Resolved
RESOLVED – That the risk management report and arrangements for managing strategic risk be noted.
Audit and Governance Committee noted this item on Tuesday 25 July 2017. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED – That the risk management report and arrangements for managing strategic risk be noted.
Audit & Governance 25 July 2017 Committee Is the final decision on the recommendations in this report to be made at this meeting? Yes
Strategic Risk Review Final Decision-Maker Audit & Governance Committee Portfolio Holder(s) All Lead Director Lee Colyer – Director of Finance, Policy and Development Head of Service Jane Clarke – Head of Policy & Governance Lead Officer/Report Author Lee Colyer – Director of Finance, Policy and Development Classification Non-Exempt Wards affected All
This report makes the following recommendations to the final decision-maker:
1. That the Committee notes the risk management report and arrangements for managing strategic risk.
This report relates to the following Five Year Plan Key Objectives: A Prosperous Borough A Green Borough A Confident Borough
This report is concerned with the internal control and governance of the Council. Successful controls and effective governance are a crucial underpinning for all corporate priorities.
Timetable Meeting Date Management Board 19 July 2017 Audit and Governance Committee 25 July 2017 Strategic Risk Register
1. PURPOSE OF REPORT AND EXECUTIVE SUMMARY
1.1The report sets out the strategic risks identified by the Council and currently being managed and tracked by senior management. The report provides a current update on the evaluated threat level and controls in place for each risk issue.
2. INTRODUCTION AND BACKGROUND
2.1The risks included in the report were initially developed in a risk management workshop facilitated by Zurich Management Services on 10 December 2013, with the risks being formally adopted by Cabinet on 16 May 2014. Since that time, risk owners have kept the risks and controls under review with periodic reporting both to the Cabinet and the Audit & Governance Committee.
2.2Following the award of a new insurance contract a strategic risk management review will be undertaken.
2.3The Council’s Management Board periodically reviews the risks identified along with the risk owners.
2.4Risk owners (managers) for certain risks are invited to attend the Audit and Governance Committee meetings to outline the Council’s approach to managing their particular risk(s). For this Committee meeting, members will be able to examine the risks owned by Karen Fossett, Head of Planning, namely;
Risk 1: Cinema site remains undeveloped; and Risk 8: Inspector decision which challenges housing target vs housing supply.
3. AVAILABLE OPTIONS
3.1There is no legal requirement on the authority formally to monitor its risks, still less is there a defined framework to do so. Although failing to monitor and record risks will leave the Council vulnerable to external criticism – for example by its external auditors who are required to assess the effectiveness of risk management when considering their annual Value For Money conclusion – the Council could decide that is a price worth paying against using some of its resources to identify and monitor risk.
3.2Even accepting the utility in gathering systematic monitoring information on the risks it faces, there is a wide range of different approaches the Council might adopt. Even if one looks solely at the local government sector, there are myriad formats, structures and arrangements adopted to record and present information to senior officers and members. 4. PREFERRED OPTION AND REASONS FOR RECOMMENDATIONS
4.1The report sets out the risks using the methodology and format previously agreed by the Council, which is essentially the method advocated by Zurich from the 2013 risk workshop.
5. CONSULTATION RESULTS AND PREVIOUS COMMITTEE FEEDBACK
5.1The Strategic Risk Register has undergone periodic review and examination by the Council’s Management Board, the Cabinet and the Audit & Governance Committee. This stands in addition to ongoing monitoring by the identified risk owners. This report incorporates feedback and updates from all sources.
6. CROSS-CUTTING ISSUES AND IMPLICATIONS
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Item 5(B): Strategic Risk Register July: Appendix A /17Appendix | 340 KB | Download |
PDF |
Strategic Risk ReportReport | 108 KB | DownloadRead as text |
Follow Audit and Governance Committee at Tunbridge Wells and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 2 Jul 2026 | Minutes of the meeting of the Audit and Governance Committee dated 10 March 2026RESOLVED – That the minutes of the meeting dated 10 March 2026 be approved as a correct record. | Approved | Open |
| 2 Jul 2026 | Future Work Programme as at 2 July 2026RESOLVED – That the Future Work Programme as at 2 July 2026, be noted. | Noted | Open |
| 2 Jul 2026 | External Audit Progress and Sector Update ReportRESOLVED - That the committee consider and agree the Audit Progress and Sector Update Report. | Agreed | Open |
| 2 Jul 2026 | Internal Audit Report & Annual Audit Opinion 2025/26RESOLVED – 1. That the Audit & Governance Committee notes the Head of Audit Partnership opinion. 2. That the Audit & ... | Decided | Open |
| 10 Mar 2026 | Minutes of the meeting of the Audit and Governance Committee dated 25 November 2025RESOLVED – That the minutes of the meeting dated 25 November 2026 be approved as a correct record. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.