CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Vale of White Horse District Council
Planning Committee, Wednesday 23 August 2017 at 6.30pm

The Bungalow, Townsend, Grove

Approved Planning 4 papers

Planning Committee approved this item on Wednesday 23 August 2017. Below is the council's own wording, with the papers it was decided on.

Item49

Resolved

RESOLVED : To grant reserved matters consent for application P17/ V0134/RM subject to the following conditions: Standard conditions 1. Approved plans. Prior to commencement 2. Details of hard and soft landscaping and boundary treatment to be submitted. 3. Arboricultural method statement including tree protection plan to be submitted. 4. External materials details. Prior to occupation 5. Existing vehicular access to be stopped up. 6. Parking in front of bin store to be prevented – details to be submitted. Compliance 7. Parking and manoeuvring areas retained in accordance with approved plan. 8. Vision splays retained in accordance with approved plan. 9. Landscaping to be implemented and maintained for five years.
Word for word from the decision Vale of White Horse published for this meeting. Source: democratic.whitehorsedc.gov.uk

Follow this further

Built from Vale of White Horse's papers

What the report saysPro

Report to Planning Committee

Vale of White Horse District Council – Planning Committee – 23 August 2017

APPLICATION NO. P17/V0134/RM SITE The Bungalow Townsend Grove WANTAGE, OX12 0AZ PARISH GROVE PROPOSAL Reserved matters application following outline planning permission P16/V0527/O WARD MEMBER(S) Ben Mabbett Chris McCarthy APPLICANT D Pink Investments Ltd. OFFICER Martin Deans

RECOMMENDATION That reserved matters consent is granted subject to the following conditions:

Standard 1. Approved plans.

Prior to commencement 2. Details of hard and soft landscaping and boundary treatment to be submitted. 3. Arboricultural method statement including tree protection plan to be submitted. 4. External materials details.

Prior to occupation 5. Existing vehicular access to be stopped up. 6. Parking in front of bin store to be prevented – details to be submitted.

Compliance 7. Parking and manoeuvring areas retained in accordance with approved plan. 8. Vision splays retained in accordance with approved plan. 9. Landscaping to be implemented and maintained for five years.

1.0INTRODUCTION AND PROPOSAL 1.1 This application was presented to committee on 12 June 2017. Following concerns expressed about the design of the proposal, members resolved to defer the application pending a site visit. The previous committee report and minute of the meeting is attached at appendix 1. Vale of White Horse District Council – Planning Committee – 23 August 2017

1.2Following comments made at committee the applicants made the following changes to the design of the proposal.

 The balconies on the right side of the building removed and those on the left side changed to a glass panel design  The roof pitch on the three storey gables reduced to 45 degrees  The roof pitch on the three storey wing reduced to 35 degrees  The external treatment on the two storey wing changed from brick to render

Officers then presented the application to the architect’s advisory panel on 5 July 2017. The applicants have submitted further revisions to the design of the proposal following the architect’s panel. The revised plans are attached as appendix 2.

2.0SUMMARY OF CONSULTATIONS & REPRESENTATIONS 2.1 A summary of consultations and representations is contained in the previous committee report in appendix 1. The comments of the architects’ advisory panel are given below.

Architects’ Panel “Overall scheme and principles are acceptable. Good potential with the architectural treatment but rear elevations require further embellishment and visual interest (consider Juliet balconies). Concern about extent of amenity space, looks inadequate. Review design of the bin store/cycle store – consider flat roof with green roof covering as part of an enhanced landscape design. Consider projecting bay in south- west corner which appears to clash/crash into the building.”

3.0ENVIRONMENTAL IMPACT ASSESSMENT 3.1 See the previous report in appendix 1.

4.0MAIN ISSUES 4.1 The assessment of the main issues are as set out in the report in appendix 1. An update on the design issues is presented below.

4.2Design and Layout The architects’ panel considered that the scale and massing of the proposal were acceptable in its context. They had concern about some of the details, namely the rear elevations, the design of the cycle/bin store, which they considered could be designed with a green roof, and reducing the height of the corner projecting bay by one storey. They also had concern about the amount of amenity space, which will be considered below. However they had no objection to the use of balconies. In response the applicants have submitted amended plans with Juliet balconies added to the rear elevation, as suggested by the panel. The applicants consider the cycle/bin store to be more suitable with its original pitched roof, and argue that the corner bay should not be Vale of White Horse District Council – Planning Committee – 23 August 2017

reduced in height because, to either side of it, the eaves of the proposed building intersect at different levels.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
East, south and north elevations 198-P5DAppendix 2 2.2 MB Download
PDF
Elevations West and south-west Proposed drwgno 198-P4 rev CAppendix 2 2.2 MB Download
PDF
Appendix 1Appendix 1 882 KB Download
PDF
The Bungalow, Townsend, GroveReport 240 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

11 of 13 attended
MD
Martin DeansOfficer, in attendance
SD
Councillor Stuart DavenportCommittee Member, present
JH
Councillor Jenny HannabyCommittee Member, present
AH
Councillor Anthony HaywardCommittee Member, present
BJ
Councillor Bob JohnstonCommittee Member, present
SL
Councillor Sandy LovattChair, present
BM
Councillor Ben MabbettCommittee Member, present
CM
Councillor Chris McCarthyCommittee Member, absent
JS
Councillor Janet ShelleyVice-Chair, present
CW
Councillor Catherine WebberCommittee Member, present
SJ
Councillor St John DicksonCommittee Member, apologies, sent representative
RH
Councillor Robert HallCommittee Member, present

All 13 on the meeting page

On this subject at Vale of White Horse

Search all
  1. The Bungalow, Townsend, GroveThis decision
  2. P17/V0134/RM - The Bungalow, Townsend Grove, WantageDeferred
  3. P16/V0527/O - The Bungalow, Townsend, GroveApproved
  4. GRO/13271/5 - Demolition of existing bungalow and outbuildings. Erection of 7 dwellings, new vehicle access and access road. Willowdene, Townsend, Grove, OX12 0AZApproved
  5. GRO/13271/4 - Demolition of bungalow and garage. Erection of eight dwellings, associated works, landscaping, parking and new vehicular access. Willowdene, Townsend, GroveRefused

More from Vale of White Horse Planning Committee

All decisions
MeetingDecisionOutcome
16 Sep 2026 P24/V2434/HH - 4 Raleigh Park Road, North Hinksey, Oxford, OX2 9AZto approve planning application P24/V2434/HH subject to the conditions set out in the report. Approved Open
16 Sep 2026 P25/V2033/FUL - 1 The Green, Drayton, Abingdon, OX14 4JAto approve planning application P25/S2033/FUL subject to the conditions set out in the report and in the update provi... Approved Open
16 Sep 2026 P25/V1947/O - Signia Park, Land at former Didcot A Power Station, Purchas Road, Didcotto approve planning application P25/V1947/O subject to the conditions set out in the report. Approved Open
22 Jul 2026 Minutesto approve the minutes of the meeting held on 10 June 2026 as a correct record and agree that the Chair sign these as... Approved Open
22 Jul 2026 P26/V0815/HH - 42 Harding Way, Marcham, Abingdon, OX13 6FJto approve planning application P26/V0815/HH subject to the following conditions: 1. Commencement within three years ... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies