Resolved
RESOLVED – That the Audit and Governance Committee considered and agreed the Audit Plan.
Audit and Governance Committee agreed this item on Tuesday 2 April 2019. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED – That the Audit and Governance Committee considered and agreed the Audit Plan.
Audit and Governance 2 April 2019 Committee Is the final decision on the recommendations in this report to be made at this meeting? Yes
External Audit Plan Final Decision-Maker Audit and Governance Committee Portfolio Holder(s) Cllr. David Reilly Lead Director Lee Colyer, Director of Finance, Policy and Development Head of Service Jane Fineman, Head of Finance and Procurement Lead Officer/Report Author Lee Colyer, Director of Finance, Policy and Development Classification Non-exempt Wards affected All
This report makes the following recommendation(s) to the final decision-maker: 1. That the Audit and Governance Committee consider and agree the appended audit plan.
This report relates to the following Five Year Plan Key Objectives: A Prosperous Borough A Confident Borough
Timetable Meeting Date Management Board 13 March 2019 Discussion with Portfolio Holder 11 March 2019 External Audit Plan
1. PURPOSE OF REPORT AND EXECUTIVE SUMMARY
1.1This report outlines the audit work that the external auditor, Grant Thornton, propose to undertake for the audit of the 2018/19 financial statements and the value for money assessment.
1.2The report also includes the outcome of the certification work for the Housing Benefit subsidy claim for 2017/18.
2. INTRODUCTION AND BACKGROUND
2.1Under the 2015 Accounts and Audit Regulations local authorities are required to publish their accounts along with the auditor’s opinion by 31 July 2019.
2.2The audit of the financial statements is planned on a risk-based approach and reflects:
Audit work specified by the external auditor; Current national risks relevant to local circumstances; and The Council’s local risks.
2.3The National Audit Office has issued a document entitled Code of Audit Practice which summaries the responsibilities of the auditor and the audited body.
2.4The audit work will be undertaken in compliance with the statutory requirements governing audit work, in particular:
The Local Audit and Accountability Act 2014; International Standard on Auditing (UK & Ireland) 260; and The Code of Audit Practice for Local Authorities.
2.5At the conclusion of the audit the external auditor will issue an audit report giving an opinion on whether the accounts give a true and fair view of the financial position of the Council as at 31 March 2019.
2.6A copy of the audit plan is attached as an appendix to this report. The proposed fees are £39,447 (previous year £51,230) for the financial statement and £12,144 for the grant certification plus £10,000 for additional testing.
Results of the 2017/18 Certification Work
2.7Grant Thornton certified the Housing Benefit subsidy claim for the financial year 2017/18 relating to subsidy claimed of £33.7 million. Four issues have been highlighted arising from the certification work which resulted in additional sample testing. Due the errors identified the claim was qualified along with all those of other district councils in Kent in accordance with the DWP’s methodology. Further details are set out in Appendix B.
3. AVAILABLE OPTIONS
3.1The Audit and Governance Committee could choose not to accept the proposed audit plan.
4. PREFERRED OPTION AND REASONS FOR RECOMMENDATIONS
4.1The audit plan sets out the audit work proposed by the external auditors for the audit of the 2018/19 financial statements.
4.2The Audit and Governance Committee’s function and delegations, as outlined in its constitution and terms of reference state, that it should:
agree the external audit plan for the year; approve the cost of the audit; consider specific reports as agreed with the external audit work and ensure it gives value for money; and comment on the scope and depth of external audit work to ensure it gives value for money.
5. CONSULTATION RESULTS AND PREVIOUS COMMITTEE FEEDBACK
5.1The external auditor has consulted with the Chief Executive and the Director of Finance, Policy and Development. The Audit and Governance Committee is now being asked for their approval.
6. NEXT STEPS: COMMUNICATION AND IMPLEMENTATION OF THE DECISION
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
/18Appendix A | 441 KB | Download |
PDF |
/18Appendix B | 168 KB | Download |
PDF |
External Audit PlanReport | 112 KB | DownloadRead as text |
Follow Audit and Governance Committee at Tunbridge Wells and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 2 Jul 2026 | Minutes of the meeting of the Audit and Governance Committee dated 10 March 2026RESOLVED – That the minutes of the meeting dated 10 March 2026 be approved as a correct record. | Approved | Open |
| 2 Jul 2026 | Future Work Programme as at 2 July 2026RESOLVED – That the Future Work Programme as at 2 July 2026, be noted. | Noted | Open |
| 2 Jul 2026 | External Audit Progress and Sector Update ReportRESOLVED - That the committee consider and agree the Audit Progress and Sector Update Report. | Agreed | Open |
| 2 Jul 2026 | Internal Audit Report & Annual Audit Opinion 2025/26RESOLVED – 1. That the Audit & Governance Committee notes the Head of Audit Partnership opinion. 2. That the Audit & ... | Decided | Open |
| 10 Mar 2026 | Minutes of the meeting of the Audit and Governance Committee dated 25 November 2025RESOLVED – That the minutes of the meeting dated 25 November 2026 be approved as a correct record. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.