Resolved
RESOLVED : To note the content of the report.
Scrutiny Committee noted this item on Wednesday 24 August 2011. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED : To note the content of the report.
Scrutiny Committee
24 August 2011 Report of Head of Corporate Strategy Report no. 18/11 Author: Heather Saunders Telephone: 01235 540506 Textphone: 18001 01235 540506 E-mail: [email protected] Cabinet member responsible: Matthew Barber Tel: 01235 540391 E-mail:[email protected] To: SCRUTINY COMMITTEE DATE: 24 August 2011
Review of progress against the energy efficiency (carbon management) plan 2010/11 Recommendation That Scrutiny Committee notes progress made towards meeting the council’s carbon emissions reduction target of 20 per cent over five years.
Purpose of report 1. The Executive adopted the council’s Carbon Management Plan in February 2009. This Plan sets out our goal to reduce the council’s carbon dioxide emissions by 20 per cent over a five year period from 2008/9 to 2012/13, and how we intend to achieve it. This Scrutiny report reviews progress on the second year of implementation of the Carbon Management Plan and sets out our plans for future action.
Strategic objectives 2. This report relates to strategic objective ‘Rising to the challenge of climate change’ and specifically the corporate priority CC1 - Minimise our impact on the causes of climate change. By reducing expenditure on energy, this work also contributes to providing value for money services.
D:\moderngov\data\published\Intranet\C00000103\M00001477\AI00016080\ValeScrutinyreportCarbonAugust2011v3Clar eschanges0.doc Last updated 12.02.10 Baseline 3. The council’s baseline emissions in 2007 were 5134 tonnes. This figure does not tie in with the baseline originally published in the Carbon Management Plan as emissions from leisure centres was underreported to the council and were revised subsequent to the publication of the Plan. The chart below shows the breakdown of baseline emissions from different sources.
Baseline CO2 emissions for 2008/9 Total emissions 5134 tonnes CO2
Civic buildings 12%
Fleet 27%
Business mileage 2%
Other buildings 6%
Leisure centres 53%
2010/11 results 4. Total carbon emissions in 2010/11 were 4689 tonnes, a reduction of nine per cent on the baseline. Reductions for different sectors are shown in the table below.
2007 2008/9 2009/10 2010/11 Percentage baseline emissions emissions emissions reduction emissions tonnes tonnes tonnes from tonnes CO2 CO2 CO2 baseline CO2 Civic buildings 663 657 612 615 7% Leisure centres 2,697 2,818 2,580 2,559 5% Other buildings 305 349 227 217 29% Business 114 121 95 48 58% mileage D:\moderngov\data\published\Intranet\C00000103\M00001477\AI00016080\ValeScrutinyreportCarbonAugust2011v3Clar eschanges0.doc Last updated 12.02.10 Fleet 1,355 1,479 1,433 1,250 8%
Total 5,134 5,424 4,944 4689 9%
Weather effects 5. Over the period of our carbon management programme, the weather has become steadily colder year on year. This has affected winter demand for gas, therefore increasing energy use and emissions. We have made nine per cent savings on our emissions despite these weather-related trends. Using national standard weather conditions, we can take away the weather effects and estimate what our savings would have been had the weather remained constant over the period. In this case, our emissions savings would have been an 18 per cent reduction on the baseline.
Projects delivered LEISURE 6. We delivered two key projects this year as set out in the table below. Swimming pool covers save energy by reducing heat loss from the pool overnight. They also reduce evaporation and substantially cut requirements for pool hall ventilation. Valve wraps are insulating jackets that cover up exposed valves in plant rooms, stopping heat loss to the surrounding air.
Project Site pool covers White Horse Tennis & Leisure Centre, Wantage Leisure Centre, Faringdon Leisure Centre valve wraps White Horse Tennis & Leisure Centre, Wantage Leisure Centre, Faringdon Leisure Centre, Tilsley Park
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Review of progress against the energy efficiency (carbon management) plan 2010/11Report | 109 KB | DownloadRead as text |
Follow Scrutiny Committee at Vale of White Horse and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 14 Sep 2026 | Minutes of the last meetingThe minutes of the meeting held on 8 June 2026 were approved as a correct record and the chair would sign them as such. | Approved | Open |
| 8 Jun 2026 | Minutes of the last meetingThe minutes of the meeting held on 23 March 2026 were agreed as a correct record, and the chair will sign them as such. | Agreed | Open |
| 23 Mar 2026 | Minutes of the last meetingThe minutes of the meeting held on 2 February 2026 were agreed as a correct record, and the chair would sign them as ... | Agreed | Open |
| 2 Feb 2026 | Minutes of the last meetingThe minutes of the meeting held on 3 November 2025 were agreed as a correct record, and the chair would sign them as ... | Agreed | Open |
| 3 Nov 2025 | Minutes of the last meetingResolved : The minutes of the meeting on 29 September 2025 were agreed as a correct record, and the chair would sign ... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.