RESOLVED That the allocation of £200,000 capital expenditure in 2010/11 is approved for essential repair and refurbishment works at the leisure facilities and for refurbishment works at Abbey House in Abingdon, as set out in paragraphs 6 , 7 and 8 of report 5/10.
Word for word from the decision Vale of White Horse published for this meeting.Source: democratic.whitehorsedc.gov.uk
Executive report 28 May 2010 Report of Head of Economy Leisure and Property Report No 5/10 Author: Chris Webb Telephone: 01235 540358 Textphone: 18001 01235 540358 E-mail: [email protected] Wards affected: All Executive member responsible: Councillor Richard Gibson Tel: 01235 559850 E-mail: [email protected] To: EXECUTIVE DATE: 28 May 2010
Allocation of capital funding for essential repairs and refurbishment works at the leisure facilities and Abbey House Recommendation That the executive approves the allocation of £200,000 capital expenditure in 2010/11 for essential repair and refurbishment works at the leisure facilities and for refurbishment works at Abbey House, as described in paragraphs 6, 7 and 8 of the report.
Purpose of Report 1. The purpose of this report is to gain the executive’s approval for the allocation of capital funding for essential repairs and refurbishment works at the Vale Council’s leisure facilities and for potential refurbishment works at Abbey House in 2010/11.
Strategic Objectives 2. The proposed essential works support the Vale Council’s strategic objective in managing its business effectively by maintaining its property portfolio to ensure
D:\moderngov\data\published\Intranet\C00000104\M00001344\AI00013592\Executive100528capitalexpenditurefin al1005130.doc Last updated 12.02.10 that services can be delivered in order to meet the needs of our residents and other service users.
Background 3. During the 2010/11 budget setting process officers requested funding to undertake essential repairs and refurbishment works at the Vale Council’s leisure facilities over a three year period. These works included both capital and revenue expenditure. The approved capital programme allocates £200,000 a year for 2010/11 – 2012/13 for maintaining the building fabric of the leisure facilities. This programme will require revision in subsequent years, as the allocated budget does not fully cover the known essential repair and refurbishment works.
4. In addition to works at the leisure facilities, it may be necessary to provide capital funding for refurbishment works at Abbey House as part of the process of relocating service teams. This project is being developed and it would be appropriate to allocate some £15,000 at this stage for these works. There is no other allocation within the capital programme that would cover these works. This would leave at least £185,000 available for works at the leisure facilities in 2010/11.
5. Officers drew up the list of proposed essential works at the leisure facilities in consultation with the former property team. Officers referred to condition surveys that were undertaken for all of the Vale facilities, as these provide indicators as to when key pieces of plant and décor might fail. Consultation with the finance team split these works into capital and revenue expenditure. The identification of these works took into account the staffing changes within the former property team and 15 per cent for professional fees was added to the estimated costs of most of the works to ensure appropriate supervision is applied to the programme.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.