RESOLVED – 1. That the actual gross and net expenditure for the year and the sources of finance, as shown in Appendices B to D to the report, be noted; 2. That the proposed variations to the Capital programme, set out in paragraph 4.3 to 4.7 of the report be approved; and 3. That the proposed movement between years set out in paragraph 4.8 of the report be approved. REASON FOR DECISION: Managing and forecasting capital expenditure effectively was vital in order to support all of the services provided by the Council
Word for word from the decision Tunbridge Wells published for this meeting.Source: democracy.tunbridgewells.gov.uk
Officer / Committee recommendations as supported by the Portfolio Holder: 1. That Cabinet note the actual gross and net expenditure for the year and the sources of finance, as shown in Appendices B to D. 2. That Cabinet approve the proposed variations to the Capital programme, set out in note 4.3 to 4.7. 3. That Cabinet approve the proposed movement between years set out in note 4.8.
Page Tunbridge Wells Borough Council 1 of 8 Quarter 2 – Capital Management to 30 September 2020 1. Introduction and Background 1.1 This report summarises the actual and forecast outturn expenditure on capital schemes as at the 30 September 2020. The total capital expenditure is forecast to be £19,652,000, a net increase of £1,690,000 from the previously approved budgets. This consists of a net decrease of £146,000 in spending rescheduled to and from 2021/22 and a net increase in the forecast projected spend of £1,836,000. An increase of £921,000 is also forecast for 2021/22.
2. Capital Management to 30 September 2020 2.1 At their meeting on 12 March 2020, Cabinet approved schemes to be met from the Capital Programme for the years 2020/21 to 2022/23. 2.2 The figures approved by Cabinet were on the basis of the net cost after specific funding to be met by the Council, either from reserves or from the sale of existing assets. The total approved spending was £23,652,000 during that period, of which £19,479,000 was to be spent during 2020/21. 2.3 As shown in Appendix A, the approved programme for 2020/21 moved to £18,397,000 by the end of the 2019/20 financial year, accounting for new schemes, deletions and deferrals into future years and was approved by Cabinet on 25 June 2020. 2.4 As the Capital Programme is a 4 year rolling plan an additional £854,000 has been included for approval for 2023/24. This consists of Disabled Facilities Grants and Housing Renewal advances. 2.5 New movements for 2020/21 are now forecasting an outturn of £19,652,000. 2.6 Appendices B and C set out in gross and net terms the actual spend and amounts approved against the forecast outturn to 31 March 2021, while Appendix D summarises the movement in approvals and in sources of finance for the year. 2.7 Approval is sought for a net increase in the capital programme of £1,690,000 for 2020/21 and £921,000 for 2021/22 (see notes 4.3 to 4.8). 2.8 There may be small differences in the figures within the report and appendices due to rounding.
Page Tunbridge Wells Borough Council 2 of 8 Quarter 2 – Capital Management to 30 September 2020 3. Options Considered 3.1 Retain the approved rolling capital programme as at the end of Quarter 1 2020/21. This would not reflect delays, advancements, underspends or new schemes and therefore provide an inaccurate forecast to the end of the financial year. 3.2 Amend the rolling capital programme to reflect changes since the end of Quarter 1 2020/21. These projections help to manage the public finances effectively which support the objectives and priorities of the Council.
4. Preferred Option and Reason
New Budget Approvals
4.1Appendix A shows how the approved capital expenditure has evolved since the programme was first agreed (CAB 140/19). The amounts approved for schemes at the June and September Cabinet meeting have been added to the figure then reported as total approvals as at Quarter 1.
Projected capital expenditure and funding for 2020/21
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Capital Management Report Quarter 1RESOLVED – 1. That the actual gross expenditure and that net of revenue for the year and the sources of finance, as s...
Revenue Management Report Quarter 1RESOLVED – 1. That the Quarter 1 net expenditure on services to the end of June 2026 was £5,414,000, £102,000 less th...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.