Vale of White Horse District Council
Scrutiny Committee, Thursday 26 October 2017 at 7.00pm

Oxford to Cambridge Expressway: Vale options

Decided Scrutiny 4 papers

Scrutiny Committee decided this item on Thursday 26 October 2017. Below is the council's own wording, with the papers it was decided on.

ItemSc33

Resolved

to 1. Advise the leader of the council and officers that the committee considers Indicative Route 2 merits further attention insofar as, in the committee’s view, it is the least damaging potential option and has strategic housing and employment sites allocated along the route; and 2. Urges the Cabinet member and officers to request Government to consider ways in which the green belt and green open space might be preserved if and when a proposed route is identified.
Word for word from the decision Vale of White Horse published for this meeting. Source: democratic.whitehorsedc.gov.uk

Follow this further

Built from Vale of White Horse's papers

What the report saysPro

Report to Scrutiny Committee

Scrutiny Committee

Report of Head of Planning Author: James Gagg Telephone: [phone removed] E-mail: [email protected] Executive member responsible: Cllr Roger Cox Tel: 01367 243360 E-mail: [email protected] To: Vale Scrutiny Committee DATE: 26 October 2017

OXFORD TO CAMBRIDGE EXPRESSWAY: VALE OPTIONS

Recommendation That the committee consider the current evidence on Expressway options presented, and give their views or preferences on these proposals for further consideration by the Cabinet member and to help inform any further officer discussion with the NIC or Highways England.

Introduction 1. The purpose of this report is to give an update on the progress of the National Infrastructure Commission; Oxford to Cambridge Expressway (O2C) proposals, and ask scrutiny members for their view on the emerging potential routes in Oxfordshire.

2. It is suggested that any views are fed back to the Cabinet member to ensure they are taken account of in any further discussions with the National Infrastructure Commission (NIC) or Highways England (HE) on these proposals. Background and Outline of Process to Date 3. The Government asked the NIC for proposals and options to maximise the O2C corridor as a single, knowledge intensive cluster that is globally competitive while protecting the high-quality environment and securing much needed homes and jobs.

4. The Government has set aside £27m to fund the O2C Expressway Study, which is a 130 mile long corridor covering 3,900 square miles with a population of 3.3m people of which, approximately 1.83m are employed and contributes £90.5bn to the UK economy. It will connect the M4 to the M11, crossing the M1 and A1(M).

5. An outline of the NIC work to date is set out below in three sections:

Early development culminating in Stage 3 report; November 2016 6. Proposals for the Oxford to Cambridge expressway have been developing over the last three years, with the ‘strategic study’ being part of the Roads Investment strategy (2015-2020) published in November 2014 with the following key objective:

‘The strategic objective of the Oxford to Cambridge Expressway study is to investigate the case for linking existing roads and creating an Oxford to Cambridge Expressway, which would provide a high quality strategic east- west road link between Oxford and Cambridge via Bedford and Milton Keynes, improving connectivity, building network resilience and supporting economic growth’

7. The Expressway in this study is believed to mean a dual carriageway with limited access points and where junctions do exist they will be slip roads to allow free flow of traffic. The route could also be a corridor for other means of transport, such as electric vehicles. It is understood that the A34 would be upgraded from the M4 and continue into the Expressway.

8. The Stage 3 report on this study was published in November 2016 by the Department for Transport (DfT), which summarised the work undertaken in 2015/ 2016.1 The main conclusions from the study were the identification of potential core route options as follows:

A. a northern option, roughly following the existing A421 to the south of Bicester and via Buckingham to the east of Milton Keynes (Route A) B. a central option, following the east-west rail corridor (Route B); and C. a southern option via Aylesbury, linking to the M1 south of Milton Keynes (Route C)

1 https://www.gov.uk/government/publications/oxford-to-cambridge-expressway-strategic-

study-stage-3-report These routes are shown in the report on key schematic diagrams, Appendix 1 (two diagrams; 1. Wire diagram, 2. Arcs diagram).

9. The Stage 3 report focused on the strategic economic and transport case for expressway road improvements, and did not go into any detail on environmental or social impacts.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
plan 1-2017-08-30_Vale-potential NIC Expressway routes: illustrative: Constraints Aug 2017Appendix 3 1.6 MB Download
PDF
plan 2- 2017-08-30_Vale -potential NIC Expressway routes -illustrative LP sites Aug 2017Appendix 3 1.5 MB Download
PDF
2017-08-31-Matthew Barber ltr to Lord Adonis ExpresswayAppendix 3 97 KB Download
PDF
Oxford to Cambridge Expressway: Vale optionsReport 632 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 16 attended
DH
Councillor Debby HallettChair, present
AB
Councillor Alice BadcockVice-Chair, present
MB
Councillor Mike BadcockCommittee Member, present
EB
Councillor Edward BlagroveCommittee Member, present
VJ
Councillor Vicky JenkinsCommittee Member, apologies, sent representative
MK
Councillor Mohinder KainthCommittee Member, present
SL
Councillor Sandy LovattCommittee Member, present
CP
Councillor Chris PalmerCommittee Member, present
JR
Councillor Judy RobertsCommittee Member, present
BM
Councillor Ben MabbettSubstitute, in attendance
MB
Councillor Matthew BarberGuest, in attendance
RS
Ron SchrieberSecretary, expected

All 16 on the meeting page

On this subject at Vale of White Horse

Search all
  1. Oxford to Cambridge Expressway: Vale optionsThis decision
  2. Appointment of representative to the Oxford to Cambridge Pan-Regional PartnershipDecided
  3. Oxford to Cambridge Arc UpdateAgreed
  4. Oxford to Cambridge Arc UpdateNoted
  5. Oxford to Cambridge Arc UpdateNoted
  6. Oxford to Cambridge Arc UpdateNoted

More from Vale of White Horse Scrutiny Committee

All decisions
MeetingDecisionOutcome
14 Sep 2026 Minutes of the last meetingThe minutes of the meeting held on 8 June 2026 were approved as a correct record and the chair would sign them as such. Approved Open
8 Jun 2026 Minutes of the last meetingThe minutes of the meeting held on 23 March 2026 were agreed as a correct record, and the chair will sign them as such. Agreed Open
23 Mar 2026 Minutes of the last meetingThe minutes of the meeting held on 2 February 2026 were agreed as a correct record, and the chair would sign them as ... Agreed Open
2 Feb 2026 Minutes of the last meetingThe minutes of the meeting held on 3 November 2025 were agreed as a correct record, and the chair would sign them as ... Agreed Open
3 Nov 2025 Minutes of the last meetingResolved : The minutes of the meeting on 29 September 2025 were agreed as a correct record, and the chair would sign ... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies