Resolved
RESOLVED : To note the changes to the treasury management strategy.
Audit and Governance Committee noted this item on Wednesday 11 July 2012. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED : To note the changes to the treasury management strategy.
Treasury Management Strategy 2012/13 – 2014/15 1. The treasury management service is an important part of the overall financial management of the council’s affairs. The prudential indicators in the council’s annual budget setting report consider the affordability and impact of capital expenditure decisions, and set out the council’s overall capital framework. The treasury service considers the effective funding of these decisions. Together they form part of the process which ensures the council meets its balanced budget requirement under the Local Government Finance Act 1992. 2. The council’s treasury activities are strictly regulated by statutory requirements and a professional code of practice (the CIPFA Code of Practice on Treasury Management – revised 2011). 3. As a part of the Code the council also adopted a Treasury Management Policy Statement. This adoption is required as one of the prudential indicators. 4. The policy requires an annual strategy to be reported to Council outlining the expected treasury activity for the forthcoming three years. A key requirement of this report is to explain the risks, and the management of those risks, associated with the providing the treasury service. Legislation requires that two further treasury reports are required: a mid-year monitoring report and an outturn report after the year-end that reports on actual activity for the year. 5. This strategy covers: • the Council’s debt and investment projections; • the expected movement in interest rates; • the Council’s borrowing and investment strategies; • treasury performance indicators; • specific limits on treasury activities; • any local treasury issues.
Debt and Investment Projections 2012/13 – 2014/15 6. The council has to provide details of its borrowing requirement, any maturing debt which will need to be re-financed, and the effect this will have on the treasury position over the next three years. This council has no external debt and doesn’t expect to borrow long term to finance its capital programme. There may be occasions when we need to borrow short-term for temporary cash flow reasons; these liabilities are likely to be for fixed rates and terms. The table therefore only specifies the limits for any temporary short-term borrowing and highlights the expected change in investment balances. Limits to borrowing activity 2011/12 2012/13 2013/14 2014/15 Revised Estimated Estimated Estimated External Debt Operational boundary £2 million £2 million £2 million £2 million Authorised limit £5 million £5 million £5 million £5 million Limit at variable interest rates nil nil nil nil Limit for maturity > 1 year nil nil nil nil The operational boundary is the limit which external borrowing is not normally expected to exceed. The authorised limit is a control on the maximum level of borrowing - a limit beyond which external borrowing is prohibited. This limit can only be set or revised by a meeting of the full Council. This is aimed at authorities with long-term borrowing and is meant to reflect the level of borrowing that would not be sustainable long term. Projected total investments 2011/12 2012/13 2013/14 2014/15 Revised Estimated Estimated Estimated Investments Total Investments at 31 March £13 million £14.5 million £15 million £15 million
The following information and commentary has been provided by Sector, the council’s investment consultants. Expected Movement in Interest Rates Medium term interest rate estimates (mid year) (source: Sector Treasury Ltd) Bank of Estimated earnings rates DMO PWLB rates England base for investments up to 3 (borrowing) rate months duration 5 yr 10 yr 50 yr 2012/13 0.50% 0.70% 2.30% 3.40% 4.40% 2013/14 0.75% 1.00% 2.70% 3.70% 4.70% 2014/15 2.00% 1.60% 3.30% 4.40% 5.10%
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Treasury Management Strategy approved by Council 22 February 2012Report | 103 KB | DownloadRead as text |
PDF |
Treasury management strategy updateReport | 42 KB | Download |
Follow Audit and Governance Committee at Vale of White Horse and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 19 Mar 2015 | Actions arisingRESOLVED : to retain the following items on the actions arising list: · To call the Building Control manager to a fut... | Decided | Open |
| 19 Mar 2015 | Internal audit management report quarter four 2014/15RESOLVED : to note the internal audit management report for the fourth quarter 2014/15. | Noted | Open |
| 19 Mar 2015 | Internal audit plan 2015/16RESOLVED : to approve the internal audit plan 2015/16. | Approved | Open |
| 22 Jan 2015 | Minutesto defer the approval of the minutes of the meeting held on 24 September 2014 as a correct record and to agree that t... | Deferred | Open |
| 22 Jan 2015 | Actions arisingto retain the amended procedure for monitoring systemic control weaknesses on the actions arising list for one more m... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.