CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Tunbridge Wells Borough Council
Joint Transportation Board, Monday 20 July 2015 at 6.00pm

Yew Tree Road

Noted Committee 1 paper

Joint Transportation Board noted this item on Monday 20 July 2015. Below is the council's own wording, with the papers it was decided on.

ItemTB12/15

Resolved

RESOLVED – That the report be noted and the Board supports the continuation of the detail design and implementation stage.
Word for word from the decision Tunbridge Wells published for this meeting. Source: democracy.tunbridgewells.gov.uk

Follow this further

Built from Tunbridge Wells's papers

What the report saysPro

Report to Joint Transportation Board

Summary

The report provides an update on an LGF funded scheme for improvements to the Yew Tree Road and Speldhurst Road junctions with the A26 London Road/St Johns Road in Southborough.

INTRODUCTION AND BACKGROUND

1.1Kent County Council (KCC) is intending to improve the traffic signal controlled junctions of Yew Tree Road and London Road, Speldhurst Road and St John’s Road in Southborough to improve capacity and reduce peak time congestion.

1.2The scheme is to be fully funded from the successful Local Growth Fund (LGF) bid and forms part of a package of improvement works for the A26 corridor between the A21 and Tunbridge Wells with the aim of reducing congestion.

1.3The principal scheme aim is to reduce the current issue of peak time congestion on the A26 through both junctions.

1.4The scheme was discussed at the last meeting of the JTB on 20th April, and the recommendation of the board was ‘that the Board supported the proposed improvement detailed in scenario 3 [improvements to the workings of the traffic signals at both junctions] being taken forward to detailed design and implementation stage, and that particular attention is paid to the needs of cyclists and pedestrians in the detailed design’.

DISCUSSION

2.1Since this recommendation, concerns have been raised about the removal of five trees at the Yew Tree Road junction which would need to be undertaken to facilitate the new splitter island on Yew Tree Road. A splitter island allows pedestrians to cross one direction of traffic at a time, so that the opposite direction of traffic can continue to flow therefore maximising the amount of traffic that can go through the junction in one cycle. The TWBC and KCC tree officers object for the following reasons:

a) They are classed as high amenity trees and are to be protected by TPO; b) They offer protection to other trees from strong north easterly winds (the site is in an elevated position); c) They provide a green oasis in the Southborough urban area which has very few trees to the north of this junction along the A26. 2.2 Owing to these concerns, KCC have investigated two alternative options:

a) Leave the Yew Tree Road layout as it is, without a splitter island on this arm; b) Instead of removing five trees, remove two mature trees right by the junction and replant replacements in the green space between the library and fire station. This would give enough room for the splitter island to be constructed, but would shorten the existing length of the two lane approach to the junction with the A26.

2.3Following investigation by KCC’s consultants, Amey, option a) has been modelled and has been found to have no detrimental impact on the operation of the proposed junction arrangement. The reason for this is that the signal stage in which this pedestrian crossing is active also contains the pedestrian crossing phase over the Speldhurst Rd arm which is already a straight-across arrangement. Therefore, the increased intergreen time associated with the longer crossing on Yew Tree Road is already factored into the model due to the similar nature of the Speldhurst Road pedestrian crossing facility.

CONCLUSION

3.1Following investigation, it is concluded that keeping the Yew Tree Road arm junction in its current layout will not be detrimental to the improved working of the scheme. Therefore no trees will need to be removed.

RECOMMENDATION(S):

1 That the Joint Transportation Board members note this update report and give approval for the detail design and implementation stage to continue.

Contact Officer: Vicki Hubert – KCC Strategic Transport and Development Planner 03000 416379 Reporting to: Nasser Sarrafan – KCC Transport and Development Manager 03000 413792

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Yew Tree RoadReport 88 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at Tunbridge Wells

Search all
  1. Yew Tree RoadThis decision
  2. Application for Consideration - 24/01184/FULL The Granary, Swigs Hole Farm, Yew Tree Green Road, Horsmonden, Tonbridge, Kent.Approved
  3. John Street and Yew Tree Road Car Parks - Issue of Season TicketsDecided
  4. Application for Consideration - 23/03322/FULL The Granary, Swigs Hole Farm, Yew Tree Green Road, Horsmonden, Tonbridge, KentApproved
  5. Application for Consideration - 20/01070/FULL The Green Barn Swigs Hole Farm Yew Tree Green Road Horsmonden Tonbridge KentApproved
  6. Application for Consideration - 17/00323 - 7 Yew Tree Road SouthboroughApproved

More from Tunbridge Wells Joint Transportation Board

All decisions
MeetingDecisionOutcome
13 Jul 2026 Minutes of the meeting dated 20 April 2026RESOLVED : That the minutes of the Joint Transportation Board meeting dated 20 April 2026 be accepted as an accurate ... Decided Open
13 Jul 2026 Parking Consultation York Road and Dudley Road, Tunbridge WellsRESOLVED – That the Joint Transport Board notes the results of a public consultation proposing changes to waiting res... Decided Open
13 Jul 2026 Active Travel UpdateRESOLVED – The report was noted. Noted Open
20 Apr 2026 Minutes of the meeting dated 2 February 2026RESOLVED – That the minutes of the meeting dated 2 February 2026 be approved as a correct record. Approved Open
20 Apr 2026 Parish Highways Improvement Projects GrantsRESOLVED – The report was noted. Noted Open