Agreed The committee agreed that the overall assessment for Dimension 1 should be Good . Dimension 2: Customer satisfaction The committee considered the report on Dimension 2. Agreed: The committee agreed that the overall assessment for Dimension 2 should be Good . Dimension 3: Council Satisfaction. Some responses to the council level of satisfaction with the contractor were “neither satisfied nor dissatisfied”. The committee was concerned to understand whether these were items for improvement, or whether the category should be changed to “not applicable”. Action: To change the heading to “not applicable” for future reports so that any response other than “satisfied” or “very satisfied” could be identified as an area for improvement. Areas for improvement: The six items outlined in the report were from the calendar year 2014. Since then, a new team had taken over the work and Biffa, and the officers, were confident that these matters would be improved. RESOLVED : to endorse the head of corporate strategy’s recommendation that the category of “Good” should be awarded to Biffa for their performance during 2014.
Word for word from the decision Vale of White Horse published for this meeting.Source: democratic.whitehorsedc.gov.uk
Report of Head of Corporate Strategy Author: Ian Matten Tel: 01235 540373 E-mail: [email protected] Vale Cabinet Member responsible: Elaine Ware South Cabinet Member responsible: Tony Harbour Tel: 01793 783026 Tel: 01235 810255 E-mail: [email protected] E-mail: [email protected] To: JOINT SCRUTINY COMMITTEE DATE: 30 July 2015
Performance review of Biffa Municipal Limited - 2014 RECOMMENDATION That the committee considers Biffa Municipal Limited’s (Biffa) performance in delivering the household waste collection, street cleansing and ancillary services contract for the period 1 January 2014 to 31 December 2014 and makes any comments to the Cabinet Members with responsibility for waste to enable them to make a final assessment on performance.
PURPOSE OF REPORT 1. The report considers the performance of Biffa in providing the household waste collection, street cleansing and ancillary services in South Oxfordshire and the Vale of White Horse for the period 1 January 2014 to 31 December 2014.
STRATEGIC OBJECTIVES 2. The service contributes to the council’s strategic objective of excellent delivery of key services with particular emphasis on achieving excellent levels of recycling, keeping streets and public spaces clean and attractive.
BACKGROUND 3. Managing contractor performance is essential for delivering the council’s objectives and targets. Since a high proportion of the council’s services are outsourced, the council cannot deliver high quality services to its residents unless its contractors are performing well. Using an agreed framework and working jointly with contractors to review performance regularly is therefore essential. 5-1 4. The council’s process for managing contractor performance focuses on continuous improvement and action planning. The council realises that the success of the framework depends on contractors and the council working together to set and review realistic, jointly agreed and measurable targets.
5. The overall framework is designed to be
a way for the council to consistently measure contractor performance, to help highlight and resolve operational issues
flexible enough to suit each contract, including smaller contracts which may not require all elements of the framework
a step towards managing risk more effectively and improving performance through action planning.
OVERVIEW OF THE REVIEW FRAMEWORK 6. Evaluating contractor performance has four elements:
1. performance measured against key performance targets (KPT) 2. customer satisfaction with the total service experience 3. council satisfaction as client 4. a summary of strengths and areas for improvement, feedback from the contractor on the overall assessment plus the contractor’s suggestions of ways in which the council might improve performance.
7. The first three dimensions are assessed and the head of service makes a judgement of classification. The fourth element is a summary of strengths and areas for improvement and includes contractor feedback. Where some dimensions are not relevant, or difficult to apply fairly to certain types of contract, the framework may be adjusted or simplified at the discretion of the head of service.
8. Biffa were awarded the joint waste contract in December 2008 with a commencement date in South Oxfordshire of June 2009. The Vale of White Horse element of the contract commenced in October 2010. The council in 2013 decided, in accordance with the conditions of contract to extend the contract for a seven year period. The contract is now due to end in June 2024.
9. The current value of the contract, as a fixed annual charge is £9,650,920 per annum of which the Vale of White Horse proportion is £4,449,442 per annum and South Oxfordshire is £5,201,478 per annum.
10. The contract includes delivery of the following services:
weekly collection of household food waste from 23 litre bins
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.