Scrutiny recognises that some areas of internal performance delivered through the five councils’ contract fall below the excellent standards the council expects. It notes that the excellent work by staff has ensured that there has been no significant impact on public services. Scrutiny welcomes the work by Cabinet and senior officers to ensure improved performance and requests a detailed update on remedial actions being put in place to be presented to Scrutiny, covering the areas minuted , at the earliest opportunity.
Word for word from the decision Vale of White Horse published for this meeting.Source: democratic.whitehorsedc.gov.uk
Report of Head of Partnership and Insight and Head of Corporate Services Author: Andrew Down / Adrianna Partridge Telephone: 01235 422300 / 01235 422485 Textphone: 18001 01235 422300 / 18001 01235 422485 E-mail: [email protected] / [email protected] Cabinet member responsible: Roger Cox Tel: 01367 243360 E-mail: [email protected] To: Scrutiny committee DATE: 9 July 2018
Capita performance: HR, payroll and IT Recommendation That Scrutiny Committee members note the contents of the report and make any recommendations arising to the relevant cabinet members
Purpose of Report 1. The purpose of this report is to provide an update on the performance of the council’s contractor, Capita, in the delivery of the HR, payroll and IT services. Current risks and issues are identified, as well as the steps which officers are taking.
Partnership vision 2. As stated in the overarching service delivery plan, Capita’s overarching partnership vision is to support the councils by:
supporting the achievement of each council’s corporate targets
improving the satisfaction of customers and service users
improving the productivity of the councils’ staff
delivering improved value for money
achieving high levels of resilience and compliance. 3. There are no formal measures associated with the points above, as the performance indicators for each element of the contract should contribute to the overall goals. When considering the performance of the services discussed in this report, officers have considered the extent to which the above vision is achieved in practice.
Transformation and milestones 4. The contract with Capita is for the delivery of a range of services. Services were transferred to Capita on the service commencement date, which for the Vale was 1 August 2016 for all services. At that date, the services continued to be operated in the same way and by the same staff as before the transfer.
5. The contract includes for each service a series of milestone dates. These are assigned to the key points in the process of transforming the service from the model in operation at service commencement date to the new way of working put forward by Capita and agreed by the councils in the contract. The new way of working is known as the target operating model, or TOM.
6. For each service, TOM can include changes of systems, team structures, location of operating premises and methods of customer interaction. For most services, TOM includes some assumptions of a move towards greater self-service by councillors, council employees and residents, with an increased use of online interactions (“channel shift”).
7. During the period of transformation activity, the key performance indicators (KPIs) and performance indicators (PIs) which are used to monitor the contractor’s performance are not enforced. Contractual monitoring of KPIs and PIs begins on the commencement date identified by officer acceptance of TOM.
Contract management 8. In the period before formal adoption of KPIs and PIs, council officers monitor the contractor’s performance by other means during the time of transformation activity. To date, much of this monitoring has taken place within the joint client team, consisting of employees of all of the councils in the Five Councils Partnership. Recently, the five councils have taken a decision to direct Capita’s delivery and performance in line with their own delivery needs, and therefore the joint client team is now reducing in size. It was envisaged at the outset that the joint client team would reduce after the first two years of the contract.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.