Resolved
RESOLVED – That the Committee noted the contents of the report.
Audit and Governance Committee noted this item on Tuesday 24 August 2021. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED – That the Committee noted the contents of the report.
Officer recommendations as supported by the Portfolio Holder: 1. That the contents of this report and the Housing Benefit Assurance Process are noted.
Page Tunbridge Wells Borough Council 1 of 4 Housing Benefit Subsidy Claim 2019-20 1. Introduction and Background 1.1 Each year the Housing Benefit audit process is due to be completed by 30 November, which is a deadline set by the Department of Work and Pensions (DWP).
1.2External Audit is required to perform specific test requirements determined by the DWP on defined sample basis and to report the results of those procedures to the local authority and DWP.
1.3Due to the COVID pandemic, the DWP recognised there might be operational issues with external audit companies and local authorities meeting this deadline so offered authorities an alternative deadline of 31 January 2021.
1.4Due to staff resource issues at Grant Thornton, the Council had to request the DWP for a another extension to 31 March 2021 and then a further extension to 31 May 2021.
1.5The value of subsidy claimed from the DWP for Housing Benefit paid to claimants amounts to £28.2 million.
1.6Testing was undertaken on samples of cases and 7 errors were found which provided for a total gross adjustment of £3,659 to the claim.
1.7The Revenues and Benefits Service carried out over 50,000 benefit assessments during 2019-20 and whilst that work is undertaken with a high degree of accuracy, supported by robust quality assurance measures, a level of error is unavoidable. It is commonplace for Housing Benefit grant claims to be qualified.
1.8Due to the number and type of errors identified, it is not proposed to have an action plan put in place. Staff will be reminded of the importance to ensure figures are not transposed and calculations are double checked to minimise errors in future.
2. Options Considered 2.1 This report is for information only
Page Tunbridge Wells Borough Council 2 of 4 Housing Benefit Subsidy Claim 2019-20 3. Cross Cutting Issues
A. Legal (including the Human Rights Act)
The Department for Work and Pensions has developed the Housing Benefit Assurance Procedure (HBAP) that provides a comprehensive guide to providing assurance of Housing Benefit Subsidy claims submitted by Local Authorities including the testing methodology to establish a basis for the assurance and amendment of claims prior to final submission and the provision of the tools with which to conduct the assurance engagement.
The Housing Benefit Grant Claim Audit by Grant Thornton was undertaken in accordance with the HBAP procedures.
Gina Clarke, Mid Kent Legal
B. Finance and Other Resources
The adjustments outlined have minimal impact on the net value of the Council’s claim and the level of error identified does not indicate any significant underlying control weaknesses. Jane Fineman - Head of Finance, Procurement and Parking
C. Staffing
There are no changes to staffing proposed in this report.
Sheila Coburn, Head of Mid Kent Revenues and Benefits
D. Risk Management
The work undertaken by Grant Thornton provides external assurance to the Council on the effectiveness of arrangements for the accurate payment and recording of benefit expenditure. Sheila Coburn, Head of Mid Kent Revenues and Benefits
Page Tunbridge Wells Borough Council 3 of 4 Housing Benefit Subsidy Claim 2019-20 E. Environment and Sustainability
No impact Sheila Coburn, Head of Mid Kent Revenues and Benefits
F. Community Safety
No impact Sheila Coburn, Head of Mid Kent Revenues and Benefits
G. Equalities
No impact
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Housing Benefit and Subsidy Claim 2019/20Report | 113 KB | DownloadRead as text |
PDF |
TWBC 2019.20: HBAP Report: Final May 2021: 21052021 SIGNED /21Report | 413 KB | Download |
Follow Audit and Governance Committee at Tunbridge Wells and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 2 Jul 2026 | Minutes of the meeting of the Audit and Governance Committee dated 10 March 2026RESOLVED – That the minutes of the meeting dated 10 March 2026 be approved as a correct record. | Approved | Open |
| 2 Jul 2026 | Future Work Programme as at 2 July 2026RESOLVED – That the Future Work Programme as at 2 July 2026, be noted. | Noted | Open |
| 2 Jul 2026 | External Audit Progress and Sector Update ReportRESOLVED - That the committee consider and agree the Audit Progress and Sector Update Report. | Agreed | Open |
| 2 Jul 2026 | Internal Audit Report & Annual Audit Opinion 2025/26RESOLVED – 1. That the Audit & Governance Committee notes the Head of Audit Partnership opinion. 2. That the Audit & ... | Decided | Open |
| 10 Mar 2026 | Minutes of the meeting of the Audit and Governance Committee dated 25 November 2025RESOLVED – That the minutes of the meeting dated 25 November 2026 be approved as a correct record. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.