Capital Management Report: Quarter 2

Noted Executive 6 papers

Cabinet noted this item on Thursday 5 December 2019. Below is the council's own wording, with the papers it was decided on.

ItemCAB108/19

Resolved

RESOLVED – That the actual gross and net expenditure for the year and the sources of finance, as shown in Appendices B to D to the report be noted; That the proposed variations to the 2019/20 Capital programme set out in paragraphs 4.3 to 4.8 of the report be approved; That the inclusion of new schemes to the Capital programme set out in notes 4.9 to 4.14 be noted; and The proposed movement between years set out in paragraph 4.15 to 4.19 be approved. REASON FOR DECISION: Managing and forecasting capital expenditure effectively was vital in order to support all of the services provided by the Council.
Word for word from the decision Tunbridge Wells published for this meeting. Source: democracy.tunbridgewells.gov.uk

Follow this further

Built from Tunbridge Wells's papers

What the report saysPro

Report to Cabinet

Cabinet 5 December 2019 Is the final decision on the recommendations in this report to be made at this meeting? Yes

Capital Management: Quarter 2 (to 30 September 2019)

Final Decision-Maker Cabinet Portfolio Holder(s) Councillor Tom Dawlings – Portfolio Holder for Finance and Governance Lead Director Lee Colyer – Director of Finance, Policy & Development Head of Service Jane Fineman – Head of Finance & Procurement Lead Officer/Author Zoe Jagniaszek – Service Accountant Classification Non-exempt Wards affected All

This report makes the following recommendations to the final decision-maker: 1. That the actual gross and net expenditure for the year and the sources of finance, as shown in Appendices B to D, be noted; 2. That the proposed variations to the 2019/20 Capital programme, set out in paragraphs 4.3 to 4.8, be approved. 3. Cabinet note the inclusion of new schemes into the capital programme as set out in notes 4.9 to 4.14. 4. Approval is given for the proposed movement between years set out in paragraph 4.15 to 4.19.

This report relates to the following Five Year Plan Key Objectives: This report supports all of the Key Objectives. Managing and forecasting capital expenditure effectively is vital in order to support all of the services provided by the Council.

Timetable Meeting Date Management Board 17 October 2019 (Verbal update) Discussion with Portfolio Holder 12 November 2019 Cabinet Advisory Board 12 November 2019 Cabinet 5 December 2019 Tunbridge Wells Committee Report, version: April 2017 Capital Management: Quarter 2 (to 30 September 2019)

1. PURPOSE OF REPORT AND EXECUTIVE SUMMARY

1.1This report summarises the actual and forecast outturn expenditure on capital schemes as at the 30 September 2019. The total capital expenditure is forecast to be £20,866,000, a net reduction of £3,087,000 from the previously approved budgets. An increase of £1,593,000 approved by Cabinet on 24 October 2019 for the Culture and Learning Hub for 2020/21.

2. INTRODUCTION AND BACKGROUND

2.1At their meeting on 7 March 2019, Cabinet approved schemes to be met from the Capital Programme for the years 2019/20 to 2021/22. 2.2 The figures approved by Cabinet were on the basis of the net cost after specific funding to be met by the Council, either from reserves or from the sale of existing assets. The total approved spending was £104,301,000 during that period, of which £22,681,000 was to be spent during 2019/20. 2.3 As shown in Appendix A, the approved programme for 2019/20 moved to £23,925,000 by the end of the 2018/19 financial year, accounting for new schemes, deletions and deferrals into future years and was approved by Cabinet on 27 June 2019. 2.4 As the Capital Programme is a 4 year rolling plan an additional £854,000 has been included for approval for 2022/23. This consists of Disabled Facilities Grants and Housing Renewal advances. 2.5 New movements for 2019/20 are now forecasting an outturn of £20,866,000. 2.6 Appendices B and C set out in gross and net terms the actual spend and amounts approved against the forecast outturn to 31 March 2020, while Appendix D summarises the movement in approvals and in sources of finance for the year. 2.7 Approval is sought for a net decrease in the capital programme of £3,087,000 (see paragraphs 4.3 to 4.19). 2.8 There may be small differences in the figures within the report and appendices due to rounding.

3. AVAILABLE OPTIONS

3.1Retain the approved rolling capital programme as at the end of Quarter 1 2019/20. This would not reflect delays, advancements, underspends or new schemes and therefore provide an inaccurate forecast to the end of the financial year.

3.2Amend the rolling capital programme to reflect changes since the end of Quarter 1 2019/20. These projections help to manage the public finances effectively which support the objectives and priorities of the Council. 4. PREFERRED OPTION AND REASONS FOR RECOMMENDATIONS

New Budget Approvals

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
13 Appendix A: Approved Gross Expenditure /19Appendix 204 KB Download
PDF
13 Appendix B: Gross Budget and Actual Expenditure /19Appendix 151 KB Download
PDF
13 Appendix C: Net Budget and Payments /19Appendix 157 KB Download
PDF
13 Appendix D: Four Year Summary /19Appendix 114 KB Download
PDF
13 Appendix E: Capital application: Housing Renewal Advances /19Appendix 159 KB Download
PDF
Capital Management Report: Quarter 2Report 136 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at Tunbridge Wells

Search all
  1. Capital Management Report: Quarter 2This decision
  2. Capital Management Report Quarter 1Noted
  3. Capital Management Report Quarter 1Decided
  4. Capital Management Report Quarter 4Decided
  5. Capital Management Report Quarter 4Decided
  6. Capital Management Report Quarter 3Decided

More from Tunbridge Wells Cabinet

All decisions
MeetingDecisionOutcome
24 Sep 2026 Treasury and Prudential Indicator Management Report Quarter 1RESOLVED – 1. That the Treasury Management and Prudential Indicator position for 2026/27 be noted. 2. That the foreca... Noted Open
24 Sep 2026 Capital Management Report Quarter 1RESOLVED – 1. That the actual gross expenditure and that net of revenue for the year and the sources of finance, as s... Noted Open
24 Sep 2026 Revenue Management Report Quarter 1RESOLVED – 1. That the Quarter 1 net expenditure on services to the end of June 2026 was £5,414,000, £102,000 less th... Noted Open
24 Sep 2026 New Updated Planning Validation Checklist (Post Public Consultation)RESOLVED – 1. That the Draft Tunbridge Wells Local Validation List be adopted and used in the validation and processi... Approved Open
24 Sep 2026 Update on the Full Council Motion regarding the Maintenance of The Pantiles ColonnadeRESOLVED – 1. That the report covering the updates on the Full Council motion (FC103/25) on the Pantiles be noted. 2.... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies