Resolved
RESOLVED : to note the internal audit management report for the second quarter 2014/15.
Audit and Governance Committee noted this item on Wednesday 24 September 2014. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED : to note the internal audit management report for the second quarter 2014/15.
1. The purpose of this report is:
• to report on management issues within internal audit;
• to summarise the progress against the 2014/2015 audit plan up to 15 September 2014; and
• to summarise the priorities for quarter three 2014/2015.
2. The contact officer for this report is Adrianna Partridge, Audit Manager for South Oxfordshire District Council and Vale of White Horse District Council, telephone (SODC) 01491 823544 and (VWHDC) 01235 547615.
Strategic objectives
3. Managing our business effectively. Background
4. The CIPFA Code of Practice for Internal Audit in Local Government in the UK 2006 states that the head of internal audit should prepare a risk-based audit plan, which should outline the assignments to be carried out and the broad resources required to deliver the plan.
5. The CIPFA Code also states that the audit committee should approve the annual internal audit plan and monitor progress against the plan. This Committee approved the annual internal audit plan on 17 March 2014.
Management issues
6. Nilesh Parmar, auditor left the council on the 29 August. The recruitment process for a replacement has commenced, and interviews will be held on the 22 and 23 September. In the interim, Craig Pullen will be returning to undertake a number of key financial system audits.
Progress against the 2014/2015 audit plan
7. Progress against the approved audit plan has been calculated for the quarter and year to date and is summarised in appendix 1 attached.
8. Performance figures to date are as follows:
Target YTD Q1 Q2 Q3 Q4 13/14 13/14 13/14 13/14 Chargeable 74% 75% 72% 77.5% (identifiable client and/or specific IA deliverable) Non-Chargeable 8% 7% 7% 6.5% (corporate, not IA deliverable) Lost 18% 18% 21% 16% (i.e. leave, study, sickness)
9. As at 15 September 2014 the status of audit work against the 2014/2015 audit plan is as follows:
Planned
Strategic, operational and financial assurance work known and approved by the Audit and Governance Committee. In progress
commence 2014/2015
Complete Planned
Draft
To PLANNED 26 5 1 2 18 Joint 26 5 1 2 18
Adhoc
Unplanned project work based on agreed terms of reference with the audit manager (i.e. implementation of new systems) and responsive work issued and agreed by the section 151 officer, members or senior management team (i.e. investigations).
In progress
commence Requested
2014/2015 Complete
Draft
To ADHOC 1 1 0 0 0 Joint 1 1 0 0 0 SODC 0 0 0 0 0 VWHDC 0 0 0 0 0
Follow up
Work undertaken to ensure that agreed recommendations have been implemented. The number of follow-up audits is a rolling number, all internal audit reports are followed up after six months. In progress
commence Requested
2014/2015 Complete
Draft
To
FOLLOW-UP 27 15 0 0 12 SODC 13 7 0 0 6 VWHDC 14 8 0 0 6
Priorities for 2014/2015 quarter three (October 2014 – December 2014)
10. The priorities for quarter three are to:
• Successfully appoint to the auditor position. • Undertake a full review of the town and parish council initiative and make recommendations to the strategic management board. • Undertake a full review of the risk management and business continuity management arrangements and make recommendations to the strategic management board.
11. Remaining 2014/2015 planned audit work can be reviewed in appendix 2.
12. There are no financial implications attached to this report.
13. None.
14. Identification of risk is an integral part of all audits.
ADRIANNA PARTRIDGE AUDIT MANAGER
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Follow-up auditsAppendix 1 | 22 KB | Download |
PDF |
Planned auditsAppendix 1 | 31 KB | Download |
PDF |
Unplanned auditsAppendix 1 | 15 KB | Download |
PDF |
Audit plan schedule 2014-15Appendix 2 | 32 KB | Download |
PDF |
Internal Audit management report: second quarter 2014/15Report | 55 KB | DownloadRead as text |
Follow Audit and Governance Committee at Vale of White Horse and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 19 Mar 2015 | Actions arisingRESOLVED : to retain the following items on the actions arising list: · To call the Building Control manager to a fut... | Decided | Open |
| 19 Mar 2015 | Internal audit management report quarter four 2014/15RESOLVED : to note the internal audit management report for the fourth quarter 2014/15. | Noted | Open |
| 19 Mar 2015 | Internal audit plan 2015/16RESOLVED : to approve the internal audit plan 2015/16. | Approved | Open |
| 22 Jan 2015 | Minutesto defer the approval of the minutes of the meeting held on 24 September 2014 as a correct record and to agree that t... | Deferred | Open |
| 22 Jan 2015 | Actions arisingto retain the amended procedure for monitoring systemic control weaknesses on the actions arising list for one more m... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.