Active Travel Projects Update Report For Joint Transportation Board on 2 October 2023
Summary Lead Member: Councillor Justine Rutland, Cabinet Member for Economic Development Lead Director: Lee Colyer, Director of Finance, Policy and Development (s151) Head of Service: David Candlin, Head of Economic Development and Property Report Author: Hilary Smith, Economic Development Manager Classification: Public document (non-exempt) Wards Affected: Speldhurst & Bidborough, Rusthall, Culverden, Park, Pantiles & St Marks, St John’s, St James’, Sherwood, Southborough & High Brooms
For Information
1. This paper provides an update on two Active Travel projects that TWBC and KCC are working on together, funded by Active Travel England. 2. This paper is for information only.
Page Tunbridge Wells Borough Council 1 of 3 Active Travel Projects Update 1. Introduction and background 1.1 In 2022 Tunbridge Wells Borough Council submitted a number of projects to Kent County Council (KCC) to be considered for Active Travel England (ATE) funding in. Two projects Tunbridge Wells projects were selected for submission by KCC and awarded funding by ATE as follows:
• Langton-Rusthall-Royal Tunbridge Wells Town Centre Cycle Route Design • Better Streets Pilot Project for St John’s and St James’ Areas Community Engagement and Design
1.2The progress on each of these projects to date is outlined below.
2. Langton-Rusthall-Town Centre Cycle Route Design
2.1This project is funded through Active Travel England’s Capability Fund which is aimed at providing support for planning cycling and walking networks and/or route design.
2.2The route linking Langton Green – Rusthall – Royal Tunbridge Wells town centre was included in the Tunbridge Wells Local Cycling & Walking Infrastructure Plan (LCWIP) Phase 1 which was published as part of the evidence base for the Submitted Local Plan.
2.3Consultants have been appointed to prepare a design for the route that would enable TWBC/KCC to apply for future Active Travel Funding to implement the route proposals.
2.4Initial engagement meetings have or will been held with local stakeholders including the Commons Conservators, Speldhurst and Rusthall Parish Councils, Royal Tunbridge Wells Town Forum and Tunbridge Wells Bicycle Users Group.
2.5The consultants are now assessing route options before moving onto the design phase of the project.
2.6The estimated completion date for the project is December 2023.
Page Tunbridge Wells Borough Council 2 of 3 Active Travel Projects Update 3. Better Streets for St John’s and St James’ Areas 3.1 This project is funded through Active Travel England’s Tranche 4 which funds both the development of designs for, and the delivery of, cycling and walking infrastructure.
3.2The Council regularly receives feedback from residents about traffic-related issues affecting them in the streets in which they live and further work is required to understand these issues and develop options to create more pleasant streets for all users.
3.3A pilot study area was identified as part of the Local Cycling and Walking Infrastructure Plan Phase 2, which was published as part of the evidence base for the Submission Local Plan. The study area covers mainly the wards of St John’s and St James’ but also smaller parts of Culverden, Park, Sherwood and Southborough & High Brooms.
3.4A Working Group comprising Councillors and local residents has been formed to support the project.
3.5As an initial phase of the project, TWBC has undertaken a comprehensive engagement with residents to understand their everyday experiences of moving through the study area.
3.6The engagement resulted in a total of 581 participants responding to a survey and/or a map to pinpoint specific locations of concern. The headline issues identified included speeding traffic, parking issues and a poor street environment.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Active Travel Projects Update ReportReport | 158 KB | DownloadRead as text |
Follow Joint Transportation Board at Tunbridge Wells and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 13 Jul 2026 | Minutes of the meeting dated 20 April 2026RESOLVED : That the minutes of the Joint Transportation Board meeting dated 20 April 2026 be accepted as an accurate ... | Decided | Open |
| 13 Jul 2026 | Parking Consultation York Road and Dudley Road, Tunbridge WellsRESOLVED – That the Joint Transport Board notes the results of a public consultation proposing changes to waiting res... | Decided | Open |
| 13 Jul 2026 | Active Travel UpdateRESOLVED – The report was noted. | Noted | Open |
| 20 Apr 2026 | Minutes of the meeting dated 2 February 2026RESOLVED – That the minutes of the meeting dated 2 February 2026 be approved as a correct record. | Approved | Open |
| 20 Apr 2026 | Parish Highways Improvement Projects GrantsRESOLVED – The report was noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.