Resolved
RESOLVED – That the report be noted.
Joint Transportation Board noted this item on Monday 17 July 2017. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED – That the report be noted.
That the report be noted.
1 Introduction
1.1Following the previous JTB on Monday 9th January it was agreed Kent County Council (KCC) would meet members of the Calverley Park Gardens (CPG) residents association to discuss their concerns. This would enable KCC to hear first-hand the issues experienced at CPG and identify the Residents association’s objectives.
1.2A meeting was arranged for Friday 10th February with KCC, TWBC and CPG residence association representatives, chaired by Cllr Peter Bulman. The representatives of CPG highlighted the current situation and what they would like to see introduced to mitigate these issues. It was agreed that CPG residents association would submit their request in order of priority with their resolutions to the issues in an immediate, short and long term plan for consideration and review by KCC officers.
2 CPG’s report of Improvements required
2.1Main issues: Inappropriate and over use of HGVs Vehicles using this route are causing congestion High speeds of vehicles using CPG No safe crossing point for pedestrians and cyclists
2.2Immediate implementation solutions: HGV Ban – including signage Implement a 20mph speed limit – including flashing signs in both directions and painted roundels on the carriageway along with appropriate signage Vehicle restriction Barrier – preventing motorised traffic except for access
2.3Short term implementation solutions: Raising and widening of pedestrian islands – including pedestrian barriers at both ends of CPG Physical traffic calming Bike stands Improvements to Lansdowne Road pedestrian facilities
2.4Long term implementation solutions: Implementation of the shared space design Appendix A (Royal Tunbridge Wells Public Real Framework, 2016) – including alterations
3 KCC Review of CPG issues
3.1KCC is keen to understand local concerns for safety within the community and the borough.
3.2Prior to the JTB 9th January, speed surveys and Non-Motorised Vehicle surveys had been ordered via KCC consultant company Amey TESC. The speed survey was carried out for from Monday 20th February to Sunday 26th February Appendix B shows the positioning and direction. The information was collated into Westbound Appendix C and Eastbound Appendix D. A key requirement on any possible improvements is that they must not have a negative impact on the A26 or the A264. These two routes are crucial arterial routes leading to and from the town centre, and KCC and TWBC are jointly working on improvement schemes to improve the capacity and flow of traffic on these routes, therefore any scheme or development that impacts negatively on these two routes would be contrary to the joint aims of both councils.
3.3Removing Calverley Park Gardens from the network (to just HGVs) had a detrimental impact on the Royal Oak junction and the volume of traffic on Pembury Road, which is contrary to KCC and TWBC joint aims.
3.4KCC and Kent Police use the mean speeds collated from speed surveys to determine the overall current speed of a road. Ascertained from the above appendices mean speed Westbound 26.9mph and mean speed Eastbound is 28.8mph. These speeds do not indicate there to be an issue currently experienced that would require immediate resolution.
3.5The survey also indicates that with current speeds, a new 20mph limit would not be achievable as a sign and lines only scheme. To be compliant, physical measures would also need to be incorporated to slow current speeds to the desired 20mph.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
13a Calverley Park Gardens Residents Association Response: Appendix A /17Appendix | 107 KB | Download |
PDF |
13b Calverley Park Gardens Residents Association Response: Appendix B /17Appendix | 119 KB | Download |
PDF |
13c Calverley Park Gardens Residents Association Response: Appendix C /17Appendix | 50 KB | Download |
PDF |
13d Calverley Park Gardens Residents Association Response: Appendix D /17Appendix | 51 KB | Download |
PDF |
13e Calverley Park Gardens Residents Association Response: Appendix E /17Appendix | 57 KB | Download |
PDF |
Calverley Park Gardens Residents' Association ResponseReport | 273 KB | DownloadRead as text |
Follow Joint Transportation Board at Tunbridge Wells and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 13 Jul 2026 | Minutes of the meeting dated 20 April 2026RESOLVED : That the minutes of the Joint Transportation Board meeting dated 20 April 2026 be accepted as an accurate ... | Decided | Open |
| 13 Jul 2026 | Parking Consultation York Road and Dudley Road, Tunbridge WellsRESOLVED – That the Joint Transport Board notes the results of a public consultation proposing changes to waiting res... | Decided | Open |
| 13 Jul 2026 | Active Travel UpdateRESOLVED – The report was noted. | Noted | Open |
| 20 Apr 2026 | Minutes of the meeting dated 2 February 2026RESOLVED – That the minutes of the meeting dated 2 February 2026 be approved as a correct record. | Approved | Open |
| 20 Apr 2026 | Parish Highways Improvement Projects GrantsRESOLVED – The report was noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.