RESOLVED – 1. That the Friends of Calverley Grounds ( FoCG ) be supported in principle in their plans to raise the funds to facilitate the purchase and installation of a new play area on the old bowling green; 2. That the Council undertake the responsibility for the procurement, planning (including the use of Local Authority permitted development powers) and project management of the installation of the play area; and 3. That the Contract Procedure Rules be waived to enable the Council to directly appoint the existing locally based design team being used by FoCG to assist with the project. REASON FOR DECISION: The Council’s five year plan identifies enhancements to Calverley Grounds as a key priority and a Management Plan has been put in place which includes aspirational schemes that could be carried out when internal/ external funds and resources become available.
Word for word from the decision Tunbridge Wells published for this meeting.Source: democracy.tunbridgewells.gov.uk
Cabinet 11 February 2016 Is the final decision on the recommendations in this report to be made at this meeting? Yes
Calverley Grounds Play Area Final Decision-Maker Cabinet Portfolio Holder(s) Councillor Jane March, Portfolio Holder for Tourism, Leisure and Economic Development Lead Director Jonathan MacDonald, Director of Planning and Development Head of Service Gary Stevenson, Head of Environment and Street Scene Lead Officer/Report Author Paul Shipley, Contract Services Manager Classification Non-exempt Wards affected Park
This report makes the following recommendations to the final decision-maker: 1. That the Friends of Calverley Grounds (FoCG) be supported in principle in their plans to raise the funds to facilitate the purchase and installation of a new play area on the old bowling green;
2. The Council undertake the responsibility for the procurement, planning (including the use of Local Authority permitted development powers) and project management of the installation of the play area; and
3. That the Contract Procedure Rules be waived to enable the Council to directly appoint the existing locally based design team being used by FoCG to assist with the project.
This report relates to the following Five yea Plan Key Priorities: A green borough – To implement the current Calverley Grounds Management Plan and work with the FoCG to develop a long term plan for the grounds.
Timetable Meeting Date Management Team Tuesday 5 January Discussion with Portfolio Holder Tuesday 8 December Cabinet Advisory Board Thursday 21 January Cabinet Thursday 11 February Calverley Grounds Play Area
1. PURPOSE OF REPORT AND EXECUTIVE SUMMARY
1.1The Council’s five year plan identifies enhancements to Calverley Grounds as a key priority and a Management Plan has been put in place which includes aspirational schemes that could be carried out when internal/ external funds and resources become available.
1.2This report seeks Cabinet approval for the proposed plans by the FoCG to fund raise £215,000 to facilitate the installation of a new natural play area on the disused bowling green in the park, whilst the Council undertakes the specialised responsibilities associated with procurement and installation.
1.3The report also seeks approval to waive the Council’s contract procedure rules to enable the future appointment of the project’s Design Team using the professional services of a number of local people that have been involved in the design process. This would be funded by appropriate section 106 developer contributions, of up to £25,000.
2. INTRODUCTION AND BACKGROUND
2.1The Calverley Grounds Management Plan (CGMP) has been in place since 2013 and is based on Green Flag criteria; the plan provides background to the park and its infrastructure along with a brief history of the park. The plan is an active working document and is reviewed regularly to ensure accuracy and allows for the development of the park.
2.2As part of the CGMP there is an action plan to cover the maintenance of the park but also to include aspirational projects that could be carried out when funds and resources become available.
2.3In 2012/13 the Council’s parks team undertook a survey of the park to understand the needs and the aspirations of the local community and the regular park visitors. The results indicated strong views in favour of the old bowling green being turned into a play area for children.
2.4The FoCG and Community Play Area group came together to look at a number of options (approximately 8) for the design and installation of a play area on the site in consultation with the Parks Team.
2.5In 2015 Community Play Area group sought advice from a locally based design company, Land Use Consultants, who volunteered to design a natural play area, based on natural play, which is attached at Appendix A.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Capital Management Report Quarter 1RESOLVED – 1. That the actual gross expenditure and that net of revenue for the year and the sources of finance, as s...
Revenue Management Report Quarter 1RESOLVED – 1. That the Quarter 1 net expenditure on services to the end of June 2026 was £5,414,000, £102,000 less th...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.