Resolved
RESOLVED : to (a) note the external auditor’s progress report; and (b) request the strategic director to consider consulting on the public’s comprehension of council financial information.
Audit and Governance Committee noted this item on Monday 24 June 2013. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED : to (a) note the external auditor’s progress report; and (b) request the strategic director to consider consulting on the public’s comprehension of council financial information.
Vale of White Horse District Council Year ending 31 March 2013
Audit Progress Report
June 2013 Councillor Simon Howell- Chairman Audit & Governance Committee Vale of White Horse District Council Abbey House Abingdon, Oxon OX14 3JE 14 June 2013
Dear Councillor Howell
Audit Progress Report - 2012/13
We are pleased to attach our Audit Progress Report.
This Progress Report summarises the work we have undertaken to date since our appointment as your auditor on 1 September 2012. The purpose of this report is to provide the Audit Committee with an overview of the stage we have reached in your 2012/13 audit and ensure our audit is aligned with the Committee’s service expectations.
Our audit will be undertaken in accordance with the requirements of the Audit Commission Act 1998, the Code of Audit Practice, the Audit Commission Standing Guidance, auditing standards and other professional requirements.
We issued our Audit Plan to the Audit & Governance Committee on 20 March 2013. Since then we have completed our walkthroughs and started our tests of control and have continued to update our risk assessment. There are no new issues that we are required to communicate to you as a result of this work.
We welcome the opportunity to discuss this report with you as well as understand whether there are other matters which you consider may influence our audit.
Yours faithfully
Maria Grindley Director For and behalf of Ernst & Young LLP Enc
Ernst & Young i Contents 1. Work completed .......................................................................................................... 2 2. Timetable..................................................................................................................... 3 Appendix 1: Audit Progress ............................................................................................... 4
Ernst & Young i Work completed
1. Work completed Meetings We have met with members of the senior management team and key members of staff as part of our ongoing audit process:
March 2013 - Meeting with Strategic Director & Chief Finance Officer and Head of Finance to discuss engagement team, audit plan and our audit approach.
Jan 2012 -Feb 2012 - meetings with key finance staff to discuss and significant issues/risks around the accounts preparation process.
Meeting with the Chief Executive and Strategic Director & Chief Finance Officer on 9 May 2013 to discuss issues facing the Council, and to update them on progress with the audit.
Completion of walkthroughs and tests of control We have completed our walkthroughs and some test of control, placing reliance on the work of internal audit where possible.
At this stage, our work has not identified any issues that we need to bring to your attention as those charged with governance.
Value for money assessment We are in the process of reviewing our initial risk assessment for our value for money work against the Audit Commission’s specified criteria and areas of focus. Once we have completed our risk assessment we will communicate to you any specific risks we have identified and any additional local risk based work we may need to undertake as a result.
Grant claim certification We have not yet started any work on the certification of your claims. We plan to start the audit of your housing benefit claim in September 2013 and your NNDR claim in August 2013
Additional work
The audit plan discussed with you on 20 March 2013 identified two possible areas of additional work to support our opinion.
Introduction of new fixed asset system; and
Adjustments to fixed asset values, and entries in the asset register
Officers have confirmed that the new fixed asset system will not be introduced for the 2012/13 accounts, and this is no longer required.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
External auditor's reportReport | 51 KB | DownloadRead as text |
Follow Audit and Governance Committee at Vale of White Horse and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 19 Mar 2015 | Actions arisingRESOLVED : to retain the following items on the actions arising list: · To call the Building Control manager to a fut... | Decided | Open |
| 19 Mar 2015 | Internal audit management report quarter four 2014/15RESOLVED : to note the internal audit management report for the fourth quarter 2014/15. | Noted | Open |
| 19 Mar 2015 | Internal audit plan 2015/16RESOLVED : to approve the internal audit plan 2015/16. | Approved | Open |
| 22 Jan 2015 | Minutesto defer the approval of the minutes of the meeting held on 24 September 2014 as a correct record and to agree that t... | Deferred | Open |
| 22 Jan 2015 | Actions arisingto retain the amended procedure for monitoring systemic control weaknesses on the actions arising list for one more m... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.