RESOLVED – That Full Council be recommended that the Capital Strategy 2021/22, as set out at Appendix A to the report be adopted. REASON FOR DECISION: To provide guidance on the Council’s capital programme and the use of its capital resources as required by the Chartered Institute for Public Finance and Accountancy and Prudential Code and Treasury Management Codes.
Word for word from the decision Tunbridge Wells published for this meeting.Source: democracy.tunbridgewells.gov.uk
Officer / Committee recommendations as supported by the Portfolio Holder: 1. That the Capital Strategy 2021/22, as set out in Appendix A to the report, be adopted.
Page Tunbridge Wells Borough Council 1 of 5 Capital Strategy 2021/22 1. Introduction and Background 1.1 This report presents the Capital Strategy 2021/22 and recommends that Cabinet proposes that it is adopted by Full Council. 1.2 The Capital Strategy forms part of the Council’s policy and strategy documents, providing guidance on the Council’s capital programme and the use of its capital resources. Its aim is to ensure that all elected Members fully understand the overall long-term policy objectives and resulting capital strategy requirements, governance procedures and risk appetite. 1.3 The guidance in this strategy complements and supplements the Medium Term Financial Strategy and the Treasury Management Policy and Strategy.
2. Capital Strategy 2021/22 2.1 The Chartered Institute for Public Finance and Accountancy (CIPFA) revised 2017 Prudential Code and Treasury Management Codes requires all local authorities to prepare a Capital Strategy report which provides the following: • a high-level, long-term overview of how capital expenditure, capital financing and treasury management activity contribute to the provision of services • an overview of how the associated risk is managed
• the implications for future financial sustainability
2.2The Capital Strategy informs the Capital Programme and gives an indication of the likely factors that will have an impact in the budget setting process. The Capital Programme and its financing play an important role in shaping future budget considerations. 2.3 The suggested Capital Strategy 2021/22 is presented in Appendix A to this report.
3. Options Considered 3.1 The Council must prepare a Capital Strategy for approval by Cabinet and Full Council.
Page Tunbridge Wells Borough Council 2 of 5 Capital Strategy 2021/22 4. Preferred Option and Reason 4.1 To agree and approve the content of the Capital Strategy 2021/22.
5. Consultation on Options 5.1 The Council takes advice from Link Asset Services on treasury management activities including investments, borrowing and capital financing.
Recommendation from Cabinet Advisory Board
5.2The Finance & Governance Cabinet Advisory Board were consulted on 12 January 2021 and agreed the following: That the recommendations to Cabinet as set out in the report be supported.
6. Implementation 6.1 Once the adoption of the Capital Strategy has been approved by Full Council it will be put into place commencing 1 April 2021.
7. Appendices and Background Documents Appendices: • Appendix A: Capital Strategy 2021/22 Background Papers: • None
Page Tunbridge Wells Borough Council 3 of 5 Capital Strategy 2021/22 8. Cross Cutting Issues
A. Legal (including the Human Rights Act)
Under Section 151 of the Local Government Act 1972 (LGA 1972) the Section 151 Officer has statutory duties in relation to the financial administration and stewardship of the authority, including securing effective arrangements for treasury management. Patricia Narebor, Head of Legal Partnership
B. Finance and Other Resources
This report forms part of the Council’s Budget and Policy Framework. Jane Fineman, Head of Finance, Procurement & Parking
C. Staffing
No implications to staffing. Jane Fineman, Head of Finance, Procurement & Parking
D. Risk Management
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Capital Management Report Quarter 1RESOLVED – 1. That the actual gross expenditure and that net of revenue for the year and the sources of finance, as s...
Revenue Management Report Quarter 1RESOLVED – 1. That the Quarter 1 net expenditure on services to the end of June 2026 was £5,414,000, £102,000 less th...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.