual Audit Opinion 2025/26RESOLVED – 1. That the Audit & Governance Committee notes the Head of Audit Partnership opinion. 2. That the Audit & ... Decided Open
10 Mar 2026 Minutes of the meeting of the Audit and Governance Committee dated 25 November 2025RESOLVED – That the minutes of the meeting dated 25 November 2026 be approved as a correct record. Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies