RESOLVED – That Full Council be recommended: 1. That the Crescent Road Car Park extension project, designed to RIBA Stage 3 (Developed Design) in accordance with Cabinet Decision CAB157/16 on 9 February 2017, be approved; 2. That funds be made available to procure and deliver the project up to a capital cost detailed in Exempt Appendix A plus VAT; and 3. That authority to procure, deliver and complete the project be delegated to the Head of Economic Development and Property in consultation with the Leader, the Portfolio Holder for Finance and Governance, the Director of Finance, Policy and Development (S.151 Officer) and the Monitoring Officer. REASON FOR DECISION: To ensure that an area of public asset that is currently underutilised is brought into revenue producing use by the provision of the new parking bays, relieving displaced parking from development and supporting the financial objectives of the Council.
Word for word from the decision Tunbridge Wells published for this meeting.Source: democracy.tunbridgewells.gov.uk
Cabinet 14 September 2017 Is the final decision on the recommendations in this report to be made at this meeting? No
* Crescent Road Car Park Tunbridge Wells – Proposed Extension Final Decision-Maker Full Council Portfolio Holder(s) Councillor David Jukes – Leader or the Council Lead Director Lee Colyer – Director of Finance, Policy and Development Head of Service David Candlin – Head of Economic Development and Property Lead Officer/Author Diane Brady – Civic Development Manager Classification Part Exempt Exempt Appendices A and B exempt by virtue of paragraph 3 of Schedule 12A of the Local Government Act 1972 (as amended): Information relating to the financial or business affairs of any particular person including the authority holding that information. Wards affected All
This report makes the following recommendations to the final decision-maker: 1. That the project designed to RIBA Stage 3 (Developed Design) in accordance with Cabinet Decision CAB157/16 on 9 February 2017 be approved for funding and delivery;
2. That funds be made available to procure and deliver the project up to a capital cost detailed in Exempt Appendix A plus VAT; and
3. That authority to procure, deliver and complete the project be delegated to the Head of Economic Development and Property in consultation with the Leader, the Portfolio Holder for Finance and Governance, the Director of Finance, Policy and Development (S.151 Officer) and the Monitoring Officer.
This report relates to the following Five Year Plan Key Objectives: A Prosperous Borough A Green Borough A Confident Borough Timetable Meeting Date Management Board (Verbal update) Wednesday 2 August 2017 Discussion with Portfolio Holder Monday 14 August 2017 Planning and Transportation Cabinet Advisory Board Monday 21 August 2017 Finance and Governance Cabinet Advisory Board Tuesday 22 August 2017 Cabinet Thursday 14 September 2017 Council Wednesday 27 September 2017 * Crescent Road Car Park Tunbridge Wells – Proposed Extension
1. PURPOSE OF REPORT AND EXECUTIVE SUMMARY
1.1In February 2017 Cabinet approved the design of an extension to the Crescent Road car park, Tunbridge Wells to RIBA Stage 3 (Developed Design). This work has been completed
1.2This report now seeks to summarise the proposed works, project timetable and indicative budget costs, to identify the benefits of the proposed extension and to seek authority to fund the extension project.
1.3The report also requests that authority be delegated to the Head of Economic Development & Property in consultation with the Leader, the Portfolio Holder for Finance and Governance, the S 151 Officer and the Monitoring Officer to procure, undertake and complete the project.
2. INTRODUCTION AND BACKGROUND
2.1Crescent Road Car Park is a multi storey car park constructed in the 1970s and currently provides 1069 car parking spaces in the Town Centre. The freehold title of the site on which the car park is located is owned by Tunbridge Wells Borough Council and the extent of the freehold ownership exceeds the footprint of the current structure. The location of the car park and extent of the site in Council’s ownership is shown at Appendix A.
2.2It is recognised that there is a need to provide further parking in the town to ease parking congestion on the streets and accommodate those vehicles that are displaced through parking management, to continue to support the revenue receipt to the Council, to facilitate proposed future development and to accommodate potential future changes to town centre parking and the provision of shared space and public realm.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Capital Management Report Quarter 1RESOLVED – 1. That the actual gross expenditure and that net of revenue for the year and the sources of finance, as s...
Revenue Management Report Quarter 1RESOLVED – 1. That the Quarter 1 net expenditure on services to the end of June 2026 was £5,414,000, £102,000 less th...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.