RESOLVED – That the actual gross and net expenditure for the year and the sources of finance as shown in Appendices B to D to the report be noted; and That the proposed variations to the 2019/20 Capital programme as set out in paragraphs 4.3 to 4.5 be approved. REASON FOR DECISION: Managing and forecasting capital expenditure effectively was vital in order to support all of the services provided by the Council.
Word for word from the decision Tunbridge Wells published for this meeting.Source: democracy.tunbridgewells.gov.uk
Cabinet 12 September 2019 Is the final decision on the recommendations in this report to be made at this meeting? Yes
Capital Management Report: Quarter 1 (to 30 June 2019) Final Decision-Maker Cabinet Portfolio Holder(s) Councillor Tom Dawlings – Portfolio Holder for Finance and Governance Lead Director Lee Colyer – Director of Finance, Policy and Development Head of Service Jane Fineman – Head of Finance and Procurement Lead Officer/Author Zoe Jagniaszek – Service Accountant Classification Non-exempt Wards affected All
This report makes the following recommendations to the final decision-maker:
1. That the actual gross and net expenditure for the year and the sources of finance, as shown in Appendices B to D, be noted;
2. That the proposed variations to the 2019/20 Capital programme, set out in paragraphs 4.3 to 4.5, be approved.
This report relates to the following Five Year Plan Key Objectives: This report supports all of the Key Objectives. Managing and forecasting capital expenditure effectively is vital in order to support all of the services provided by the Council.
Timetable Meeting Date Management Board 31 July 2019 (Verbal update) Discussion with Portfolio Holder 20 August 2019 Cabinet Advisory Board 20 August 2019 Cabinet 12 September 2019 Tunbridge Wells Committee Report, version: April 2017 Capital Management Report: Quarter 1 (to 30 June 2019)
1. PURPOSE OF REPORT AND EXECUTIVE SUMMARY
1.1This report summarises the actual and forecast outturn expenditure on capital schemes as at the 30 June 2019. The total capital expenditure is forecast to be £23,953,000, an increase of £29,000 from the previously approved budgets. An increase of £854,000 is also included for approval for the year 2022/23.
2. INTRODUCTION AND BACKGROUND
2.1At their meeting on 7 March 2019, Cabinet approved schemes to be met from the Capital Programme for the years 2019/20 to 2021/22.
2.2The figures approved by Cabinet were on the basis of the net cost after specific funding to be met by the Council, either from reserves or from the sale of existing assets. The total approved spending was £104,301,000 during that period, of which £22,681,000 was to be spent during 2019/20.
2.3As shown in Appendix A, the approved programme for 2019/20 moved to £23,925,000 by the end of the 2018/19 financial year, accounting for new schemes, deletions and deferrals into future years and was approved by Cabinet on 27 June 2019.
2.4As the Capital Programme is a 4 year rolling plan an additional £854,000 has been included for approval for 2022/23. This consists of Disabled Facilities Grants and Housing Renewal advances.
2.5New movements for 2019/20 are now forecasting an outturn of £23,953,000.
2.6Appendices B and C set out in gross and net terms the actual spend and amounts approved against the forecast outturn to 31 March 2020, while Appendix D summarises the movement in approvals and in sources of finance for the year.
2.7Approval is sought for an increase in the capital programme of £29,000 (see paragraphs 4.3 to 4.5).
2.8There may be small differences in the figures within the report and appendices due to rounding.
3. AVAILABLE OPTIONS
3.1Retain the approved rolling capital programme as at the end of Quarter 4 2018/19. This would not reflect delays, advancements, underspends or new schemes and therefore provide an inaccurate forecast to the end of the financial year.
3.2Amend the rolling capital programme to reflect changes since the end of Quarter 4 2018/19. These projections help to manage the public finances effectively which support the objectives and priorities of the Council.
4. PREFERRED OPTION AND REASONS FOR RECOMMENDATIONS
New Budget Approvals 4.1 Appendix A shows how the approved capital expenditure has evolved since the programme was first agreed (CAB 148/18). The amounts approved for schemes at the June Cabinet meeting have been added to the figure then reported as total approvals to date.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Capital Management Report Quarter 1RESOLVED – 1. That the actual gross expenditure and that net of revenue for the year and the sources of finance, as s...
Revenue Management Report Quarter 1RESOLVED – 1. That the Quarter 1 net expenditure on services to the end of June 2026 was £5,414,000, £102,000 less th...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.