Property Asset Programme

Approved Executive 3 papers

Cabinet approved this item on Thursday 29 July 2021. Below is the council's own wording, with the papers it was decided on.

ItemCAB39/21

Resolved

RESOLVED – 1. To vire from the Capital and Revenue Initiatives Reserve the sum of £500,000 be used to establish a suitable budget for external consultancy services be approved. 2. That the head of Economic Development and Property in consultation with the S151 Officer and the Portfolio Holder for Finance and Governance be given authority to allocate funding to specific projects be approved. 3. That the head of Economic Development and Property in consultation with the S151 Officer and Portfolio Holder for Finance and Governance be given authority to appoint external professional advisors to deliver specific projects be approved. 4. That the establishment of a working group of Cabinet – the Property Asset Oversight Panel and associated terms of reference as detailed be approved. REASON FOR DECISION: To allow the delivery of capital receipts to support wider delivery of Council priorities and services.
Word for word from the decision Tunbridge Wells published for this meeting. Source: democracy.tunbridgewells.gov.uk

Follow this further

Built from Tunbridge Wells's papers

What the report saysPro

Report to Cabinet

Recommendations

Cabinet recommendations as supported by the Portfolio Holder: 1. To vire from the Capital and Revenue Initiatives Reserve a sum of £500,000 to establish a suitable budget for external consultancy services. 2. Delegate to the Head of Economic Development & Property, in consultation with the s.151 Officer and the Portfolio Holder for Finance and Governance authority to allocate funding to specific projects. 3. Delegate to the Head of Economic Development & Property, in consultation with the s.151 Officer and the Portfolio Holder for Finance and Governance authority to appoint external professional advisors to deliver specific projects. 4. Establish a working group of Cabinet - Property Asset Oversight Panel – with the terms of reference set out in Appendix B.

Page Tunbridge Wells Borough Council 1 of 9 Property Asset Programme 1. Introduction and Background 1.1 In 2012 the Council introduced the Land Asset Disposal programme. This has demonstrated the benefits of a focused resource to boost capacity, through specific advice in Property and Legal services, enabling a range of smaller sites to be assessed. In addition in 2013 the Council established the Development Programme to bring forward a range of larger opportunities for development and disposal.

1.2In the two programmes identified the Council has been able to raise receipts of £17.4m more than covering the resources allocated to enable the sites to be developed and disposed. These programmes allowed the disposal of 86 assets, making a substantial contribution to the Councils reserves and enabled the larger development opportunities to be progressed and enabled the larger capital schemes to be funded including works to the Town Hall, Assembly Hall, Multi- Story Car Parks, RVP and The Amelia Scott.

1.3The Covid-19 pandemic has thrown into sharp relief the use of the operational estate. With the Council able to deliver on flexible modern ways of working the total floor space required moving forward is being reconsidered. This impact and review of asset ownership and occupation is also being felt across the wider private sector with major employers in the town considering their space and use requirements going forward. There is evidence of alternative office demand developing with co-working proposals being identified. The impact on the retail and hospitality sector has also been significant with many businesses not returning post pandemic. While the independent sector in Tunbridge Wells has to an extent survived the headline casualties being amongst national chain stores.

2. Current Financial Position 2.1 The Council operates a four-year rolling capital programme that provides investment in, new property, plant and equipment to deliver services and schemes that ensure existing assets continue to be fit for purpose.

2.2To fund the capital programme the council will need to identify a continuous supply of capital receipts to supplement other external income that can used for capital purpose.

2.3The Budget 2021/22 and Medium-Term financial Strategy Update approved by Full Council on 24 February 2021 set out the medium-term forecast reserve position which has been updated following the closure of the year-end accounts as below.

Page Tunbridge Wells Borough Council 2 of 9 Property Asset Programme Total Reserves 25,000

20,000

15,000 £000

10,000

5,000

0 £000's £000's £000's £000's £000's £000's £000's Actual Forecast Forecast Forecast Forecast Forecast 31-Mar-21 31-Mar-22 31-Mar-23 31-Mar-24 31-Mar-25 31-Mar-26 Minimum

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
/21Appendix A 59 KB Download
PDF
/21Appendix B 89 KB Download
PDF
Property Asset ProgrammeReport 207 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at Tunbridge Wells

Search all
  1. Property Asset ProgrammeThis decision
  2. Property Asset ProgrammeDecided
  3. Managing Property AssetsApproved

More from Tunbridge Wells Cabinet

All decisions
MeetingDecisionOutcome
24 Sep 2026 Treasury and Prudential Indicator Management Report Quarter 1RESOLVED – 1. That the Treasury Management and Prudential Indicator position for 2026/27 be noted. 2. That the foreca... Noted Open
24 Sep 2026 Capital Management Report Quarter 1RESOLVED – 1. That the actual gross expenditure and that net of revenue for the year and the sources of finance, as s... Noted Open
24 Sep 2026 Revenue Management Report Quarter 1RESOLVED – 1. That the Quarter 1 net expenditure on services to the end of June 2026 was £5,414,000, £102,000 less th... Noted Open
24 Sep 2026 New Updated Planning Validation Checklist (Post Public Consultation)RESOLVED – 1. That the Draft Tunbridge Wells Local Validation List be adopted and used in the validation and processi... Approved Open
24 Sep 2026 Update on the Full Council Motion regarding the Maintenance of The Pantiles ColonnadeRESOLVED – 1. That the report covering the updates on the Full Council motion (FC103/25) on the Pantiles be noted. 2.... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies