RESOLVED – 1. That the contractual obligation on the council as the freeholder of the long leasehold interest between the Council and British Land consent to the proposed mall refresh refurbishment works and to contribute to the full cost of such works as provided for under the terms of the lease be noted; and 2. That the Head of Economic Development and Property in consultation with the Monitoring Officer, the Director of Finance, Policy and Development, the Portfolio Holder for Finance and Governance and the Portfolio Holder for Property, Major Projects and Strategic Engagement be delegated authority to: a. Complete of all necessary negotiations, legal documentation and legal formalities and to appoint external solicitors to deal with such matters as considered appropriate; and b. Make all proven and necessary payments to ensure compliance with the lease obligations in relation to the identified Type 1 Qualifying Refurbishment works. REASON FOR DECISION: To allow the refurbishment works at Royal Victoria Place Shopping Centre to be taken forward.
Word for word from the decision Tunbridge Wells published for this meeting.Source: democracy.tunbridgewells.gov.uk
Cabinet 24 October 2019 Is the final decision on the recommendations in this report to be made at this meeting? Yes
Royal Victoria Place Tunbridge Wells Update Final Decision-Maker Cabinet Portfolio Holder(s) Councillor David Scott – Portfolio Holder for Property, Major Projects and Strategic Engagement Councillor Tom Dawlings – Portfolio Holder for Finance and Governance Lead Director Lee Colyer Director of Finance, Policy & Development (S151 Officer) Head of Service David Candlin – Head of Economic Development & Property Lead Officer/Author Diane Brady – Property , Estates and Development Lead Classification Part Exempt Appendices exempt by virtue of paragraph 3 of Schedule 12A of the Local Government Act 1972 (as amended): Information relating to the financial or business affairs of any particular person including the authority holding that information. Wards affected Park
This report makes the following recommendations to the final decision-maker:
1. To note the contractual obligation on the Council as the freeholder of the long leasehold interest between the Council and British Land to consent to the proposed mall refresh refurbishment works and to contribute to the full cost of such works as provided for under the terms of the lease and
2. To delegate to the Head of Economic Development and Property in consultation with the Monitoring Officer, the Director of Finance, Policy and Development, the Portfolio Holder for Finance and Governance and the Portfolio Holder for Property, Major Projects and Strategic Engagement the authority to – (i) complete all necessary negotiations, legal documentation and legal formalities and to appoint external solicitors to deal with such matters as considered appropriate and (ii) make all proven and necessary payments to ensure compliance with the lease obligations in relation to the identified Type 1 Qualifying Refurbishment works.
This report relates to the following Five Year Plan Key Objectives: A Prosperous Borough – by making the best use of land and property assets for the benefit of residents and in encouraging future growth and investment by marketing opportunities that the Borough owns. The Five Year Plan (2017-22) sets out an overarching vision as follows:” To encourage investment and sustainable growth and to enhance quality of life for all” It also sets out a commitment that “at times we will need to invest to create the best opportunities for ….additional income” Timetable Meeting Date Management Board 11/09/2019 Discussion with Portfolio Holder 2 September 2019 Finance & Governance Cabinet Advisory 1 October 2019 Board Cabinet 24 October 2019 Tunbridge Wells Committee Report, version: April 2017 Royal Victoria Place Tunbridge Wells Update
1. PURPOSE OF REPORT AND EXECUTIVE SUMMARY
1.1This report seeks to notify Cabinet of the intention of the long leaseholder, BL Tunbridge Wells Ltd (British Land) to undertake refurbishment works to the Royal Victoria Place Shopping Centre and to note and confirm the Council’s obligation to contribute towards the cost of such works as provided for under the terms of the long leasehold interest.
1.2To note the summary specification of the proposed works to be undertaken and the proposed project programme for undertaking the works.
1.3To note the proposed estimated total cost of the works and the proportion of the cost of those works required to be contributed by the Council under the terms of the lease.
1.4To note that the figures in this report are estimates and to further note that the Council is obliged under the covenants of the lease to pay the landlord’s proportion of the actual costs of the Qualifying Refurbishment properly incurred.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Capital Management Report Quarter 1RESOLVED – 1. That the actual gross expenditure and that net of revenue for the year and the sources of finance, as s...
Revenue Management Report Quarter 1RESOLVED – 1. That the Quarter 1 net expenditure on services to the end of June 2026 was £5,414,000, £102,000 less th...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.