2014 Leisure management contract

Decided Executive 2 papers

Cabinet decided this item on Thursday 11 April 2013. Below is the council's own wording, with the papers it was decided on.

Item72

Resolved

RESOLVED : to 1. jointly with South Oxfordshire District Council , commence the procurement of a leisure management contract under the competitive dialogue process; 2. set the evaluation weighting for the joint contract at 50 per cent price and 50 per cent quality.
Word for word from the decision Vale of White Horse published for this meeting. Source: democratic.whitehorsedc.gov.uk

Follow this further

Built from Vale of White Horse's papers

What the report saysPro

Report to Cabinet

Joint Cabinet report

Report of head of economy, leisure and property Author: Kate Arnold / Gemma Thynne Telephone: 01491 823091 (South) 01235 540416 (Vale) / 01235 540444 (Vale) Textphone: 18001 01491 823091 / 18001 01235 540416 / 18001 01235 540444 E-mail: [email protected] / [email protected] Wards affected: All Cabinet member responsible (South): Bill Service Cabinet member responsible (Vale): Elaine Ware Tel: 01235 510810 Tel: 01793 783026 E-mail: [email removed] E-mail: [email removed] To: CABINET To: CABINET DATE: 11 April 2013 DATE: 11 April 2013

2014 leisure management contract Recommendation Cabinet agrees: (a) jointly with South Oxfordshire District Council, to commence the procurement of a leisure management contract under the competitive dialogue process (b) to set the evaluation weighting for the joint contract at 50 per cent price and 50 per cent quality.

Purpose of report 1. The purpose of this report is to secure both cabinets agreement to the proposed approach for procuring a contractor to provide leisure management services on behalf of both councils from 1 September 2014.

1 Corporate objectives 2. The proposal to re-let the councils’ leisure management contracts as a joint contract will contribute towards the achievement of the following strategic objectives and corporate priorities: • strategic objective 1 – excellent delivery of key services; in particular the delivery of high performing services with particular emphasis on, amongst other things, ensuring good quality sports and leisure provision • strategic objective 2 – effective management of resources; in particular the councils continuing to work together to extend the sharing of services and resources, such as a shared client team and a single contract provider.

Background 3. Currently South has a single leisure management contract, whilst Vale has three. SOUTH • 2009-2014 contract with GLL for seven sites (including an outdoor pool) from which the council receives a management fee. VALE • 2002–2012 contract with DC Leisure for the management of the White Horse Leisure and Tennis Centre, which has been extended until 2014 to run coterminously with the other contracts. The Vale Council receives a management fee from the extension of this contract. • 2004-2014 contract with SOLL Leisure for the management of Faringdon and Wantage Leisure Centres and Tilsley Park. The Vale Council pays a management fee to the contractor for this contract. • 2011-2014 contract with SOLL for the management of Abbey Meadows Outdoor Pool. The Vale Council pays a management fee to the contractor for this contract, which is funded by Abingdon Town Council.

4. As all four contracts end on 31 August 2014, the councils have the opportunity to explore whether there are benefits from entering into a joint contract for the future management of their leisure facilities. At this early stage, separate contracts with different contractors will remain an option, although officers consider it unlikely that this will ultimately prove to be financially or operationally attractive.

5. Whichever route is taken, each site will be priced separately in the tender submissions, as some sites will generate a surplus, whilst others will generate a deficit. Not only will this enable us to ensure that the appropriate contract sums are apportioned to each council, it also provides us with the costs for individual sites if, at a later date, a decision is taken to remove one or more from the contract.

6. There will be a number of subsequent considerations in relation to this project, such as the length of the term of the contract and any arrangements for future contract extensions. These will be the subject of a further report, which will seek authority to agree the specification for the contract.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
2014 Leisure management contractReport 121 KB DownloadRead as text
PDF
Draft notes of briefing to joint Cabinet meeting 11 April 2013Report 34 KB Download

At this meeting

Whole meeting
722014 Leisure management contractThis decision

Who was there

13 of 16 attended
KA
Kate ArnoldOfficer, present
MB
Councillor Matthew BarberChair, apologies
SB
Steve BishopOfficer, present
DB
David BuckleOfficer, present
YC
Councillor Yvonne ConstanceCommittee Member, apologies
RC
Councillor Roger CoxVice-Chair, present
KF
Kathy FianderOfficer, present
JH
Councillor Jim HallidayGuest, present
MM
Councillor Michael MurrayCommittee Member, apologies
MP
Matt ProsserOfficer, present
MR
Margaret ReedOfficer, present
JR
Councillor Judy RobertsGuest, present

All 16 on the meeting page

On this subject at Vale of White Horse

Search all
  1. 2014 Leisure management contractThis decision
  2. 2014 Leisure Management ContractDecided

More from Vale of White Horse Cabinet

All decisions
MeetingDecisionOutcome
3 Jul 2026 MinutesThe minutes of the Cabinet meeting on 5 June 2026 were agreed as a correct record and the chair would sign them as such. Agreed Open
3 Jul 2026 Business Rates – Local Discretionary Relief scheme for 2026/2027That Cabinet (a) Approves the introduction of a local discretionary relief scheme, providing further relief for eligi... Approved Open
3 Jul 2026 At the Heart of the Vale: Annual Delivery Plan End of Year Report 2025-26That cabinet approves the Annual Delivery Plan End of Year Report 2025-26. Approved Open
3 Jul 2026 Thames Valley Spatial Development Strategy (SDS) Development and GovernanceThat Cabinet: · Notes the establishment of a partnership with the councils covering Oxfordshire, Berkshire and Swindo... Decided Open
3 Jul 2026 Revised Land and Property Asset Disposal PolicyRESOLVED : That Cabinet (a) Approves the revised Joint Property Asset Disposal policy. (b) Approves the revised Joint... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies