RESOLVED : To (a) recruit a part-time project manager for up to 18 months, an additional full-time senior planner for 18 months, and secure additional consultancy support to expedite the delivery of the local plan core strategy; and RECOMMEND Council : To (b) approve a one-off supplementary budget increase of £145,000 to fund the additional resources to expedite the delivery of the local plan core strategy.
Word for word from the decision Vale of White Horse published for this meeting.Source: democratic.whitehorsedc.gov.uk
Cabinet Report Report of Planning Policy Manager Author: Miles Thompson Telephone: 01235 540339 Textphone: 18001 01235 540339 E-mail: [email protected] Wards affected: All Cabinet member responsible: Roger Cox Tel: 01367 243360 E-mail: [email protected] To: CABINET DATE: 12 July 2012
Resourcing of planning policy team to expedite delivery of Vale local plan - core strategy Recommendations (a) To recruit a part time project manager for up to eighteen months and an additional full time senior planner for eighteen months, and to secure additional consultancy support, and
(b) To recommend Council to approve a one-off supplementary budget increase of £145,000.
Purpose of Report 1. To secure approval for the deployment of resources additional to those allocated this year to the Planning Service budget, to help expedite the delivery of the Vale Local Plan - Core Strategy.
Strategic Objectives 2. The Vale Local Plan - Core Strategy will guide investment and development decisions across the Vale for a fifteen year period. Through the process of producing the document and in its implementation it will be a major contributor to achieving the strategic objectives of: (a) a strong economy
(b) positive and constructive work with community groups
(c) housing for people who need it, and
(d) communities involved in decisions about development affecting their local area
Background 3. Completion of the Core Strategy internal review at cabinet on 9 March 2012 provided a clear basis to progress the more detailed work for the next draft of the replacement Vale Local Plan - Core Strategy. That report included an indicative timetable for progress on the local plan, setting out alternative timelines, with the difference between them relating to the scope of further work required if new strategic housing sites were added.
4. Having regard to the significance of the Vale Local Plan - Core Strategy to the achievement of the Council’s strategic objectives, there are benefits to securing the earliest possible adoption of the document, and conversely, the longer it takes then there is more exposure to risks. The sooner it can be progressed to the submission stage with a robust plan, the sooner we will give the emerging plan added weight for decision making on planning applications.
5. However, speed of progress should not be at the expense of producing an unsound document, whether by reason of process or content. Many of the tasks have limited potential to be completed more quickly, particularly as some are subject to statutory requirements.
6. To drive forward the preparation of the Vale Local Plan, to achieve either an earlier completion date or at least to minimise any additional time required to bring it to adoption, a step-change in the resourcing of the project is required. We need to consider a combination of targeted use of consultants, project management support to free up team time for preparing the plan and associated documents, and the recruitment of additional, experienced planners to help with preparation of the plan, up to and including the Examination stage.
Use of consultants
7. The project already allows for the use of consultants to assist in the preparation of evidence base documents and other specialist tasks, by the provision of a budget for 2012/13 (£100,000). The majority of this budget is committed. We can expand the use of consultants to bring forward other evidence we would otherwise prepare in house. For example to manage the preparation of policies for strategic sites, including masterplanning work and the preparation of technical site studies. This will free up time to allow the policy team to make progress on other tasks in the project.
Appointment of a Project Manager
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.