Performance Summary Quarter 3

Decided Executive 3 papers

AI summaryCabinet noted quarter three, 2025/26 service performance [D] [P2]. The report says 15 indicators with agreed targets were performing, one was underperforming, and two used quarter two data [P17]. It records £10,000 released for Hawkenbury Hub [P17] [3.3].

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedPerformance: 15 performing, one underperforming, two using quarter two data [P17].
Money£10,000 of S106 funds [3.3]A Cabinet Member Decision released funds for Hawkenbury Hub [3.3].
What happens nextNo implementation timetable needed [6.3]Any Cabinet action would come through separate reports [5.2].
Who it affectsServices, projects and residents [1.1]Quarterly reporting supports scrutiny, challenge and improvement [1.5] [1.6].

What was decided

Cabinet noted service performance for quarter three, 2025/26. Report P2

The paper was for noting only and put no options to Cabinet. It stated that no implementation period was necessary. Report 4.1, 6.3

Why

Performance management assesses progress towards desired aims and outcomes. Quarterly publication supports scrutiny, transparency and trust in public spending. Report 5.1

Cabinet oversight helps make the performance framework robust and keeps delivery open to political challenge. Report 1.5

For substantively underperforming services, a Recovery Plan sets out actions to bring performance back on track. Report 1.3

What happens next

Any actions Cabinet chooses would be brought forward in separate reports with options appraisals and decisions. Report 5.2

The Hawkenbury Hub project manager will consult locally, develop a scheme of works and return it for a further Cabinet decision. Report 3.3

The Royal Victoria Place planning application remains on track for Easter 2026. The Rusthall cycle scheme can be submitted to Active Travel England for funding in March 2026, and steel works for the Royal Victoria Place solar scheme are expected to start in March 2026. Report 3.10, 3.12, 3.15

The money

  • £10,000 A Cabinet Member Decision released S106 funds to appoint a Hawkenbury Hub project manager and oversee design and implementation of works. Report 3.3

Implications

  • Legal: Cabinet has no statutory duty to receive regular performance reports. As a best value authority, the Council must secure continuous improvement in how it exercises its functions. The recommendations do not adversely affect Human Rights Act rights or freedoms. Report P67
  • Financial: A number of performance indicators and projects have financial implications. Capital, Revenue and Treasury Monitoring Reports cover these where appropriate. Report P69
  • Staffing: Most work on services and projects is undertaken by Council staff. Heads of Service monitor performance monthly and assess staffing against Council priorities. Report P71
  • Risk: All risks from this report are within the Council's risk appetite and are managed under its risk management strategy. Report P73
  • Equalities: The recommendations have remote or low relevance to the Equality Act. No apparent equality impact on end users was identified. Report P79
  • Climate: No environmental or sustainability issues arise from the report or recommendations. Report P75
  • Legal: No data protection issues arise from the report or recommendations. Report P81
  • Other: No consultation took place because the report contained factual information and no direct decisions. No community safety, health and safety, or health and wellbeing issues arise from the report or recommendations. Report 6.1, P77, P83, P85

Who and where

  • Council services Report 1.1, 1.2
  • Council Strategic Plan projects Report 1.9, 3.1
  • Residents Report 1.5, 1.6
  • Councillors and stakeholders Report 1.6
  • Council staff Report P71
  • Service users Report P79
  • Management Board and Leadership Team Report 1.8, 1.9

Timeline

  • October to December 2025/26: Quarter three service and project performance was summarised. Report P3, 1.1, 3.1
  • 12 November 2025: Planning permission was approved for solar energy on the Royal Victoria Place car park. Report 3.15
  • 4 December 2025: A Cabinet decision was taken on continuing leisure centre services at the end of the current contract. Report 3.5
  • 30 January: An All Member Briefing took place on the leisure centre services. Report 3.5
  • 11 February 2026: Relevant officers dated their cross cutting assessments. Report P67, P69, P71, P73, P75, P77, P79, P81, P83, P85
  • March 2026: The Rusthall cycle scheme can be submitted to Active Travel England for funding, and steel works are expected to commence at Royal Victoria Place. Report 3.12, 3.15
  • Easter 2026: Submission of the Royal Victoria Place planning application remains on track. Report 3.10
  • 2 March 2026: The Finance, Innovation and Transformation Cabinet Advisory Board supported the recommendations. Report 6.2

Plain English for the jargon

  • Performance indicator: A measure showing whether a service is performing or underperforming against an agreed target. [1.2]
  • Recovery Plan: Actions showing how substantively underperforming services will be brought back on track. [1.3]
  • Management Board: The Chief Executive and Directors, receiving service performance reports quarterly. [1.8]
  • Leadership Team: Cabinet and Management Board, reviewing Strategic Plan project progress quarterly. [1.9]
  • Hawkenbury Hub: The long term project to increase pitches and improve playing surfaces at Hawkenbury Recreation Ground. [3.3]
  • S106 funds: Funding released for a Hawkenbury Hub project manager to oversee design and implementation of works. [3.3]
  • RVP: Royal Victoria Place. [3.10]
  • Best value authority: An authority with a statutory duty to secure continuous improvement in its functions. [P67]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemCAB159/25

Resolved

To consider and decide on the recommendations as set out in the associated report.
Word for word from the decision Tunbridge Wells published for this meeting. Source: democracy.tunbridgewells.gov.uk

Follow this further

Built from Tunbridge Wells's papers

What the report saysPro

Report to Cabinet, 9 pages

Recommendations

Officer recommendations as supported by the Portfolio Holder:

1. That Cabinet notes the summary of service performance over quarter three, 2025/26, at Appendix A.

Page Tunbridge Wells Borough Council 1 of 9 Performance Summary Q3 (October to December) 2025/26 1. Introduction and background

1.1This report summarises the performance of the Council’s services and projects in quarter three of 2025/26.

1.2Appendix A provides a summary of the Council’s service performance for quarter three of 2025/26, with an indicator for each to show if the service is performing or underperforming against its agreed target.

1.3Where substantive underperformance is identified for a service, a Recovery Plan detailing actions to bring performance back on track is created.

1.4The performance management framework is part of the overall governance framework of the Council, which seeks to ensure that risks are managed whilst results are delivered.

1.5Quarterly performance reporting helps the Council to improve services and deliver better results for residents. Cabinet oversight ensures that the framework is robust, and that performance is open to challenge from those with political responsibility for the delivery of projects and services.

1.6This summary report and its appendix documents, which are made publicly available, help other Councillors, residents and stakeholders to engage with the work of the Council, and to provide further challenge where it is appropriate and effective to do so.

1.7This summary report is divided into two main sections:

• Strategic Plan projects performance • Service performance (Appendix A)

1.8Service performance is monitored daily by line managers, reported to Heads of Service monthly, and Management Board (Chief Executive and Directors) on a quarterly basis.

1.9Delivery of projects under the Council's Strategic Plan 2024-32 is reviewed quarterly by Management Board. Progress is also monitored quarterly by Leadership Team (Cabinet and Management Board) through provision of standard progress reports.

Page Tunbridge Wells Borough Council 2 of 9 Performance Summary Q3 (October to December) 2025/26 2. Service performance

2.1The Council is currently reporting on 21 performance indicators, 16 of which have agreed targets.

2.2Of the 16 performance indicators which have agreed targets, in quarter three 2025/26:

• 15 were performing • one was underperforming • two were not able to provide performance data for quarter three, therefore their performing indicator is based on data provided for quarter two.

3. Strategic Plan projects performance

3.1Updates on the projects within the Council’s Strategic Plan 2024-32 are set out below. Further updates can be found on the Council’s website at:

https://tunbridgewells.gov.uk/council/strategies-plans-and-policies/strategic-plan- 2024-2032/making-it-happen

Affordable Housing

3.2We continue to look for opportunities to progress this initiative. It should be noted that affordable housing policies are included in the Local Plan adopted at the last Full Council meeting.

Hawkenbury Hub

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Performance Report /25Appendix A 25 pages Download
PDF
CT Under Performance Recovery Plan /25Appendix B 1 pages Download
PDF
Performance Summary Quarter 3Report 9 pages DownloadRead as text

At this meeting

Whole meeting
CAB142/25Leaders Introduction and AnnouncementsOn the agenda CAB145/25Notification of visiting Persons wishing to speakOn the agenda CAB146/25Minutes of the meeting dated 5 February 2026Approved CAB147/25Questions from Members of the CouncilOn the agenda CAB148/25Questions from Members of the PublicOn the agenda CAB149/25Consideration of the Forward Plan as at 11 March 2026Noted CAB150/25Royal Victoria Place Business Plan 2026/27Approved CAB151/25Housing Payment PolicyApproved CAB152/25*Household Waste and Street Cleansing Contract AwardNoted CAB153/25Treasury and Prudential Indicator Management Report Quarter 3Noted CAB154/25Capital Management Report Quarter 3Decided CAB155/25Revenue Management Report Quarter 3Noted CAB156/25*Community Safety Partnership Plan 2026/27Decided CAB157/25Proposal for a Dogs on Leads Public Spaces Protection Order for The Grove - Recommendation reportDecided CAB158/25Review of Housing Assistance Policy 2026-30Decided
CAB159/25Performance Summary Quarter 3This decision
CAB160/25Refreshed Health Inequalities Action Plan 2026-29Approved CAB161/25Biodiversity Duty ReportApproved CAB162/25New Updated Planning Validation Checklist (Pre-Public Consultation)Decided CAB163/25Review-Update of Tunbridge Wells Borough Council's Statement of Community Involvement (pre-public Consultation)Approved CAB164/25Sandhurst Neighbourhood Development Plan (Pre-Referendum Report)Decided CAB165/25Southborough and High Brooms Neighbourhood Development Plan (Pre-Referendum Report)Decided

On this subject at Tunbridge Wells

Search all
  1. Performance Summary Quarter 3This decision
  2. Performance Summary Quarter 4Decided
  3. Performance Summary Quarter 4Agreed
  4. Performance Summary Quarter 3Decided
  5. Performance Summary Quarter 2Noted
  6. Performance Summary Quarter 2Decided

More from Tunbridge Wells Cabinet

All decisions
MeetingDecisionOutcome
24 Sep 2026 Treasury and Prudential Indicator Management Report Quarter 1RESOLVED – 1. That the Treasury Management and Prudential Indicator position for 2026/27 be noted. 2. That the foreca... Noted Open
24 Sep 2026 Capital Management Report Quarter 1RESOLVED – 1. That the actual gross expenditure and that net of revenue for the year and the sources of finance, as s... Noted Open
24 Sep 2026 Revenue Management Report Quarter 1RESOLVED – 1. That the Quarter 1 net expenditure on services to the end of June 2026 was £5,414,000, £102,000 less th... Noted Open
24 Sep 2026 New Updated Planning Validation Checklist (Post Public Consultation)RESOLVED – 1. That the Draft Tunbridge Wells Local Validation List be adopted and used in the validation and processi... Approved Open
24 Sep 2026 Update on the Full Council Motion regarding the Maintenance of The Pantiles ColonnadeRESOLVED – 1. That the report covering the updates on the Full Council motion (FC103/25) on the Pantiles be noted. 2.... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies