P16/V3097/FUL - 54 Hurst Rise Road, Cumnor Hill

Approved Planning 2 papers

Planning Committee approved this item on Wednesday 13 September 2017. Below is the council's own wording, with the papers it was decided on.

Item63

Resolved

to grant planning permission for application P16/V3097/FUL, subject to the following conditions: 1. Commencement three years - full planning permission. 2. Approved plans. 3. Samples of external materials. 4. Detailed tree protection measures. 5. Landscaping scheme and boundary treatments including details of what will be retain and improved and including ditch details. 6. Detailed drainage scheme for surface, foul and groundwater based on submitted strategy plan and supporting documents. 7. Details of screw piling method to be used. 8. Badger protection method statement. 9. Details of delivery times for construction/demolition traffic. 10. Details of wheel washing for construction/demolition traffic. 11. Access and vision splays to be provided as on plan. 12. Parking to be provided as on plan. 13. High level windows to be 1.7m cill height. 14. Landscaping and boundary treatments implemented as approved. 15. Routing of construction/delivery traffic shall be in accordance with section 3.2 of appendix G of the transport statement. 16. Use of banksman for construction traffic shall be in accordance with section 4.3 of appendix G of the transport statement. 17. Removal of permitted development rights for extensions and outbuildings.
Word for word from the decision Vale of White Horse published for this meeting. Source: democratic.whitehorsedc.gov.uk

Follow this further

Built from Vale of White Horse's papers

What the report saysPro

Report to Planning Committee

Appendix 1 `

Appeal Decisions Site visit made on 3 November 2015

by Kenneth Stone Bsc(Hons) DipTP MRTPI an Inspector appointed by the Secretary of State for Communities and Local Government

Decision date: 30 November 2015

Appeal A: APP/V3120/W/15/3119211 54 Hurst Rise Road, Oxford OX2 9HQ x The appeal is made under section 78 of the Town and Country Planning Act 1990 against a refusal to grant planning permission. x The appeal is made by Bouvard Group against the decision of Vale of White Horse District Council. x The application Ref P14/V1888/FUL, dated 15 August 2014, was refused by notice dated 23 December 2014. x The development proposed is described as ‘demolition of two existing dwellings and associated outbuildings, removal of concrete oversite. Creation of 7 dwellings with associated bin and bike stores. Alterations to existing dropped kerb’.

Appeal B: APP/V3120/W/15/3119212 54 Hurst Rise Road, Oxford OX2 9HQ x The appeal is made under section 78 of the Town and Country Planning Act 1990 against a refusal to grant planning permission. x The appeal is made by Bouvard Group against the decision of Vale of White Horse District Council. x The application Ref P14/V1887/FUL, dated 15 August 2014, was refused by notice dated 23 December 2014. x The development proposed is described as ‘demolition of two existing dwellings and associated outbuildings, removal of concrete oversite. Creation of 10 family dwellings with associated bin and bike stores. Alterations to existing dropped kerb’.

Decision

1. Appeal A is dismissed and Appeal B is dismissed.

Procedural matter

2. The address of the site in the application and appeal forms refers to it as 54 Hurst Rise Road. The site is made up of the plots of the existing properties of both 54 and 56 Hurst Rise Road.

Background and Main Issues

3. The Council accept that they cannot demonstrate sites sufficient for five years worth of housing against their housing requirements as they are advised to do in the National Planning Policy Framework (the Framework). Paragraph 49 of the Framework advises that housing applications, as this is, should be considered in the context of the presumption in favour of sustainable development and that relevant policies for the supply of housing should not be considered up to date if the Council cannot demonstrate a five year supply of deliverable housing sites. The presumption in favour of sustainable development is set out at paragraph 14 of the Framework and includes advice

www.planningportal.gov.uk/planninginspectorate Appeal Decisions APP/V3120/W/15/3119211, APP/V3120/W/15/3119212

that where relevant policies are out of date planning permission should be granted unless the adverse impact of doing so would significantly and demonstrably outweigh the benefits of the scheme. Given the need to boost significantly the supply of housing and that the site is located within the built up area of Botley, an area where new housing will be permitted subject to its impact on character and facilities important to the local community (policy H10 of the Vale of White Horse Local Plan 2011, July 2006 (LP)), there is strong support for the principle of developing the site for housing.

4. However, the presumption in favour of sustainable development seeks to achieve economic, social and environmental gains and positive improvements to the built and natural environment. I must therefore consider the detailed aspects of the proposals against these aims to determine whether the benefits of the development proposals would be significantly and demonstrably outweighed by any adverse impacts that may arise from granting permission such that the proposals would not amount to sustainable development.

5. Whilst the two appeals relate to two differing schemes the appeal site is consistent and the issues raised in the appeals are to a great extent similar. In order to avoid repetition I will address both appeals under each heading highlighting any differences where necessary.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
P16/V3097/FUL: 54 Hurst Rise Road, Cumnor Hill: AppendicesReport 8.5 MB DownloadRead as text
PDF
P16/V3097/FUL: 54 Hurst Rise Road, Cumnor HillReport 530 KB Download

At this meeting

Whole meeting

Who was there

13 of 16 attended
EH
Emily HamertonOfficer, present
MD
Martin DeansOfficer, present
SG
Sarah GreenOfficer, present
HB
Holly BatesOfficer, expected
NM
Nicola MeurerOfficer, present
SD
Councillor Stuart DavenportCommittee Member, present
JH
Councillor Jenny HannabyCommittee Member, present
AH
Councillor Anthony HaywardCommittee Member, present
BJ
Councillor Bob JohnstonCommittee Member, present
SL
Councillor Sandy LovattChair, present
BM
Councillor Ben MabbettCommittee Member, present
CM
Councillor Chris McCarthyCommittee Member, present

All 16 on the meeting page

On this subject at Vale of White Horse

Search all
  1. P16/V3097/FUL - 54 Hurst Rise Road, Cumnor HillThis decision
  2. P15/V0891/FUL - 81 Hurst Road, Botley, OX2 9HFDeferred
  3. 9 Thurston Close, Abingdon. P12/V1685/FULApproved

More from Vale of White Horse Planning Committee

All decisions
MeetingDecisionOutcome
16 Sep 2026 P24/V2434/HH - 4 Raleigh Park Road, North Hinksey, Oxford, OX2 9AZto approve planning application P24/V2434/HH subject to the conditions set out in the report. Approved Open
16 Sep 2026 P25/V2033/FUL - 1 The Green, Drayton, Abingdon, OX14 4JAto approve planning application P25/S2033/FUL subject to the conditions set out in the report and in the update provi... Approved Open
16 Sep 2026 P25/V1947/O - Signia Park, Land at former Didcot A Power Station, Purchas Road, Didcotto approve planning application P25/V1947/O subject to the conditions set out in the report. Approved Open
22 Jul 2026 Minutesto approve the minutes of the meeting held on 10 June 2026 as a correct record and agree that the Chair sign these as... Approved Open
22 Jul 2026 P26/V0815/HH - 42 Harding Way, Marcham, Abingdon, OX13 6FJto approve planning application P26/V0815/HH subject to the following conditions: 1. Commencement within three years ... Approved Open