RESOLVED – 1. That at Quarter 3 the net expenditure on services year to date was £8.601 million, £258,000 less than forecast, be noted; 2. That by year end the Council anticipated net expenditure of £14.358 million on services, £450,000 under budget and an improvement of £234,000 from Quarter 1, and that expected additional grant income of £102,000 reported at Quarter 2 bringing the overall forecast underspend to £552,000, be noted; 3. That the establishment of a ‘Rent Advance and Deposit Reserve’ to hold money set aside by the Council to fund the rent advance and deposit guarantee schemes be approved; and 4. That the Write Offs explained at paragraph 2.28 of the report and detailed at Appendix J to the report be approved. REASON FOR DECISION: To show the actual expenditure on services compared to the revised budget for the period ended 30 December 2017, and the forecast outturn position, highlighting significant variances from the revised annual budget.
Word for word from the decision Tunbridge Wells published for this meeting.Source: democracy.tunbridgewells.gov.uk
Cabinet 1 March 2018 Is the final decision on the recommendations in this report to be made at this meeting? Yes
Revenue Management Report: Quarter 3 (to 31 December 2017) Final Decision-Maker Cabinet Portfolio Holder(s) Councillor David Reilly – Portfolio Holder for Finance and Governance Lead Director Lee Colyer – Director of Finance, Policy & Development Head of Service Jane Fineman – Head of Finance and Procurement Lead Officer/Report Author Clare Hazard – Accountancy Manager Classification Non-Exempt Wards affected All
This report makes the following recommendations to the final decision-maker:
1. That at Quarter 3 the net expenditure on services year to date was £8.601 million, £258,000 less than forecast be noted;
2. That by year end the Council anticipates net expenditure of £14.358 million on services, £450,000 under budget and an improvement of £234,000 from Quarter 1, and that expected additional grant income of £102,000 reported at Quarter 2 bringing the overall forecast underspend to £552,000, be noted;
3. That the establishment of a ‘Rent Advance and Deposit Reserve’ to hold money set aside by the Council to fund the rent advance and deposit guarantee schemes be approved;
4. That the Write Offs explained at paragraph 2.28 and detailed in Appendix J be approved.
This report relates to the following corporate priorities: A Prosperous Borough A Green Borough A Confident Borough
Timetable Meeting Date Management Team 17 January 2018 (Verbal update) Cabinet Advisory Board 6 February 2018 (Verbal update) Cabinet 1 March 2018 Revenue Management Report: Quarter 3 (to 31 December 2017)
1. PURPOSE OF REPORT AND EXECUTIVE SUMMARY
1.1This report shows the actual expenditure on services compared to the revised budget for the period ended 31 December 2017, and the forecast outturn position, highlighting significant variances from the revised annual budget.
1.2The net expenditure on services for the year is forecast to be £14,358,000 which is an underspend to budget of £450,000.
2. INTRODUCTION AND BACKGROUND
Summary Outturn – See Appendix A 2.1 Appendix A shows the overall income and net expenditure on services outturn position as at 31 December 2017. Total income and expenditure on services can be seen in greater detail within Appendix B, which provides information per service area. The approved budget was set by Full Council on 22 February 2017 and does not change. The revised budget is used to record virements amongst service areas and from reserves, whilst the forecast outturn is used to record the reporting of savings, overspends and allocations from reserves.
2.2It can be seen that the forecast outturn for expenditure on services is £14,358,000 which is £450,000 below budget. The various movements to forecast can be seen in Appendix C.
2.3Investment interest is forecast to be £700,000, an increase of £70,000 against budget. The forecast for investments is based on an overall interest rate of 1.69% and average funds of £41.5m. The additional interest will be transferred to the Strategic Plan Reserve. The outstanding PWLB loan is now £6 million. Interest is being paid at 2.38%, the total cost of which is £145,310 for 2017/18.
2.4Appendices A and F show that £160,000 has been recorded and transferred to the Vacancy Factor from Directorate budgets, which is the full requirement for the year. Vacancy factor is the saving created whilst a budgeted post is vacant.
Usable Reserves – See Appendix D 2.5 Appendix D shows all usable reserves including the earmarked reserves. Usable reserves are those that the Council can use to provide services, subject to the need to maintain an overall prudent level of reserves. Earmarked reserves are amounts set aside to meet identified, and often committed, future liabilities.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Capital Management Report Quarter 1RESOLVED – 1. That the actual gross expenditure and that net of revenue for the year and the sources of finance, as s...
Revenue Management Report Quarter 1RESOLVED – 1. That the Quarter 1 net expenditure on services to the end of June 2026 was £5,414,000, £102,000 less th...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.