Resolved
RESOLVED – That the provided for information, be noted.
Planning Committee noted this item on Wednesday 18 January 2023. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED – That the provided for information, be noted.
The Council’s adopted “Enforcement and Compliance Strategy” (July 2010) requires a report to be made at appropriate intervals to the Planning Committee.
This report provides a summary of the planning enforcement cases from 1 April 2022 to 30 September 2022.
Report status
For information
Route to Implementation/Timetable:
This report has been submitted to the Planning Committee for information purposes only.
1 BACKGROUND & INTRODUCTION
1.1This matter is to be reported to Committee every six months.
1.2The enforcement report is normally presented to the Committee every six months, however due to staffing changes and other priorities this is the first such report for a number of years. 1.3 Much of the enforcement and compliance work follows from reports and queries from the public, Councillors and Parish and Town Councils. The number of new complaints registered for investigation compared to previous months is as follows: 2 ENFORCEMENT COMPLAINTS RECEIVED
2.1Enforcement complaints are categorised on receipt to one of the below categories. The table identifies how many of each category were received in the period 1 April 2022 to 30 September 2022. These represent the number of cases, in many instances there would be multiple complaints/complainants regarding the same case. Number of New Cases 1 April Type 2022 to 30 September 2022 Advertisements 4 Article 4 Creation 2 Breach of Conditions/Breach of 39 Approved Plans Change of Use 24 High Hedge Complaints 10 Unauthorised work to Listed 15 Buildings Unauthorised work to Protected 11 Trees Operational Development 80 Waste/Untidy Site 9 TOTAL 194
2.2The geographical spread of new cases received in the period 1 April 2022 to 30 September 2022 is outlined in the table below.
Area Advert Article Breach Change High Listed Trees Op Waste TOTAL 4 of Cond/ of Use Hedge Building Dev Plans Benenden 2 1 4 7 Bidborough 2 2 Brenchley & 4 2 1 2 1 10 Matfield Capel 1 1 3 5 Cranbrook & 1 3 1 1 1 1 9 1 18 Sissinghurst Frittenden 1 1 2 Goudhurst 5 5 Hawkhurst 1 2 1 3 1 1 9 Horsmonden 2 1 4 7 Lamberhurst 2 1 5 1 2 11 Paddock Wood 7 1 8 Pembury 1 4 1 7 2 15 Rusthall 3 6 1 10 Sandhurst 1 1 2 Southborough 1 2 1 1 2 1 8 Speldhurst 2 4 2 2 5 15 Tunbridge 1 12 9 5 1 4 25 3 60 Wells 2.3 Each of these received complaints are investigated. There are four priority categories when dealing with investigations of new cases. These are explained below:
Top Priority
Unauthorised work causing significant damage to listed buildings; felling of protected trees/hedgerows; works to ancient monuments/SSSIs/SNCIs likely to cause irreversible harm to the natural or historic environment; developments affecting the Highway to the extent that is causes immediate danger to life.
Target: Initial investigation and site visit to control the situation carried out within one working day.
High Priority
Unauthorised developments causing significant harm to the quality of life of a number of local residents, causing or potentially causing significant harm to the landscape function of the AONB or the quality of Conservation Areas etc. or harm to listed buildings causing lesser harm than Top Priority cases or developments affecting the highway to the extent that it causes significant hazards to traffic.
Target: Initial investigation and site visit will be carried out within five working days of the complaint being lodged.
Medium Priority
Unauthorised developments which cause limited harm to individuals, a single neighbour; or other interests of planning importance (e.g. works not in general public view, advertisements).
Target: Initial investigation and site visit will be carried out within ten working days of the complaint being lodged.
Other priority
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Enforcement Report April 2022 to September 2022Report | 144 KB | DownloadRead as text |
Follow Planning Committee at Tunbridge Wells and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 19 Aug 2026 | To approve the minutes of the meeting dated 22 July 2026RESOLVED – That the minutes of the meeting dated 22 July 2026 be recorded as a correct record. | Decided | Open |
| 19 Aug 2026 | Application for Consideration - 26/00985/FULL - Chapel, Tunbridge Wells Borough Cemetery, Benhall Mill Road, Royal Tunbridge Wells, KentDecision/voting – On the basis that members were satisfied that all relevant planning considerations had been covered... | Approved | Open |
| 19 Aug 2026 | Application for Consideration - 26/01446/FULL - 23 Hilbert Road, Royal Tunbridge Wells, KentDecision/voting – On the basis that members were satisfied that all relevant planning considerations had been covered... | Approved | Open |
| 19 Aug 2026 | Application for Consideration - 26/01627/LAWPRO - 2A Sherwood Road, Royal Tunbridge Wells, KentDecision/voting – On the basis that members were satisfied that all relevant planning considerations had been covered... | Approved | Open |
| 19 Aug 2026 | Appeal Decisions for NotingRESOLVED – That the list of appeal decisions provided for information, be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies