Cabinet, Friday 2 August 2019 at 10.30am

Funding agreement - flood risk in Abingdon

Agreed Executive 1 paper

Cabinet agreed this item on Friday 2 August 2019. Below is the council's own wording, with the papers it was decided on.

Item14

Resolved

RESOLVED to: (a) make a payment of £68,075 and provide limited assistance in kind to the Environment Agency as a contribution towards the cost of appraisal and outline design work for the flood storage area and natural flood management opportunities in the catchment of the River Ock in Abingdon; and (b) authorise the head of legal and democratic, in consultation with the deputy chief executive - partnership and planning, to finalise the terms of and enter into an agreement with the Environment Agency as to the terms on which the contribution is to be made, the assistance in kind given, and the terms on which the Environment Agency is to provide reports to the council following completion of the work.
Word for word from the decision Vale of White Horse published for this meeting. Source: democratic.whitehorsedc.gov.uk

Follow this further

Built from Vale of White Horse's papers

What the report saysPro

Report to Cabinet

Cabinet Report Report of Acting Deputy Chief Executive – Partnership and Planning Author: Andrew Down Telephone: 01235 422300 E-mail: [email protected] Wards affected: Abingdon Caldecott, Abingdon Fitzharris, Marcham Cabinet member responsible: Judy Roberts Tel: 01865 864041 E-mail: [email protected] To: CABINET Date: 2 August 2019

Funding agreement re flood risk in Abingdon Recommendations (a) To make a payment of £68,075 and provide limited assistance in kind to the Environment Agency (EA) as a contribution towards the cost of appraisal and outline design work for the flood storage area and natural flood management (NFM) opportunities in the catchment of the River Ock.

(b) To authorise the Head of Legal and Democratic in consultation with the Deputy Chief Executive - Partnership and Planning to finalise the terms of and enter into an agreement with the EA as to the terms on which the contribution is to be made; the assistance in kind given, and the terms on which EA is to provide reports to the Council following completion of the work.

Purpose of Report 1. The purpose of this report is to provide Cabinet with a summary of the background and work to date on the flood management schemes of Abingdon, to inform a decision about future Vale of White Horse contributions to the project and to agree a delegation of authority to the Head of Legal and Democratic Services to enter into an agreement with the EA that determines the agreed level of contribution to the project and the conditions surrounding our involvement.

2. The EA also provided a briefing for councillors on Monday 15 July 2019. Corporate Objectives 3. The Vale of White Horse Corporate Plan 2016-2020 sets out the strategic objectives “Providing funding towards works on temporary flood barriers in South Hinksey and for the investigations of options to manage flood risks at sites in Abingdon, including Hillview Road on the River Stert; St Helen’s Mill on the River Ock, and a more comprehensive scheme for the River Ock, as well as the major Oxford and Abingdon Flood Alleviation Scheme.”

4. Additionally, the Vale has a corporate priority and commitment to “working with infrastructure partners to find solutions to flooding problems across the district.”

Background 5. Abingdon lies to the west of the River Thames, at the confluence of the Rivers Ock and Stert.

6. In 2007, extensive flooding (a 1 in 200-year event) from the Ock led to 433 residential properties and 21 commercial properties flooding.

7. Following further widespread flooding in 2013-14 (a 1 in 20-year event), proposals to reduce flood risk in Abingdon and Oxford were reviewed.

8. Vale of White Horse District Council made an early commitment of up to £2.5 million to reduce flood risk in Abingdon by means of a number of potential schemes, one of which was the creation of a flood storage area upstream of the A34. The initial draw down of this contribution was used to re-establish the Abingdon River Ock scheme in 2014 to investigate a flood storage area on the River Ock upstream of the A34 at Abingdon, alongside a package of other measures, jointly known as the ‘Abingdon Flood Schemes’.

9. In October 2016, a Memorandum of Understanding in respects of the Oxford and Abingdon Flood Alleviation Schemes was signed between:  The Environment Agency  Oxfordshire County Council  Oxford City Council  Vale of White Horse District Council  Thames Regional Flood and Coastal Committee  Thames Water Utilities Ltd  Oxfordshire Local Enterprise Partnership  Oxford Flood Alliance.

10. While this Memorandum primarily focusses upon the much larger Oxford Flood Alleviation Project, it does mention that the Environment Agency is looking at solutions in Abingdon for the River Ock. It states that these proposals could be delivered within the next few years following additional feasibility work and subject to the necessary funding being in place.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Funding agreement: flood risk in AbingdonReport 151 KB DownloadRead as text

At this meeting

Whole meeting
13North Wessex Downs Area of Outstanding Natural Beauty Management Plan 2019-2024Approved
14Funding agreement - flood risk in AbingdonThis decision

Who was there

13 of 16 attended
ES
Councillor Emily SmithChair, apologies
DH
Councillor Debby HallettVice-Chair, present
AC
Councillor Andrew CrawfordCommittee Member, apologies
NF
Councillor Neil FawcettCommittee Member, present
JH
Councillor Jenny HannabyCommittee Member, present
RM
Councillor Ruth MolyneauxCommittee Member, present
HP
Councillor Helen PighillsCommittee Member, apologies
JR
Councillor Judy RobertsCommittee Member, present
BT
Councillor Bethia ThomasCommittee Member, present
CW
Councillor Catherine WebberCommittee Member, present
SC
Steve CullifordOfficer, present
AD
Andrew DownOfficer, present

All 16 on the meeting page

More from Vale of White Horse Cabinet

All decisions
MeetingDecisionOutcome
3 Jul 2026 MinutesThe minutes of the Cabinet meeting on 5 June 2026 were agreed as a correct record and the chair would sign them as such. Agreed Open
3 Jul 2026 Business Rates – Local Discretionary Relief scheme for 2026/2027That Cabinet (a) Approves the introduction of a local discretionary relief scheme, providing further relief for eligi... Approved Open
3 Jul 2026 At the Heart of the Vale: Annual Delivery Plan End of Year Report 2025-26That cabinet approves the Annual Delivery Plan End of Year Report 2025-26. Approved Open
3 Jul 2026 Thames Valley Spatial Development Strategy (SDS) Development and GovernanceThat Cabinet: · Notes the establishment of a partnership with the councils covering Oxfordshire, Berkshire and Swindo... Decided Open
3 Jul 2026 Revised Land and Property Asset Disposal PolicyRESOLVED : That Cabinet (a) Approves the revised Joint Property Asset Disposal policy. (b) Approves the revised Joint... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies