RESOLVED – 1. That the Director of Planning and Development, in consultation with the Leader of the Council, the Portfolio Holder for Finance for Governance and the Section 151 Officer, be authorised to approve the required funds, up to the budget sum set out in exempt Appendix C to the report, and the professional expertise to progress and deliver the office accommodation brief from the development programme budget; 2. That the Director of Planning and Development to ensure that the Development Advisory Panel is engaged as appropriate during the delivery of the work; 3. That an outline of additional development programme budget resources required be provided for the December Cabinet meeting; 4. That the architect’s brief include a statement that the new building should create a strong sense of civic stature; and 5. That there be no final commitment to the project without first having a clear, agreed plan for the existing Town Hall site. REASON FOR DECISIONS: To enable the scheme to develop quickly and to enable the Council to explore and progress discussion with potential pre-let tenants with a view to tying them into a formal commitment.
Word for word from the decision Tunbridge Wells published for this meeting.Source: democracy.tunbridgewells.gov.uk
This report seeks approval to progress with the design of office accommodation potentially for the Council and a pre-let at Mount Pleasant Avenue Car Park.
LINK TO STRATEGIC COMPASS
The proposal contained in the report supports the aims and objectives of the Asset Management Plan and a key objective in the Five Year Plan, demonstrating that we are passionate about providing value by seeking to optimise income and deliver value through innovation.
Report status:
For Cabinet Decision
Route to Implementation/Timetable:
The Cabinet decision will come into effect after the call-in period.
BACKGROUND/INTRODUCTION
1. Mount Pleasant Avenue Car Park is situated behind the shops and restaurants on Mount Pleasant Road, with the Calverley Grounds to the east, Great Hall Car Park to the south and AXA offices to the north. It is leased to AXA PPP for car parking mid- week with public car parking at the weekend. The core site covers approximately 0.16 hectares.
2. The site has been reviewed for a range of uses as the location, adjacent to Calverley Grounds, could be suitable for residential, office or hotel use. As part of this work a valuation of the site had been undertaken by the Regeneration Company and latterly through the Development Programme. Planning policy (Policy AL/RTW 21) identifies the site for office employment uses and the site is identified in the Five Year Plan and in the Development Programme as a development opportunity for an office building.
3. Progressing with an office use has been endorsed internally by the Development Advisory Panel and work on initial massing has been undertaken as well as a range of ground testing and topographical surveys. However, a formal decision to progress has not been taken. The site provides an opportunity for wider regeneration and economic benefits including the retention of existing local businesses, or attracting new businesses to the town centre. In terms of massing it is considered that if the Council occupied the site there is potentially sufficient space to attract a pre-let. A number of discussions with potential pre-lets have taken place previously and more recent pre-let interests are currently being followed up. To build on this interest we are seeking to progress the development of an office use on this site.
4. Work to progress an office development has been on hold over the past year whilst the site is considered as part of the wider work commissioned on the Assembly Hall Theatre Mandate which includes the civic complex, Great Hall Car Park and the Mount Pleasant Avenue Car Park. Within this work the opportunity for the site to be developed as an office for potential use by the Council in the future with a potential pre-let to another occupier has formed part of the core opportunities. The work is at an advanced stage and the final report from the appointed consultants Bilfinger GVA is programmed for consideration by Cabinet on 5 December.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Capital Management Report Quarter 1RESOLVED – 1. That the actual gross expenditure and that net of revenue for the year and the sources of finance, as s...
Revenue Management Report Quarter 1RESOLVED – 1. That the Quarter 1 net expenditure on services to the end of June 2026 was £5,414,000, £102,000 less th...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.