Cabinet, Wednesday 22 June 2016 at 6.30pm

* Civic Complex - Review of Stage 1 and Next Steps

Noted Executive 5 papers

Cabinet noted this item on Wednesday 22 June 2016. Below is the council's own wording, with the papers it was decided on.

ItemCAB17/16

Resolved

RESOLVED – That Full Council be recommended: 1. To note that: a. all consultancy fees identified in the report are spent at risk and that they will be abortive costs if the buildings are not developed; b. the Council has moved into RIBA Stage 2 (concept design) for the project to progress: i. Office ii. Theatre iii. Underground Car Park iv. Masterplan v. Procurement of a development partner; 2. That the Great Hall Car Park be the preferred site for the new theatre; 3. That Calverley Grounds be the preferred site for an underground car park; 4. That the authority to move into RIBA Stage 3 (detail design) for the project be delegated to the Portfolio Holder for Finance and Governance, the Leader, the S151 Officer and the Director for Planning and Development; 5. That authority be delegated to the Director for Planning and Development, the S151 Officer and Monitoring Officer in consultation with the Leader and Portfolio Holder for Finance and Governance, to enter into a formal agreement for lease with the prospective tenant on appropriate market terms, and that the principle of the capital commitment of doing so is recognised, and the financial risk if the commitments in the agreement to lease are not fulfilled, be recognised; 6. That the allocation of £2 million from the General Fund to the Capital and Revenue Initiatives Reserve and that this sum is vired into the Development Programme Budget be approved; and 7. That the S151 Officer, in consultation with the Portfolio Holder for Finance and Governance, be requested to bring back a report to a future meeting with options to address the revenue implications for funding the capital cost of the project, when or before the capital request is being considered. REASON FOR DECISION: The Borough has a clear and ambitious vision to ‘grow our role as the cultural centre of the Kent & Sussex High Weald, so that by 2024 the borough of Tunbridge Wells is nationally recognised for its vibrant cultural provision’. Having a modern theatre sits at the heart of this vision. Likewise, the commitment to deliver a modern theatre fit for the 21st Century, is a key component of the Council’s Five Year Plan.
Word for word from the decision Tunbridge Wells published for this meeting. Source: democracy.tunbridgewells.gov.uk

Follow this further

Built from Tunbridge Wells's papers

What the report saysPro

Report to Cabinet

Cabinet 22 June 2016 Is the final decision on the recommendations in this report to be made at this meeting? No

* Civic Complex – Review of Stage 1 and Next Steps Final Decision-Maker Full Council Portfolio Holder(s) Councillor David Jukes, Leader of the Council Lead Director Jonathan MacDonald, Director of Planning and Development Head of Service David Candlin, Head of Economic Development Lead Officer/Report Author Diane Brady, Civic Development Manager Classification Non exempt, except Appendix E, which is exempt information under the Local Government Act 1972 Schedule 12A Paragraph 3: Information relating to the financial or business affairs of any particular person (including the authority holding that information). Wards affected All

This report makes the following recommendations to the final decision-maker: 1. To note that: - all consultancy fees identified in the report are spent at risk and that they will be abortive costs if the buildings are not developed. - the Council has moved into RIBA Stage 2 (concept design) for the project to progress: o Office o Theatre o Underground Car Park o Masterplan o Procurement of a development partner 2. That the Great Hall Car Park is the preferred site for the new theatre. 3. That Calverley Grounds is the preferred site for an underground car park. 4. That the authority to move into RIBA Stage 3 (detail design) for the project be delegated to the Portfolio Holder for Finance and Governance, the Leader, the S151 Officer and the Director for Planning and Development. 5. That authority be delegated to the Director for Planning and Development, the S151 Officer and Monitoring Officer in consultation with the Leader and Portfolio Holder for Finance and Governance, to enter into a formal agreement for lease with the prospective tenant on appropriate market terms, and that the principle of the capital commitment of doing so is recognised, and the financial risk if the commitments in the agreement to lease are not fulfilled, be recognised. 6. That the Council approves the allocation of £2 million from the General Fund to the Capital and Revenue Initiatives Reserve and that this sum is vired into the Development Programme Budget. 7. That the S151 Officer in consultation with the Portfolio Holder for Finance and Governance is requested to bring back a report to a future meeting with options to address the revenue implications for funding the capital cost of the project, when or before the capital request is being considered.

This report relates to the following Five Year Plan Key Objectives:  A Prosperous Borough  A Green Borough  A Confident Borough The report supports delivery of the Council’s Five Year Plan and seeks to progress the redevelopment of the theatre, provide brand new office space and improve the entrance setting to Calverley Grounds whilst protecting the historic integrity of the listed civic suite of buildings and providing a masterplan framework within which this place shaping may take place to complement and enhance Tunbridge Wells.

Timetable Meeting Date Management Board 24 May 2016 Discussion with Portfolio Holder 20 May 2016 Cabinet Advisory Board 7 June 2016 Cabinet 22 June 2016 Council 20 July 2016 Other committee(s) Overview and Scrutiny Tunbridge Wells Committee Report, version: April 2016 * Civic Complex – Review of Stage 1 and Next Steps

1. PURPOSE OF REPORT AND EXECUTIVE SUMMARY

1.1The borough has a clear and ambitious vision to ‘grow our role as the cultural centre of the Kent & Sussex High Weald, so that by 2024 the borough of Tunbridge Wells is nationally recognised for its vibrant cultural provision’. Having a modern theatre sits at the heart of this vision. Likewise, the commitment to deliver a modern theatre fit for the 21st Century, is a key component of the Council’s Five Year Plan.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
* Civic Complex: Review of Stage 1 and Next StepsReport 255 KB DownloadRead as text
PDF
11a Civic Complex: Review of Stage 1 and Next Steps: Appendix A: Approvals /16Appendix 118 KB Download
PDF
11b Civic Complex: Review of Stage 1 and Next Steps: Appendix B: Summary /16Appendix 169 KB Download
PDF
11c Civic Complex: Review of Stage 1 and Next Steps: Appendix C: Projection /16Appendix 151 KB Download
PDF
11d Civic Complex: Review of Stage 1 and Next Steps: Appendix D: Timeline /16Appendix 46 KB Download

At this meeting

Whole meeting

On this subject at Tunbridge Wells

Search all
  1. * Civic Complex - Review of Stage 1 and Next StepsThis decision
  2. Civic Complex Cross-Party Working Group UpdateNoted
  3. Civic Complex Planning Development Framework Supplementary Planning DocumentNoted
  4. Civic Complex Development - Portfolio Holder UpdateNoted
  5. Civic Complex DevelopmentNoted
  6. Civic Complex - Assembly Hall Theatre Mandate Next StepsAgreed

More from Tunbridge Wells Cabinet

All decisions
MeetingDecisionOutcome
24 Sep 2026 Treasury and Prudential Indicator Management Report Quarter 1RESOLVED – 1. That the Treasury Management and Prudential Indicator position for 2026/27 be noted. 2. That the foreca... Noted Open
24 Sep 2026 Capital Management Report Quarter 1RESOLVED – 1. That the actual gross expenditure and that net of revenue for the year and the sources of finance, as s... Noted Open
24 Sep 2026 Revenue Management Report Quarter 1RESOLVED – 1. That the Quarter 1 net expenditure on services to the end of June 2026 was £5,414,000, £102,000 less th... Noted Open
24 Sep 2026 New Updated Planning Validation Checklist (Post Public Consultation)RESOLVED – 1. That the Draft Tunbridge Wells Local Validation List be adopted and used in the validation and processi... Approved Open
24 Sep 2026 Update on the Full Council Motion regarding the Maintenance of The Pantiles ColonnadeRESOLVED – 1. That the report covering the updates on the Full Council motion (FC103/25) on the Pantiles be noted. 2.... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies