RESOLVED – 1. That the actual gross and net expenditure for the year and the sources of finance, as shown in Appendices B to D of the report, be noted; 2. That the proposed movement between years set out in paragraph 4.3 to 4.4 of the report be approved; 3. That the proposed variations to the 2016/17 Capital programme set out in paragraphs 4.5 to 4.19 of the report be approved; and 4. That the new proposed schemes set out in paragraphs 4.20 to 4.23 of the report be approved. REASON FOR DECISION: Managing and forecasting capital expenditure effectively is vital in order to support all of the services provided by the Council.
Word for word from the decision Tunbridge Wells published for this meeting.Source: democracy.tunbridgewells.gov.uk
Cabinet 22 June 2017 Is the final decision on the recommendations in this report to be made at this meeting? Yes
Capital Management Report: Quarter 4 (to 31 March 2017) Final Decision-Maker Cabinet Portfolio Holder(s) Councillor David Reilly – Portfolio Holder for Finance and Governance Lead Director Lee Colyer – Director of Finance, Policy & Development Head of Service Jane Fineman – Head of Finance, Procurement & Parking Lead Officer/Author Zoe Jagniaszek – Service Accountant Classification Non-exempt Wards affected All
This report makes the following recommendations to the final decision-maker: 1. That the actual gross and net expenditure for the year and the sources of finance, as shown in Appendices B to D of the report, be noted;
2. That the proposed movement between years set out in paragraph 4.3 to 4.4 of the report be approved;
3. That the proposed variations to the 2016/17 Capital programme set out in paragraphs 4.5 to 4.19 of the report be approved; and
4. That the new proposed schemes set out in paragraphs 4.20 to 4.23 of the report be approved.
This report relates to the following Five Year Plan Key Objectives: This report supports all of the Key Objectives. Managing and forecasting capital expenditure effectively is vital in order to support all of the services provided by the Council.
Timetable Meeting Date Management Board 10 May 2017 Discussion with Portfolio Holder 30 May 2017 Cabinet Advisory Board 30 May 2017 (Verbal Update) Cabinet 22 June 2017 Capital Management Report: Quarter 4 (to 31 March 2017)
1. PURPOSE OF REPORT AND EXECUTIVE SUMMARY
1.1This report summarises the actual outturn expenditure on capital schemes as at the 31 March 2017. The total capital expenditure is £7,823,000, a reduction of £1,851,000 from the previously approved budgets. This consists of a net decrease of £1,310,000 in spending rescheduled to and from 2017/18, new schemes totalling £48,000 and a decrease in the forecast project spend of £589,000.
2. INTRODUCTION AND BACKGROUND
2.1At their meeting on 3 March 2016, Cabinet approved schemes to be met from the Capital Programme for the years 2016/17 to 2018/19.
2.2The figures approved by Cabinet were on the basis of the net cost after specific funding to be met by the Council, either from reserves or from the sale of existing assets. The total approved spending was £18,508,000 during that period, of which £15,999,000 was to be spent during 2016/17.
2.3As the Capital Programme is a 4 year rolling plan an additional £740,000 for 2019/20, has now been approved. This consists of Disabled Facility Grants, Housing Revenue Advances, Community Grants, Conservation Area Enhancement and Heritage Partner Grants.
2.4As shown in Appendix A, the approved programme for 2016/17 moved to £17,116,000 by the end of the 2015/16 financial year, accounting for new schemes, deletions and deferrals into future years.
2.5New movements for 2016/17 result in an actual spend of £7,823,000 a reduction on the approved £9,674,000 as at quarter 3.
2.6Appendices B and C set out in gross and net terms the actual spend and amounts approved against the forecast outturn to 31 March 2017, while Appendix D summarises the movement in approvals and in sources of finance for the year.
2.7Approval is sought for £1,375,000 gross expenditure to be deferred into future years and £65,000 to be rescheduled from 2017/18 into the current year. Also there is a decrease in the forecast projected spend of £589,000 (see notes 4.5 to 4.19).
2.8Approval is also sought for increases in the overall capital programme of £120,000 in 2017/18 (see notes 4.20 to 4.23). 3. AVAILABLE OPTIONS
3.1This report is mainly for information, giving the actual spend for 2016/17.
3.2Retain the approved rolling capital programme as at the end of Quarter 3. This would not reflect delays, advancements, underspends or new schemes and therefore provide an inaccurate forecast to the end of the financial year.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Capital Management Report Quarter 1RESOLVED – 1. That the actual gross expenditure and that net of revenue for the year and the sources of finance, as s...
Revenue Management Report Quarter 1RESOLVED – 1. That the Quarter 1 net expenditure on services to the end of June 2026 was £5,414,000, £102,000 less th...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.